Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

M21 - Limerick to Rathkeale/Foynes [advance works to commence shortly]

1131416181922

Comments

  • Registered Users, Registered Users 2 Posts: 1,754 ✭✭✭KrisW1001


    Given the length of road involved, it really won’t make much difference whether M21 is present or absent - if your commute involves Adare now, it would still be disrupted by the event. But it lasts around a week, so it’s not the end of the world.

    But, that said, the stretch from the Croagh junction (actually on the Limerick side of the village) up to the existing M21 looks like the most likely candidate for the first section in a phased opening.


    To save searching back through the thread, here are the drawings that were submitted to ABP back in 2019.

    FINAL DESIGN UPDATE - NOVEMBER 2018 | foyneslimerick



  • Registered Users, Registered Users 2 Posts: 797 ✭✭✭mydiscworld


    Am I correct in saying this will be fully funded by the EU so there won't be any issue if the winning tender price is very high with current construction costs?

    After such a long delay, you'd hope they have the tender application/specs ready to go, bar any amendments required from ABP approval conditions...



  • Registered Users Posts: 468 ✭✭Limerick74


    Minimal EU funding potentially available for design work on this project as it involves an EU TEN-T corridor. The construction element will be funded by the exchequer.



  • Registered Users Posts: 1,318 ✭✭✭pigtown


    Adare was lovely in the sunshine at the weekend and this road will be such a huge improvement.


    Do you think that the proposal would be much different if the design team had to consider active travel and rail too like they did for the M20? It might have been a handy way of extending the greenway from Rathkeale at least



  • Registered Users, Registered Users 2 Posts: 7,040 ✭✭✭Pete_Cavan


    The best solution for active travel back at design stage and now is utilising the existing N21 between Rathkeale and Adare, imo. Most of the existing road is wide enough that it can accommodate two narrower driving lanes and walking/cycle lanes, plus a bit of separation between them. The traffic volumes on what will be the "old road" will be low, making it more pleasant that a route beside the motorway. The rail line is already there, and looks like it could reopen anyway, so that is not a consideration.

    East of Adare, probably best to wait for the active travel proposal for the N/M20 project and tie into that.



  • Advertisement
  • Registered Users Posts: 830 ✭✭✭DumbBrunette


    ABP docs here, not sure if posted already:




  • Posts: 0 [Deleted User]


    Realistically, how long until construction starts? I'm guessing a long process of tendering, selecting bids etc..



  • Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,460 Mod ✭✭✭✭marno21


    I should add to my earlier comments on the 2027 date, the Ryder Cup provides a rare opportunity to use a future event to catalyse the development of a scheme like this. While the M21 should not be built for the Ryder Cup (it’s not), it does provide a reason for there to be justified impetus placed on its delivery. Most road schemes are a case of “yera it’ll be built when it’s built” so having something to publicly justify its acceleration, however merited that is, is an asset.

    Ryder Cup aside, the 16km of motorway from Patrickswell to Rathkeale should be prioritised without question. The existing route here is a national embarrassment.



  • Registered Users, Registered Users 2 Posts: 1,754 ✭✭✭KrisW1001


    It’s an odd argument, though, when the improvements will provide almost no benefit to the event organisers or visitors. I take your point about international events spurring development of infrastructure, but surely in that case M20 would be the critical project, not M21. This road would have a bigger impact on patrons of the competition, given that it is the road that everyone arriving at Cork Airport will be forced to use to reach the venue. I have heard nobody make a case that M20 is important to get working because of the Ryder Cup being staged in Ireland, but we keep hearing about how “essential” M21 is for the staging of this event, when in reality it will contribute to just 3 km of the route taken by well over 90% of those attending.

    Honestly, I think it’s just a lazy word-association between “Adare” in the two phrases “Ryder Cup 2027 at Adare Manor” and “M21 Adare Bypass”.



  • Moderators, Sports Moderators Posts: 12,189 Mod ✭✭✭✭Cookiemunster


    It's not that odd. Vitrually the same argument was used back in the early 00s to get the N7 widening done and opened before the 2006 Ryder Cup at the K Club.

    I doubt many will be arriving via Cork Airport though. DUB and SNN are the ones with the trans Atlantic connections.



  • Advertisement
  • Registered Users, Registered Users 2 Posts: 19,474 ✭✭✭✭road_high


    That’s great news- now get on with building the damn thing



  • Registered Users, Registered Users 2 Posts: 1,754 ✭✭✭KrisW1001



    I mentioned M20 mainly to highlight how illogical this “Need to have a motorway open for golf tournament to happen” argument is.

