Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Help Keep Boards Alive. Support us by going ad free today. See here: https://subscriptions.boards.ie/.
If we do not hit our goal we will be forced to close the site.

Current status: https://keepboardsalive.com/

Annual subs are best for most impact. If you are still undecided on going Ad Free - you can also donate using the Paypal Donate option. All contribution helps. Thank you.

DART+ (DART Expansion)

1393394396398399408

Comments

  • Registered Users, Registered Users 2 Posts: 1,452 ✭✭✭Consonata


    Part of it is the depot surely being rejected. Hard to hit the ground running when one component which underpins 3 of the 4 Dart+ projects is reject.



  • Registered Users, Registered Users 2 Posts: 7,897 ✭✭✭Former Former Former




  • Registered Users, Registered Users 2 Posts: 1,487 ✭✭✭gjim


    Tendering is a non-trivial and generally expensive process and doing it wrong can prove fatal for a business particularly for the bidders.

    No engineering/construction company is going to go to the bother of dedicating staff and resources to do the required amount of research required to to produce accurate estimates for a project unless such a project is definitely going ahead and where the parameters and scope of the project are definite and clear.



  • Registered Users, Registered Users 2 Posts: 439 ✭✭PlatformNine


    Public consultation is a legal requirement of any railway order. In fact my understanding is two rounds of non-statutory(pre-ABP) public consultation is required in addition to statutory(in-ABP) public consultation. Any RO that doesn't follow would be rejected for not following legal procedure, and even if it somehow wasn't it would be a swift JR.

    Now whether the changes require an RO is a better question. The works you are referring to are for phase 1 (Bray-Wicklow) include other than track works and platform extensions, some OHLEs and a substation for charging, at least one LC closure, and potentially some modifications to bridges. The track works will be the most likely reason for an RO. As for phase 2(CC-Bray) that is a better question, pretty much the only significant works would be the LC closures and if the Cork line LC closures say anything, it is likely any modifications to the 6 LCs on will require an RO.



  • Registered Users, Registered Users 2 Posts: 254 ✭✭Bsharp


    The Wicklow Pre-Feasibility study was linked earlier in the discussion, looked like an RO could be avoided. Plenty of land to play with at Wicklow Station for charging infrastructure, substation, platform extensions and track work. The Wicklow Port Access Route got its part 8 to deliver lifts, stairs to both platforms, as well as improved access, parking and bus drop off.



  • Advertisement
  • Registered Users, Registered Users 2, Paid Member Posts: 15,866 ✭✭✭✭loyatemu


    Two rounds of public consultation to add a passing loop to an existing railway - I don't know the legal requirements but if that's the case, it's absurd. I'm also not sure what the general public can contribute to what's essentially an engineering plan.

    Put your money where yer mouth is... Subscribe and Save Boards!

    https://subscriptions.boards.ie/



  • Registered Users, Registered Users 2 Posts: 439 ✭✭PlatformNine


    The track works are a bit more complicated than that but yes potentially. I am not worried about the passing loops, however if it requries a CPO, I think it would require a RO? That said the works that would worry me are those between Bray and Bray head, as it would involve turning one of the sidings into a second track and may involve bridge work, and they may want to replace the lost sidings which could require a CPO as well.

    If it does requrie an RO, I wouldn't look at it as a problem of the planning system (although I won't deny the RO process could benifit from streamlining for these exact scenarios), but an odd case of a small project just happening to meet the criteria for an RO. It is a bit of a messy situation, again as for context, the Cork line LC closures really weren't that complicated but required a project, but needed an RO.

    Honestly I don't know the planning system all that well. But I do know it can be very messy at times, and overall seems to be designed more around larger projects (to an extent) than it is for smaller ones.



  • Registered Users, Registered Users 2 Posts: 202 ✭✭OisinCooke


    Is there any word on the DART depot…? Weren’t we supposed to hear something around this time?



  • Registered Users, Registered Users 2 Posts: 289 ✭✭scrabtom


    Hearing from someone inside Irish Rail that they still haven't fully decided on a new location yet.



