Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

N5 - Westport to Turlough [open to traffic]

18911131429

Comments

  • Registered Users, Registered Users 2 Posts: 9,527 ✭✭✭irishgeo


    The breaffy road junction section has the old road removed already and trucks crossing the diverted section so beware of the crossing guards stepping out on the road to allow the trucks across.


  • Registered Users, Registered Users 2 Posts: 2,381 ✭✭✭Westernyelp


    First spans on the overbridge at the N84 junction going in at the moment


  • Registered Users Posts: 543 ✭✭✭yew_tree


    What sort of central divide will be on this dual carriageway? A single wired fence like the Tuam bypass or a double sided crash barrier which I believe they are going to install on the Castlebaldwin - Collooney type 2 dual ?


  • Registered Users, Registered Users 2 Posts: 1,753 ✭✭✭KrisW1001


    It should be a double-sided metal crash-barrier, as that's the new standard.


  • Registered Users, Registered Users 2 Posts: 1,951 ✭✭✭6541


    Hello,

    I have two questions regarding road construction. Both of which can be seen on the N5.

    Question 1. If you look at the areas where the new N5 crosses existing roads you will notice a patch of concrete. Why do they use concrete at these crossings ?


    Question 2. If you look at the road you will notice big square drains, this is a general new road question. Look at the infamous Balla road realignment you will see a big square mass of water. Look at the Tuam bypass again you will see big square pools of water. I notice they have two of them built at Breaffy intersection.
    Can anyone tell me the engineering principles here ?

    Thanks,
    6541


  • Registered Users, Registered Users 2 Posts: 9,527 ✭✭✭irishgeo


    6541 wrote: »
    Hello,

    I have two questions regarding road construction. Both of which can be seen on the N5.

    Question 1. If you look at the areas where the new N5 crosses existing roads you will notice a patch of concrete. Why do they use concrete at these crossings ?


    Question 2. If you look at the road you will notice big square drains, this is a general new road question. Look at the infamous Balla road realignment you will see a big square mass of water. Look at the Tuam bypass again you will see big square pools of water. I notice they have two of them built at Breaffy intersection.
    Can anyone tell me the engineering principles here ?

    Thanks,
    6541

    1. The big Volvo dump truck would have tarmac taken up in no time. The concrete is a stronger option for the crossing point.

    2. I'm no engineer but it's basically holding ponds for water run off.


  • Registered Users, Registered Users 2 Posts: 2,466 ✭✭✭mayo.mick


    Some dashcam footage of the N5 junction under construction at Turlough last Tuesday 23rd February.



  • Registered Users Posts: 829 ✭✭✭DumbBrunette




  • Advertisement
  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    New aerial shot of the GSJ on the Ballinrobe Road in Castlebar.

    547599.jpg

    Pic courtesy of Jack Walsh drone photography.


  • Registered Users Posts: 41 thomas385


    New drone video on YouTube from around the Derrylea roundabout to the Belcarra Road.

    (Can't post link as it says I am a new member, the YouTube channel name is "JayKay")


  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    That's a great video, thanks for sharing :) Here is the link:

    https://youtu.be/L3dJR87m7Tk

    thomas385 wrote: »
    New drone video on YouTube from around the Derrylea roundabout to the Belcarra Road.

    (Can't post link as it says I am a new member, the YouTube channel name is "JayKay")


  • Registered Users, Registered Users 2 Posts: 2,466 ✭✭✭mayo.mick


    thomas385 wrote: »
    New drone video on YouTube from around the Derrylea roundabout to the Belcarra Road.

    (Can't post link as it says I am a new member, the YouTube channel name is "JayKay")



  • Registered Users, Registered Users 2 Posts: 4,037 ✭✭✭Cosmo Kramer


    Great video, it's coming on really well. Didn't realise it went quite as close to the rugby pitch as that, there could be a few overhit conversions bouncing out onto the road at Cloondeash.

    Looking forward to spinning back to Westport on the dual carriageway with the sun setting in the background some evening in the not too distant future.


  • Registered Users Posts: 829 ✭✭✭DumbBrunette




  • Advertisement
  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    Bridge deck now in place on the Islandeady Road, looking west towards Westport and Croagh Patrick.

    549724.jpg

    Link https://m.facebook.com/Structive/photos/a.109636937518872/242183844264180/?type=3&source=48


  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    Very detailed maps of the entire project have appeared on the scheme website https://n5w2t.com/

    This is very welcome as these maps haven't been available online previously.


  • Registered Users Posts: 4,321 ✭✭✭m17


    On there way to castlebar 14/04/21
    VAqjdML.jpg


  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    Couple of quick updates on this scheme:

    1. The railway bridges on either side of Castlebar are well advanced with abutments and embankments in place. It appears to my untrained eye that the bridge decks could be installed at any time.

    2. Earthworks are well underway on the N59 section. There is a lot of machinery in the area and the outline of the realigned road is clearly visible, but a lot of digging is still needed in the Barleyhill/Slaugar area.