    The N7 widening argument was also a bit of a red-herring, given that M4 is how most visitors arriving in Ireland would have got to that year’s venue. Okay, some people would have been arriving at other airports and travelling up, but even then, they would have left the works site almost immediately, at N7 J7.

    Basically, the only rational argument for “need to have it done before {some big event}” is if people attending that event need that infrastructure to get to or from the venue. That wasn’t true of N7, it’s really not true of M21, and the only major road that comes close to that description is N20, but the idea of needing to upgrade N20 simply because a big golf match is happening in Adare sounds pretty stupid… because it is, and that was the point I was making.



  • Moderators, Science, Health & Environment Moderators Posts: 5,144 Mod ✭✭✭✭spacetweek


    This is such great and unexpected news! When exactly was this scheme submitted for PP?



  • Registered Users, Registered Users 2 Posts: 1,754 ✭✭✭KrisW1001


    Lodged in December 2019. Final submissions were done by December 2020.



  • Registered Users Posts: 146 ✭✭Mrs Dempsey


    As someone who has no interest in golf, I'm looking down the other end of your telescope. What do I see? I see me not being gummed up in Adare (or an adjacent rat run) during a large golf event (or indeed at any time. IMHO this welcome project is for the likes of me & not for the golf fans



  • Registered Users, Registered Users 2 Posts: 14,863 ✭✭✭✭markodaly


    So almost 2 years stuck in planning.... Not a great turnaround to be honest. Stuff like this should be done in 6 months max.



  • Registered Users Posts: 2,056 ✭✭✭awaywithyou


    bypassing Adare is great unfortunately it just moves the backlog down the road to newcastle west.... and then abbeyfeale... our american friends who will holed up in Killarney for the ryder cup wont be amused by having castleisland bypassed.. then bottleneck x 2 before arriving in bypassed Adare..

    on ryder cup.. im sure it will be of benefit to have non-golf traffic kept away from Adare village while event is going on.. and ryder cup isnt just 2 days.. there will be huge organising work going on for weeks and months before event tees off....



  • Moderators, Sports Moderators Posts: 12,189 Mod ✭✭✭✭Cookiemunster




  • Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,460 Mod ✭✭✭✭marno21


    They’re of such a size that they should move through the motions quite quickly and have a decent chance of progressing in the medium term.

    They’re also short and remove traffic from choked towns which allows them to curry favour with the incumbent anti-road Minister.



  • Moderators, Science, Health & Environment Moderators Posts: 5,144 Mod ✭✭✭✭spacetweek


    Agreed. Roads in open countryside taking total of nearly 3 years to get a decision.

    I shudder to think how long Metrolink in Dublin will be awaiting its decision.



  • Advertisement
  • Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,460 Mod ✭✭✭✭marno21


    To be fair, there was a lot of uncertainty in 2020 when the project was supposed to commence its oral hearing. It doesn’t excuse all of the delays but it does explain several months of delays.

    ABP will be very busy with infrastructure with the DART extensions, MetroLink and BusConnects infrastructure all heading their way at the minute. Luckily for them roads projects have slowed to a crawl since 2020.



  • Registered Users, Registered Users 2 Posts: 736 ✭✭✭Cushtie


    Delighted this has been given the green light. From what I remember the money for this was coming from EU and ring fenced so hopefully they can crack on and get the next stages started asap.



  • Moderators, Sports Moderators Posts: 12,189 Mod ✭✭✭✭Cookiemunster


    'Some' money comes from the EU. The vast majority is funded by the State. It is part of the Core TEN-T network so the EU want it open by 2030.



  • Registered Users Posts: 2,056 ✭✭✭awaywithyou


    Abbeyfeale maybe as its a good bit south of the town.... but newcastle west will be a diff story... there will be many objections/submissions etc...

    it is great to have an event like the Ryder cup to focus the minds on getting this project done... only for it... there would be no rush by the Dublin crowd... i can remember very well the widening of the naas road and the general improvements made in and around Straffan for Ryder cup in 06... teams of men working flat out and surprise surprise it was done in time... and was absolutely worth the time and money spent on it..



  • Registered Users, Registered Users 2 Posts: 1,754 ✭✭✭KrisW1001


    Improvements around Straffan, maybe, but the N7 had nothing to do with the Ryder Cup. No extra effort was put in to finish it “on time” - it was always scheduled to be done in 2006, and any desire to get it open earlier was down to minimising disruption on the State’s busiest stretch of road - it’s not even on the way to Straffan unless you’re lost.