  • Registered Users, Registered Users 2 Posts: 439 ✭✭PlatformNine


    Do we know what some of the potential locations are? From the space constraints alone (2.5km x 300m) I don't think there are that many possible locations?

    Also somewhat related to the depot, I still don't think we have heard any news on the third fleet order? I believe it was supposed to be placed last year but nothing has happened and I am not sure if it will even be placed this year.



  • Advertisement
  • Registered Users, Registered Users 2, Paid Member Posts: 19,035 ✭✭✭✭LXFlyer


    No the third tranche has yet to be approved by cabinet.



  • Registered Users, Registered Users 2 Posts: 4,426 ✭✭✭goingnowhere


    Third order has no depot dependency



  • Moderators, Education Moderators Posts: 26,411 Mod ✭✭✭✭Peregrine


    The new location is the old location with additional info to get it over the line.



  • Registered Users, Registered Users 2 Posts: 7,473 ✭✭✭Pete_Cavan


    They should scale back plans for the original location a bit and add stabling beside Hazelhatch and elsewhere. The issue is they are trying to do too much at one location.



  • Registered Users, Registered Users 2, Paid Member Posts: 1,317 ✭✭✭riddlinrussell


    I believe it was one specific 'corner' of the site that was at risk with regard to flooding, so you might be right, drop those facilities/rejig stabling to remove that section of the site entirely and move the facilities/additional stabling to Hazelhatch

    Boards is in danger of closing very soon, if it's yer thing, go here (use your boards.ie email!)

    👇️ 👇️



  • Registered Users, Registered Users 2 Posts: 1,494 ✭✭✭bikeman1


    Yes, that is correct it was "only" part of the site, but at a critical point to access the depot as a whole.

    The DART plus website ( https://www.dartplus.ie/en-ie/projects/dart-depot ) mentions the following:

    Why is the site previously refused by An Bord Pleanála included again?

    The Board’s decision did not preclude the previous site from any new site selection process but rather set out a process to be followed for any site that experiences flooding to be assessed. The Board’s decision set out an approach to be followed in any new site selection process and this approach is being followed.

    What other sites are being sites considered?

    The options assessment has considered the full extents of the DART network including the three DART+ Programme projects (DART+ Coastal, DART+ Southwest and DART+ West). The study area for this DART+ Depot site selection study was also extended to consider sites within 10km of the furthest extent of the previous DART+ projects.

    -

    So the original site can still be used. Maybe move it further away and complete the full flood risk assessments and have measures in place to deal with floods as per the Boards recommendations. For Irish Rail's credibility, they have to get this application and site perfect.



  • Registered Users, Registered Users 2 Posts: 7,897 ✭✭✭Former Former Former


    From that page

    The options assessment is underway and it is hoped to have identified a preferred site in Spring 2025.

    They've got three days of Spring left…



  • Moderators, Sports Moderators Posts: 13,059 Mod ✭✭✭✭Cookiemunster


    It says 'it is hoped'. Spring 2025 is neither a promise date nor a deadline.



  • Registered Users, Registered Users 2 Posts: 284 ✭✭Ronald Binge Redux


    They'd be more honest if they said, 'Ah sure, ya know yourself'. The lack of urgency of Offalcial Ireland on this project and others deserve a book to be written about them. A very big one.



  • Registered Users, Registered Users 2 Posts: 7,897 ✭✭✭Former Former Former


    I know, but every single date in the entire process has been missed and since everything (apparently) has to be done in strict sequence, delays become cumulative.

    A year to decide to resubmit the same location seems… long.

    There does not seem to be any urgency at all and precisely zero effort to recoup lost time.



  • Advertisement
  • Registered Users, Registered Users 2 Posts: 387 ✭✭Thunder87


    And zero accountability or need to explain the endless delays.

    On metrolink for example, does anyone know why the construction start date is now going to potentially be SEVEN YEARS behind schedule? I've never heard a single explanation or justification given for a one year delay never mind seven and any time a politician is pressed on it it's just the usual one paragraph soundbite that they're "committed to the project".