    3. New drone footage from the Turlough end of the scheme: https://www.instagram.com/tv/COGlUtQJGdR/?igshid=11wu4zuh0a999


  • Registered Users, Registered Users 2 Posts: 1,541 ✭✭✭Dudda


    Couple of quick updates on this scheme:

    1. The railway bridges on either side of Castlebar are well advanced with abutments and embankments in place. It appears to my untrained eye that the bridge decks could be installed at any time.
    Possibly something that will be done over the May Bank Holiday weekend. Irish Rail usually do their engineering works over long weekends and operate bus transfers.


  • Advertisement
  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    Google maps have updated their satellite imagery for most of the new N5 route. It looks like the images are only a few weeks old.

    There's a fantastic level of detail visible, well worth a look.


  • Registered Users, Registered Users 2 Posts: 1,386 ✭✭✭yannakis


    Google maps have updated their satellite imagery for most of the new N5 route. It looks like the images are only a few weeks old.

    There's a fantastic level of detail visible, well worth a look.

    Google Earth (desktop) says 2 Apr 2021 :)


  • Registered Users Posts: 375 ✭✭Reuben1210


    yannakis wrote: »
    Google Earth (desktop) says 2 Apr 2021 :)

    Where on google maps can you check dates the satellite images are taken?


  • Registered Users, Registered Users 2 Posts: 1,386 ✭✭✭yannakis


    Reuben1210 wrote: »
    Where on google maps can you check dates the satellite images are taken?

    That's the date of the images you see in Google Maps.

    Earth Desktop just indicates the dates, that's why I checked there. It also has more versions of images (sometimes newer ones than what's published in Maps).


  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    The Islandeady Road closure row has been resolved: https://www.con-telegraph.ie/2021/05/07/agreement-reached-on-temporary-closure-of-n5-access-to-west-mayo-community/

    The local residents did well, the original planned closure was 9 months.

    552616.jpeg


  • Registered Users Posts: 41 thomas385


    New drone video on YouTube from Kilbree into Westport



  • Moderators, Science, Health & Environment Moderators Posts: 5,144 Mod ✭✭✭✭spacetweek


    The last 30 sec shows very little progress around Westport.


  • Registered Users, Registered Users 2 Posts: 9,527 ✭✭✭irishgeo


    spacetweek wrote: »
    The last 30 sec shows very little progress around Westport.

    Only type 2 that and no bridges so I imagine it's probably going to be the last bit done. The priority is to get the bridges done first.


  • Registered Users, Registered Users 2 Posts: 10,207 ✭✭✭✭Oscar Bravo


    Massive progress around the Castlebar area. Different kind of road building than times gone by. very little mess etc. Ballyhaunis plant hire have 2 road sweepers flat out going from site to site keeping the place clean.


  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    Serious digging at the N60 junction in Castlebar today, courtesy of Jack Walsh drone photography.

    553073.jpg


    Link: https://m.facebook.com/2224058757921503/photos/a.2761274107533296/2910175265976512/?type=3&source=54&ref=page_internal


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 5,963 ✭✭✭Chris_5339762


    I know that it has to happen, but holy crap those two poor households.


  • Registered Users, Registered Users 2 Posts: 69,537 ✭✭✭✭L1011


    I would take a guess that they were offered CPO and declined.


  • Registered Users, Registered Users 2 Posts: 5,963 ✭✭✭Chris_5339762


    L1011 wrote: »
    I would take a guess that they were offered CPO and declined.


    They look like those Chinese Nail Houses.


    https://www.theguardian.com/cities/gallery/2014/apr/15/china-nail-houses-in-pictures-property-development


  • Registered Users, Registered Users 2 Posts: 4,037 ✭✭✭Cosmo Kramer


    I know that it has to happen, but holy crap those two poor households.

    Thankfully both houses were CPOd as per the post below.
    WBEngineer wrote: »
    The house on the far right was purchased in 2017 by its current occupants. Mayo CoCo agreed to CPO the property in August 2020 after some issues arose with the owners. They are still residing in the property.

    The property to its left was not originally meant to be CPO'd either. However, in 2016 Mayo CoCo changed its mind, altered the road plan and CPO'd the property after issues with the owners arose. Those occupants moved to a new build on the Westport Road in 2019.

    However, that house was then given by Mayo CoCo to the couple that lived in the sole property to be demolished (property once stood with the green portaloo is located). They were residing there while their new home was being built. They are in the process of vacating the property. This property was/is expected to become a site office for WillsBam.

    The house to the left of the demolished property (corner/garden visible in image) is occupied. That house is actually built on the sheet rock that is being broken/blasted and as such they are living in hell with noise and tremors echoing through the house from 7am to 7pm Monday to Friday. If you walk past that property you may be able to see the sound recorders installed in the rear garden by Mayo CoCo during working hours.