    This idea that stuff will only gets done because some event is on is nonsense. One-off events have zero impact on any decision-making regarding what gets built and when. If a road not being there means it takes an extra hour to reach an event that lasts only six days and won’t ever return to the town, then that’s just fine - the road is being built for the people who will be using it day in, day out, not some one-off international travelling circus.



  • Registered Users, Registered Users 2 Posts: 5,963 ✭✭✭Chris_5339762


    The N7 improvements were not for the Ryder Cup, I don't think... simply because Newlands wasn't done at the same time (why they improved the N7 and left Newlands seperate is beyond me to this day).

    But maybe it was sped up a bit to make the nice new road finished, and not a construction site.

    Anyway, M21. Glad this got approved... hopefully they can get moving on this a little bit now.



  • Registered Users Posts: 14 nearlybroke


    Does anybody know the next three steps and timeframe for this road?



  • Moderators, Science, Health & Environment Moderators Posts: 5,144 Mod ✭✭✭✭spacetweek


    I suppose tender is next. The Gov put out an investment brochure recently talking about all their big infrastructure plans and this scheme was pencilled in for starting in 2025.



  • Registered Users, Registered Users 2 Posts: 7,040 ✭✭✭Pete_Cavan


    First steps will be to complete the CPOs and then get going with advanced works. Tender docs can be prepared in the bacbackground but could be a while before we see the tender issued.



  • Advertisement
  • Registered Users Posts: 239 ✭✭specialbyte


    First they need to wait 4 weeks to get the final ABP order. ABP have announced their decision but they need to wait 4 weeks before issuing the final board order that legally confirms the CPOs and planning permission are approved. The delay is to allow someone to ask the High Court to judicially review the legality of the decision from ABP. That's the next hurdle. Then processing the CPOs and tendering for advanced works (fencing, clearance, archaeology, etc.) then tender for the actual design and build contract.



  • Registered Users Posts: 468 ✭✭Limerick74


    High Court Judicial Review period is 8 weeks from the ABP decision or advertisement of same (whatever is later).



  • Registered Users Posts: 239 ✭✭specialbyte


    You're dead right. Don't know why I said it was 4 weeks. I'm certainly praying for a quiet an uneventful few weeks with no trips to the High Court.



  • Moderators, Sports Moderators Posts: 12,189 Mod ✭✭✭✭Cookiemunster


    Well there has been nothing negative in the local media since the decision was announced, so fingers crossed.



  • Advertisement
  • Registered Users, Registered Users 2 Posts: 1,620 ✭✭✭Hibernicis


    Very frustrating. It will be very interesting to see who is behind this and what the grounds are.



  • Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,460 Mod ✭✭✭✭marno21


    I’ve been waiting for this ever since the Galway Ring Road debacle a few weeks back.

    Either disgruntled landowners or the greenies is my bet. Planning reform cannot come quick enough



  • Registered Users, Registered Users 2 Posts: 7,633 ✭✭✭prunudo


    Ireland is grinding to a halt, there needs to be a major change in how everything is done here because red tape, snail pace administration and clerical work is crippling buisness and day to day life.


    And its not just roads, every government department (probably bar revenue :) ) is hugely inefficient and needlessly drags out even the simplest of interactions.


    I understand the right of people to object but after a glaical abp review we now have the prospect of a much needed infrastructure project being tied up for years in the courts. Its not right and very frustrating.

    Post edited by prunudo on


  • Registered Users, Registered Users 2 Posts: 796 ✭✭✭MICKEYG


    There must be some bar a claimant has to meet to get a judicial review. Hopefully it is not just filling out a form.

    Seeing as the project is approved, maybe progress can continue on tendering etc. While this is underway?



  • Registered Users, Registered Users 2 Posts: 574 ✭✭✭Aontachtoir


    This news is unsurprising, and I have predicted multiple times in this thread that it would occur. I don’t understand why some people thought it wouldn’t. There doesn’t need to be a sustained loud public campaign against a road when anyone, anywhere in the country, can torpedo it with a judicial review.

    Because they have become so easy to access, JRs are now de facto a part of the planning process. This has coincided with the rise of an extreme strand of environmentalism, which views construction of almost any new road infrastructure as heresy (or even illegal, as was claimed in Donnchadh Woulfe’s article yesterday in the Irish Times), and a Climate Act which grants them even more tools to stop development. Even the most ragtag group of activists can effortlessly stall a road for years, against the wishes of the local community.