    Maybe there are legitimate reasons for a lot of it but the lack of scrutiny just feeds into this culture of deadlines and plans being completely meaningless



  • Registered Users, Registered Users 2 Posts: 2,779 ✭✭✭KrisW1001


    Metrolink start is expected in 2028. That is not "SEVEN YEARS" behind schedule. It's more like three. (Metro North is not Metrolink)

    Three years is still bad, so there's no need to inflate it and make your complaints look stupid.



  • Registered Users, Registered Users 2 Posts: 10,195 ✭✭✭✭cgcsb


    The opening year for metrolink was stated as 2027 at the project launch in 2018 so a 7 year delay seems accurate (or indeed conservative) now that they're saying completion is going to be after 2035. And that's not accounting for the JRs.



  • Registered Users, Registered Users 2 Posts: 309 ✭✭Qaanaaq


    Well it's quite obvious that the current lengthy planning approval process is the main cause of delay. So i guess that unless you can change the whole planning, consultation, review, revise, appeal, judicial review cycle etc, then the original estimated timelines didn't accurately reflect the reality of that real planning process.

    However if you were to put a realistic timeline in that reflects the real process, then you run the risk of taking the pressure off the project and it takes even longer !

    The planning cycle for something like this is way too long and needs to be changed but the project is a victim of it at present. The planning cycle also takes longer than a government cycle so this is a big negative from a political point of view.

    The only thing that can be done now is to try and keep pressure on as much as possible because objectors will use the void before anything is built to try and cast doubt on the viability. Which is what we see the likes of the Irish Times are doing.

    We need to get a shovel in the ground as quick as possible.



  • Registered Users, Registered Users 2 Posts: 387 ✭✭Thunder87


    Thanks for the advice, I'd suggest you apply the same to your reply 🙂

    Construction was supposed to start in 2021 and we've never had any reason given for why that didn't happen, just endless missed deadlines and radio silence. We did of course have the scrapping of the southern section which involved a (fairly minor in the grand scheme) redesign at Charlemont but which also should have concurrently freed up time and resources that halving the length of the project enabled.



  • Moderators, Science, Health & Environment Moderators Posts: 5,460 Mod ✭✭✭✭spacetweek


    The timeline was 2021 to 2027 for many years until Eamon Ryan became the minister for transport and made his famous statement that the timeline was never credible which was news to the public.
    I still haven’t got over the shock that a politician would have the balls to say that, openly rubbishing the idea that the public would believe a government timeline and making us all feel foolish.



  • Registered Users, Registered Users 2 Posts: 10,195 ✭✭✭✭cgcsb


    1000029351.jpg

    Well he was correct. And it's not something that the government has direct control over, the 6 month abp planning deliberation is 3 years now for this project and likely to face another 2 in JR.

    Meanwhile other EU countries that are signed up to the same planning rules and regulations as us just quickly, quietly and cheaply build out their metros. Copenhagen is adding a 5th metro line after some months of planning and Madrid is finally extending its line 5 to the airport for a mere €180mil for 1.7km. Roughly 10% of the metrolink costs on a per km basis.

    The only real solution is for the government to host a series of referrenda to radically alter the way our legal system works to bring it more in to line with developed countries.



  • Registered Users, Registered Users 2 Posts: 91 ✭✭PH0NER


    Everyone always says that the government isn’t directly responsible for delivering these projects, because so many review processes hold them up. Is there a reason the government can’t employ a team to directly interact with ABP and others to ensure progress is always being made and government pressure is there to speed things along? As of now, it seems like nothing gets done in reasonable time. The Dart+ expansions should be throwing up overhead power lines by now even if the depot hasn’t been sorted yet.

    What would it take to get the government to alter the legal system to be in line with other EU countries who seem to build public infrastructure exponentially faster?



  • Registered Users, Registered Users 2 Posts: 1,487 ✭✭✭gjim


    What would it take to get the government to alter the legal system to be in line with other EU countries

    Which country’s planning system do you have in mind?



  • Advertisement
  • Moderators, Science, Health & Environment Moderators Posts: 5,460 Mod ✭✭✭✭spacetweek


    ”What would it take to get the government to alter the legal system?”

    Unspeakably impossible.



Advertisement