Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie

Cork developments

Options
1146147149151152301

Comments

  • Registered Users Posts: 1,778 ✭✭✭Mefistofelino


    Markcheese wrote: »
    I don't see how they can cock it up , it's a contractor,they've started ,the money's already allocated by central government ... Once the scrub and undergrowth is cleared ,and the rails ( which have a value ) are lifted ,the original ballast is still there , so either gravel blinding or tarmac on top ...
    Famous last words I know .....

    Much of the route is heavily overgrown and removing the tree & shrub roots is likely to significantly disturb the ballast. And I'd suspect most of the rails have gone - either legally or otherwise - precisely because they had a value.

    There's also the small matter of Eirgrid wanting to run the new HVDC interconnector cable along the route of the greenway, which will require the installation of some serious ductwork.


  • Registered Users Posts: 18,179 ✭✭✭✭namloc1980


    If I recall correctly about half the length of track between Midleton and Youghal was lifted in the 1990s for use on a track renewal job up in Sligo.


  • Registered Users Posts: 8,440 ✭✭✭Markcheese


    Eirgrid doing work on the route is at their cost I assume ( I hadn't realised that was happening). In a way it's a separate project ..( just hope they're coordinating)
    , clearing the scrub and trees over the length of the line is a big job ,but with the right equipment could be done seriously quickly and efficiently ,( saw a woodchipper on the mallow road 2plus1 improvements that was based on a sileage harvester , literally chewed up whole trees ...
    Probably need herbicide to keep the regrowth at Bay so you won't need to dig up the ballast ,
    But none of that is rocket science or unexpected .. it's been done on similar projects elsewhere ...
    You'd hope it's been tendered for correctly ...

    Slava ukraini 🇺🇦



  • Registered Users Posts: 4,547 ✭✭✭AugustusMinimus


    There isn’t a hope this will ever revert from being a Greenway to Rail use ever again. Whatever the decision is now is pretty much final.


  • Registered Users Posts: 18,179 ✭✭✭✭namloc1980


    There isn’t a hope this will ever revert from being a Greenway to Rail use ever again. Whatever the decision is now is pretty much final.

    Better off making a use of it. If it was being kept for rail then it would just sit there disused forever. Greenways are great facilities - see Waterford Greenway for example.


  • Advertisement
  • Registered Users Posts: 5,868 ✭✭✭Chris_5339762


    There are no plans, but would a reopening of the railway as far as Bandon ever be feasible? CPO a few houses and the alignment is mostly there. Send it under the Kinsale Road roundabout and take half of the South Link for the railway line and you're at the old location for the station just opposite the Elysian.

    Would this be a more sensible option than a long term plan to upgrade the N71?


  • Registered Users Posts: 18,179 ✭✭✭✭namloc1980


    There are no plans, but would a reopening of the railway as far as Bandon ever be feasible? CPO a few houses and the alignment is mostly there. Send it under the Kinsale Road roundabout and take half of the South Link for the railway line and you're at the old location for the station just opposite the Elysian.

    Would this be a more sensible option than a long term plan to upgrade the N71?

    Much of the alignment has been lost to agriculture / farmers ploughing it up and incorporating into their fields. And as nothing was done to challenge this over the last 60 years they now effectively own it. In any case the old alignment was poor, very twisty and not suitable for modern transport. Building a new alignment would be prohibitively expensive and is essentially a non-runner. Closing half the South link is also not feasible.


  • Registered Users Posts: 8,440 ✭✭✭Markcheese


    There are no plans, but would a reopening of the railway as far as Bandon ever be feasible? CPO a few houses and the alignment is mostly there. Send it under the Kinsale Road roundabout and take half of the South Link for the railway line and you're at the old location for the station just opposite the Elysian.

    Would this be a more sensible option than a long term plan to upgrade the N71?