    We have known about this problem for a long time and nobody has done anything about it. The solutions are the same: slashing access to JRs and introducing mandatory decision deadlines. A new step will be to amend the Climate Act to specifically exclude designated key national infrastructure from its provisions.

    Until that point, no new significant infrastructure will be delivered in this country.

    My understanding is that the only bar is that you need to have been involved in some way earlier in the process, even tangentially. Of course, there is no bar to that, so, for all intents and purposes, anyone anywhere in the country is able to launch a judicial review.

    Edit: As the JR process typically grinds on for years, with appeal after appeal after appeal, I doubt they will make much headway on tendering. Open to correction on that.



  • Advertisement
  • Registered Users, Registered Users 2 Posts: 5,963 ✭✭✭Chris_5339762


    Look to the M28 for the timeline of judicial reviews. High court, appeal to Supreme Court, Supreme Court generally won't be going near it. I don't think it'll stop the road, but it will delay it.



  • Registered Users, Registered Users 2 Posts: 855 ✭✭✭corm500


    This country is a joke.



  • Registered Users, Registered Users 2 Posts: 3,241 ✭✭✭hans aus dtschl


    I think some of what you suggest is slightly dangerous because some undeserving things seem to slip into the "strategic infrastructure" bracket since they brought it in. I've seen some wholly private power generation projects getting put through as "strategic" for instance. I'm definitely in favour of the decision deadlines though, I think that's badly needed. And reduced access to JR's too seems to make sense to me.

    Despite all the "tools" etc at the disposal of environmentalists to completely stop or delay projects, there still aren't a lot of good tools to enforce good roads design. Things like the current iteration of Shannonpark Roundabout in Carrigaline, or the Tivoli dual carriageway realignment etc: these projects shouldn't be getting approved and I have no idea how they're passing safety audits. So I definitely don't like the idea of allowing roads to progress through planning as "strategic" as there's just too many basic mistakes as it is.



  • Registered Users, Registered Users 2 Posts: 1,754 ✭✭✭KrisW1001


    Have you ever filed an objection to a project? Sometimes, the reason can simply be that nobody raised the issue...



  • Registered Users, Registered Users 2 Posts: 3,241 ✭✭✭hans aus dtschl


    Absolutely. I've had them ignore my submissions (in writing) before being slapped down by the regulator, NTA or politicians. They'll also hilariously often try and "ghost" you, if you point to the relevant standards: they'll communicate plenty if they think you know nothing, fobbing you off about how designs meet all the standards, and they go silent if you point out the relevant standards!

    The process is really bad. Like surprisingly bad. You would think that professionals would appreciate you flagging basic mistakes, but it's like they consider it an insult to their profession or something. I can only assume there's a bad culture in Irish road engineering: it wouldn't fly in the industries I work in - people get rewarded for pointing out mistakes.

    And as a recent example in terms of approvals, no matter what side of the Galway ring road you're on, most people will agree that it's actually astounding that it was approved, but that they didn't subsequently attempt to defend it's approval. Whatever you think of the grounds for the objection (whether you think it's right or wrong) it was really well known at the time ABP were "reviewing" it and approving it. It wasn't some vague fine-print text clause on a document, it was something that was regularly being discussed and debated in public. And the project was approved without even attempting to deal with the issue.

    So yes, I would have fears about putting roads through as strategic infrastructure for that reason. We need to improve the process definitely so that projects progress way faster, but I think pushing roads through planning with the good old ABP as our expert eyes and ears would possibly be a step in the wrong direction!



  • Registered Users Posts: 540 ✭✭✭Limerick91


    How long will this delay the project by, months/years??



  • Registered Users, Registered Users 2 Posts: 7,040 ✭✭✭Pete_Cavan


    Depends. If it reaches the High Court then likely two years, maybe more or even indefinitely if those takingtheJR are successful. They could be thrown out or withdrawn before getting there, it which case it would be months.



  • Moderators, Science, Health & Environment Moderators Posts: 5,144 Mod ✭✭✭✭spacetweek


    This project isn't due to commence until 2025, which is ample time for JRs to be dealt with.



  • Registered Users, Registered Users 2 Posts: 7,040 ✭✭✭Pete_Cavan


    But advanced works need to be completed first, not sure if they can proceed with a JR is progress.



  • Registered Users Posts: 14 nearlybroke


    What’s the latest on this road it seems a certain hotel has lodged an objection



  • Advertisement
Advertisement