  • Registered Users Posts: 7,838 ✭✭✭munchkin_utd


    marno21 wrote: »
    There won't be any announcement about an early opening until they can open it.

    There's no point in saying now - a year before any possible date - that they'll open it early in case they encounter any issues
    a staged opening also would mean that they can connect to the old road at some point, and open intermediate section of new road in stages, but isnt most of it well offline from the old road meaning theres very little chance of opening it in stages ?


  • Registered Users Posts: 4,322 ✭✭✭m17


    a staged opening also would mean that they can connect to the old road at some point, and open intermediate section of new road in stages, but isnt most of it well offline from the old road meaning theres very little chance of opening it in stages ?

    They could open tuam to kilternan and then kilternan to gort


  • Registered Users Posts: 4,322 ✭✭✭m17


    The m17 at cloonkleen north pic 1 28/11/15 pic 2 03/08/16


  • Registered Users Posts: 4,322 ✭✭✭m17


    The m18 going over the galway to Dublin railway line pic2 the m17/m18 flyover at rathmorrisy 08/08/16


  • Posts: 0 [Deleted User]


    Whatever about an early opening, there won't be a staged opening IMHO.

    As far as I can see, there's no good reason for the contractors to do so. Completion bonuses only apply for a full finished project.

    Opening part of it ahead of time is of no benefit and would be a headache more than anything else


  • Advertisement
  • Registered Users Posts: 966 ✭✭✭medoc


    m17 wrote: »
    The m17 at cloonkleen north pic 1 28/11/15 pic 2 03/08/16


    Savage progress. Taking shape now.


  • Registered Users Posts: 4,322 ✭✭✭m17


    The m18 at coldwood pic1 and 2 top of the flyover pic3 looking towards gort pic4 looking towards rathmorrisy 09/08/16


  • Registered Users Posts: 4,322 ✭✭✭m17


    There are still saying that there will be no phased openings new newsletter q3http://www.directroutegorttotuam.ie/newsletter.aspx


  • Registered Users Posts: 4,322 ✭✭✭m17


    Beam lift in progress over the m18


  • Registered Users Posts: 4,322 ✭✭✭m17


    The m17 rathmorrisy to tuam part one 09/08/16 flyover opening date's in brackets pic1 castle Lambert (07/07/16) looking towards rathmorrisy pic2 looking towards tuam pic3 carthymore (05/04/16) looking towards rathmorrisy pic4 looking towards tuam


  • Advertisement
  • Registered Users Posts: 4,322 ✭✭✭m17


    Part two Sheeaunpark (04/11/16) pic1 looking towards rathmorrisy pic2 looking towards tuam pic3 kilskengh (09/09/16) looking towards rathmorrisy pic4 looking towards tuam


  • Registered Users Posts: 4,322 ✭✭✭m17


    Part three laraghmore (18/05/16) pic1 looking towards rathmorrisy pic2 looking towards tuam pic3 annagh hill (27/04/16) looking towards rathmorrisy pic4 looking towards tuam


  • Registered Users Posts: 4,322 ✭✭✭m17


    Part four brockagh ( 08/03/16) pic1 looking towards rathmorrisy pic2 looking towards tuam pic3 ballinphuil (20/12/15 ) looking towards rathmorrisy pic4 looking towards tuam


  • Registered Users Posts: 4,322 ✭✭✭m17


    Part five cloontooa (29/10/16) pic1 looking towards rathmorrisy pic2 looking towards tuam pic3 kileelaun (10/10/16) looking towards rathmorrisy pic4 looking towards tuam


  • Registered Users Posts: 112 ✭✭Baldilocks


    Quick question, the total route length for this stretch (the Gort-Tuam project) is 53km, and they have some of the tarmac in place. But how many kilometres are currently layed?


  • Registered Users Posts: 4,322 ✭✭✭m17


    http://connachttribune.ie/gort-to-tuam-motorway-earthworks-near-completion-111/thanks for that bad report the flyover at coldwood is not open for another 2 months,this motorway will open in November 17 and that pic of rathmorrisy is 5 weeks old where the crane is that beam lift is done


  • Registered Users Posts: 4,675 ✭✭✭serfboard


    m17 wrote: »
    http://connachttribune.ie/gort-to-tuam-motorway-earthworks-near-completion-111/thanks for that bad report the flyover at coldwood is not open for another 2 months,this motorway will open in November 17 and that pic of rathmorrisy is 5 weeks old where the crane is that beam lift is done
    The report is simply a summary of what's in the latest newsletter, and since you posted the link, we've already read it!


  • Registered Users Posts: 4,675 ✭✭✭serfboard


    m17 wrote: »
    pic3 kileelaun (10/10/16) looking towards rathmorrisy pic4 looking towards tuam
    Thanks again for all the photos. In this case, though, I think you've got the labels the wrong way around. It looks like pic3 is towards Tuam and pic4 is looking south.


  • Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,345 Mod ✭✭✭✭marno21


    serfboard wrote: »
    The report is simply a summary of what's in the latest newsletter, and since you posted the link, we've already read it!
    Yep, this is the DirectRoute newsletter simply rehashed for newspaper print.

    The DirectRoute newsletter was likely out of date when it was published, simply due to the size and pace of the project.


  • Registered Users Posts: 4,322 ✭✭✭m17


    marno21 wrote: »
    Yep, this is the DirectRoute newsletter simply rehashed for newspaper print.

    The DirectRoute newsletter was likely out of date when it was published, simply due to the size and pace of the project.

    Thank god we a have boards


  • Advertisement
  • Registered Users Posts: 6,048 ✭✭✭Truckermal


    m17 wrote: »
    Thank god we a have boards

    Or more importantly you!!!!


  • Registered Users Posts: 4,322 ✭✭✭m17


    The dunkellin river bridge on the m18 07/07/16


  • Registered Users Posts: 4,322 ✭✭✭m17


    Truckermal wrote: »
    Or more importantly you!!!!

    Just keeping this great forum alive


  • Registered Users Posts: 4,322 ✭✭✭m17


    The rock cut at corofin


  • Registered Users Posts: 4,322 ✭✭✭m17


    Brockagh corofin pic1 07/06/15 pic2 07/08/16


  • Registered Users Posts: 4,322 ✭✭✭m17


    The m17 3kms form tuam pic1 25/02/15 pic2 15/07/16


  • Registered Users Posts: 4,322 ✭✭✭m17


    Bauilphuil corofin pic1 08/05/15 pic2 08/08/16


  • Registered Users Posts: 4,322 ✭✭✭m17


    The m17 6kms form tuam where the jersey barrier ends,through the bog just click on the link 14/08/16https://goo.gl/photos/XAHjjennS8hznG2N7


  • Banned (with Prison Access) Posts: 1,142 ✭✭✭Middle Man


    m17 wrote: »
    The m17 6kms form tuam where the jersey barrier ends,through the bog just click on the link 14/08/16https://goo.gl/photos/XAHjjennS8hznG2N7
    As always, great job by M17! :)


  • Advertisement
  • Registered Users Posts: 4,322 ✭✭✭m17


    The townland of cloontooa 3kms form tuam 14/08/16 pic1 top of the flyover pic2 looking towards rathmorrisy pic3 looking towards tuam the have layed another 1 km of the jersey barrier that is 6.5kms in total