    Honestly it'd be bonkers ... I'm for public transport , ahead of massive new road builds , but to shut the main road to bandon and shut half of the south link for a bandon ,inishannon and halfway ( and maybe a bit of bishopstown ) rail line , never mind the expense ,
    You'd cause riots ....

    Slava ukraini 🇺🇦



  • Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,373 Mod ✭✭✭✭marno21


    Comments on the Custom House Tower from reddit thread on the new North Main Street development:
    The odds, quite high actually! Planning is looking v good with some reasonable RFI's (Request for Further Information) in at the moment. I reckon all of these will be satisfied and planning granted within this year. The Sullivans are ready to go with the conntruction and they move fast, if their NYC projects are anything to go by!

    One thing that may hold the whole thing up is a geoligical survey. The "point" of the centre island of the city is essentially mud on top of mud. The last survey went 50m down and didn't find rock, thats why the tower moved from the point back to Custom House Street, with the hope that the rock will be shallower.

    One thing is for sure, these brothers mean business. They have tonnes of cash and are not afraid to fight! Nice guys but they get their way in the end. You might have seen from another post on here today that the Prism building will start construction this quarter - this is another one of their projects.

    Fantastic if true.


  • Registered Users Posts: 584 ✭✭✭BeansBeans


    Have you got a link to that thread handy? Please


  • Advertisement
  • Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,373 Mod ✭✭✭✭marno21


    BeansBeans wrote: »
    Have you got a link to that thread handy? Please

    Indeed I do

    https://www.reddit.com/r/cork/comments/ekly26/the_proposed_student_accomodation_on_north_main/


  • Registered Users Posts: 3,577 ✭✭✭snotboogie


    He's saying Railway Gardens will be built too, hmmm....


  • Registered Users Posts: 3,104 ✭✭✭hans aus dtschl


    There isn’t a hope this will ever revert from being a Greenway to Rail use ever again. Whatever the decision is now is pretty much final.

    I don't necessarily agree with you.

    For instance I could see potential rail expansion to Mogeely if there was a county UEA, with a big P&R.
    Take for example if an M25 gets funded, I'd prefer to see such an East Cork P&R. I don't think you can get a P&R into the Midleton station at this point, given the scale of housing and warehousing on the East of the town, and Midleton traffic is quite poor at peak times. So the only way to suck cars off the N25/M25 from what I can see would be Mogeely or thereabouts. Such a job could even push out the urgency of an M25 maybe?

    I think you can see where I'm going with this. Maybe I'm dreaming here, but it's roughly the same distance as the previous early-2000's line reopening (Glounthaune to Midleton). What would an M25 upgrade cost? It'd surely deserve consideration?


  • Registered Users Posts: 1,800 ✭✭✭Tomtom364


    marno21 wrote: »
    Comments on the Custom House Tower from reddit thread on the new North Main Street development:
    The Sullivans are ready to go with the conntruction and they move fast, if their NYC projects are anything to go by!
    Fantastic if true.


    Considering full planning was granted in May, they were talking about having the prism tender process completed last October and as of yet a contractor hasn't been appointed, I wouldn't exactly say they are moving all too fast.

    However they do seem to be moving, which is a lot more that a rake of other projects around the city so have to give them credit for following through.


  • Registered Users Posts: 3,577 ✭✭✭snotboogie


    Tomtom364 wrote: »
    Considering full planning was granted in May, they were talking about having the prism tender process completed last October and as of yet a contractor hasn't been appointed, I wouldn't exactly say they are moving all too fast.

    However they do seem to be moving, which is a lot more that a rake of other projects around the city so have to give them credit for following through.

    How long do you think it will be from a contractor being appointed to construction starting? I remember for the Crows Nest that it took nearly 12 months


  • Registered Users Posts: 6,538 ✭✭✭kub


    snotboogie wrote: »
    How long do you think it will be from a contractor being appointed to construction starting? I remember for the Crows Nest that it took nearly 12 months

    I wonder have we a time and money business decision here with the Sullivan brothers as opposed to UCC building an apartment block for their own students?


  • Registered Users Posts: 1,800 ✭✭✭Tomtom364


    snotboogie wrote: »
    How long do you think it will be from a contractor being appointed to construction starting? I remember for the Crows Nest that it took nearly 12 months

    If all parties are 100% good to go then its a month a least, id expect all things being ready, 1-3 months.

    But there could be some things that need working out after appointment that delay it, site investigation surveys throw up obstacles or any issues with the ESB Substation on the site for example.


  • Registered Users Posts: 6,814 ✭✭✭Pete_Cavan


    Tomtom364 wrote: »
    If all parties are 100% good to go then its a month a least, id expect all things being ready, 1-3 months.

    But there could be some things that need working out after appointment that delay it, site investigation surveys throw up obstacles or any issues with the ESB Substation on the site for example.

    Those things absolutely do not get agreed after appointing a contractor, that would be a blank cheque for the contractor. Site investigations have been done to allow for the design of foundations, there could be changes due to unforeseen conditions once excavation has started but the tender would have been based on a set design. If an ESB substation is required, or existing one extended, it would need planning permission so has already been considered. If there are any questions on these things, it would be very stupid for the client to enter into a contract without first agreeing how these things are dealt with.


  • Registered Users Posts: 1,800 ✭✭✭Tomtom364


    Pete_Cavan wrote: »
    Those things absolutely do not get agreed after appointing a contractor, that would be a blank cheque for the contractor. Site investigations have been done to allow for the design of foundations, there could be changes due to unforeseen conditions once excavation has started but the tender would have been based on a set design. If an ESB substation is required, or existing one extended, it would need planning permission so has already been considered. If there are any questions on these things, it would be very stupid for the client to enter into a contract without first agreeing how these things are dealt with.


    The ESB substation located on the site has to be replaced and relocated. It is currently on Ground level and therefore to construct a two level basement this provides complications. This station also provides capacity for a large chunk of the city therefore being offline long term isn't really an option.
    This has all been considered in the tender, however works commencing is reliant on the ESB being in a position to move forward with their side of the plans to address this.


    I was specifically replying to a query as to how long between appointment and start on site.
    I should have clarified that I was responding with a timescale for the the preferred tender being selected and letter of intent submitted, not contracts signed.


  • Registered Users Posts: 6,538 ✭✭✭kub


    Tomtom364 wrote: »
    The ESB substation located on the site has to be replaced and relocated. It is currently on Ground level and therefore to construct a two level basement this provides complications. This station also provides capacity for a large chunk of the city therefore being offline long term isn't really an option.
    This has all been considered in the tender, however works commencing is reliant on the ESB being in a position to move forward with their side of the plans to address this.


    I was specifically replying to a query as to how long between appointment and start on site.
    I should have clarified that I was responding with a timescale for the the preferred tender being selected and letter of intent submitted, not contracts signed.

    I imagine the ESB have the necessary expertise and experience to have everything done on the preparation side of things, have the cables ready and a sub station set up elsewhere before they disconnect the power in order to set up the sub station elsewhere.
    The down time will be minimal.


  • Advertisement
  • Registered Users Posts: 21,254 ✭✭✭✭Water John


    Might be of interest here. A car park in Norway burned two days ago, Opel Zafira may be the culprit.
    https://www.thelocal.no/20200108/norway-airport-flights-held-as-hundreds-of-cars-burn-in-fire


  • Registered Users Posts: 9,446 ✭✭✭TheChizler


    There's a public meeting in City Hall next Tuesday about the sustainable mobility policy, could be interesting to people who read this thread.

    https://www.eventbrite.ie/e/have-your-say-review-of-the-sustainable-mobility-policy-tickets-88635407891


  • Registered Users Posts: 14,255 ✭✭✭✭leahyl


    TheChizler wrote: »
    There's a public meeting in City Hall next Tuesday about the sustainable mobility policy, could be interesting to people who read this thread.

    https://www.eventbrite.ie/e/have-your-say-review-of-the-sustainable-mobility-policy-tickets-88635407891

    Was just about to share, got an email about it in work :)


  • Registered Users Posts: 4,988 ✭✭✭opus


    The apartments being built on Millard Street have almost topped out.

    499673.jpg

    Also noticed this development site for sale on the Coal Quay.

    499674.jpg


  • Registered Users Posts: 1,735 ✭✭✭AwaitYourReply


    Hotel and golf resort staff in limbo as resort owner fails to attend meeting in Cork

    Hotel workers who fear their jobs are at risk have been left in limbo after the complex owner failed to attend a meeting this morning to discuss the future of the business.

    The Armagh-based developer, who bought the Blarney Golf Resort north of Cork City just over two years ago, pulled out of this morning’s scheduled meeting with the staff just days after he ordered the immediate and indefinite closure of the resort’s leisure and gym complex.

    While the hotel was always due to close for January, staff were until last weekend operating under the assumption that it would reopen for business in February.

    But the sudden closure of the leisure centre and pool have raised fears for the future of the resort and the 80 jobs there. The golf course is operating as normal.

    However, rumours are swirling locally that the complex is being considered as a direct provision centre.

    The hotel staff were told last weekend to attend a briefing at the hotel this morning where they hoped the owner would explain what was happening.

    Source courtesy:
    https://www.irishexaminer.com/breakingnews/ireland/hotel-and-golf-resort-staff-in-limbo-as-resort-owner-fails-to-attend-meeting-in-cork-974689.html


  • Registered Users Posts: 3,669 ✭✭✭who_me


    Some good news (if it hasn't already been posted: )

    Over €9.2m has been allocated to Athletics Ireland / CIT, presumably for the indoor sports arena they were planning.

    €2m allocated for the Cork City training facility in Glanmire, though it seems to be on hold pending the FAI getting its act together.

    €1.5m for the indoor training facility at Irish Independent (/ Musgrave) Park.


  • Registered Users Posts: 4,988 ✭✭✭opus


    First time I came across a pic of what the finished student apartments on the Mardyke are going to look like.

    499846.jpg


  • Registered Users Posts: 68 ✭✭WhoElse


    We do joined up thinking as good as anywhere else. The problem is that nothing gets implemented for a myriad of reasons.

    Not being facetious, genuinely interested. What do you see as the main reasons? I don't knwo too much about local government or how it works/doesn't work! :D


  • Registered Users Posts: 18,179 ✭✭✭✭namloc1980


    .

    Councillors vote against housing shocker in support of local NIMBYs. Terry Shannon said the 38 apartments were an overdevelopment. The proposed site is adjacent to the possible future Luas line at the Blackrock greenway that the councillors celebrated when CMATS was launched! This city is screwed with these guys in charge. They have zero vision and can't look beyond the next election and as such spend their time placating locals for votes.


  • Advertisement
  • Registered Users Posts: 13,385 ✭✭✭✭D'Agger


    Cllr Shannon called for the council not to go against the City Development Plan, saying it was “unacceptable” to change zoning from sport to housing, and that he has never seen it happen before.

    “There is no point building communities on one hand, and destroying communities on the other hand,” he said.

    Well this is foolish thinking to say the least - it's never happened before, so it's unacceptable? How would this destroy the community? Traffic can be poor around Blackrock I get that but this isn't even specifically called out as an issue, speaking in broad strokes to garner votes from the locals who don't want this.
    Cllr Lorna Bogue said she was against the development, but warned that the proposal could be sent to An Bord Pleanala “and have a decision forced on us.”

    She also said she didn’t want to create a precedent for developers to be able to approach sports clubs in financial distress to buy land for developments.

    As opposed to the boom days where Mallow & Clonakilty had their sites bought off them with new, massive complexes built for them further away, outside of their towns. This has/is already going on. Blackrock hurling club in financial distress - my eye!


Advertisement