    Finally, the property to the left of that house but out of view in the drone image is temporary vacant. The occupants complained about the noise and Mayo CoCo has agreed to pay them to rent a property elsewhere until the project is completed.


  • Registered Users, Registered Users 2 Posts: 5,963 ✭✭✭Chris_5339762


    Thanks for the update. Awful situation, but sadly it must happen.


  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    I drove the full length of the scheme today- it was a beautiful day here and the contractor was hard at it at every location I visited. Huge amount of haulage traffic on the existing W-C road also. Here are some highlights, from west to east.

    1. Barleyhill bends: Earthworks are advancing apace, with much of the top of the hill beside the Slaugar road junction now removed.

    2. Lodge Road underbridge: Embankments are now being built up here to connect with the future underbridge.

    3. Sheeaun road overbridge: Huge progress here, the temporary road diversion is open and a concrete pour for the bridge pillars was underway when I passed. The embankments leading up to the new bridge are largely complete too.

    4. Derradda and Drumneen overbridges: The temporary diversions are open in both of these locations and digging out the future cuttings is continuing apace. The Drumneen cutting will be a monster, 30 metres from the top to road level.

    5. Islandeady Road overbridge: The bridge is complete, tie-in works will be carried out during a road closure in June.

    6. Lough Lannagh causeway: This has been built up and widened further since my last visit at Christmas, I presume it must be near its final level now.

    7. Castlebar west roundabout: Not much change here, but a lot of haulage traffic along the new road, with flagmen in place.

    8. Belcarra road overbridge and N60 overbridge: Temporary diversions open and the cuttings through the limestone bedrock look to be nearly finished. Foundation works for bridge abutments are underway and workers were securing rebar for the next concrete pour at the N60 junction when I passed.

    9. Castlebar east roundabout: Very busy here with both haulage traffic and earthworks to realign the existing N5 to line up with the future roundabout.


  • Registered Users, Registered Users 2 Posts: 4,720 ✭✭✭serfboard


    7. Castlebar west roundabout
    The most disappointing aspect of this scheme for me - a roundabout in the middle of a dual carriageway. I know a roundabout is cheaper, but I presume that this was as a result of lobbying by Castlebar businesses to have a roundabout instead of a GSJ (like they have at the N84 and N60 junctions).

    Fair enough there are roundabouts in Castlebar East and Westport East at the start and end of the dual carriageway section, but a roundabout in the middle of it is awful bloody annoying!


  • Registered Users Posts: 375 ✭✭Reuben1210


    serfboard wrote: »
    The most disappointing aspect of this scheme for me - a roundabout in the middle of a dual carriageway. I know a roundabout is cheaper, but I presume that this was as a result of lobbying by Castlebar businesses to have a roundabout instead of a GSJ (like they have at the N84 and N60 junctions).

    Fair enough there are roundabouts in Castlebar East and Westport East at the start and end of the dual carriageway section, but a roundabout in the middle of it is awful bloody annoying!

    100% agreed!


  • Registered Users Posts: 41 thomas385


    serfboard wrote: »
    The most disappointing aspect of this scheme for me - a roundabout in the middle of a dual carriageway. I know a roundabout is cheaper, but I presume that this was as a result of lobbying by Castlebar businesses to have a roundabout instead of a GSJ (like they have at the N84 and N60 junctions).

    Fair enough there are roundabouts in Castlebar East and Westport East at the start and end of the dual carriageway section, but a roundabout in the middle of it is awful bloody annoying!

    Agree completely.

    Another thing that I find strange is that between that Castlebar West roundabout and Westport East roundabout there isn't a single exit or junction, a distance of roughly 10km. There are certain stretches of motorway that don't have that distance between exits, never mind a predominantly rural dual carriageway!


  • Advertisement
  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    This junction was always planned to be a roundabout. The amount of traffic going on/off the DC to access Castlebar is too high for a GSJ. See screenshot from design report from 2013.

    553474.jpg
    serfboard wrote: »
    The most disappointing aspect of this scheme for me - a roundabout in the middle of a dual carriageway. I know a roundabout is cheaper, but I presume that this was as a result of lobbying by Castlebar businesses to have a roundabout instead of a GSJ (like they have at the N84 and N60 junctions).

    Fair enough there are roundabouts in Castlebar East and Westport East at the start and end of the dual carriageway section, but a roundabout in the middle of it is awful bloody annoying!


  • Registered Users, Registered Users 2 Posts: 4,720 ✭✭✭serfboard


    This junction was always planned to be a roundabout.
    Don't disagree that it was always planned to be roundabout.
    The amount of traffic going on/off the DC to access Castlebar is too high for a GSJ.
    What? There are GSJs on the M50 for God's sake. Is somebody seriously saying that there is going to be more traffic around Castlebar than there is on the M50?

    This smacks to me of making an argument to suit an outcome that was already wanted.


  • Registered Users, Registered Users 2 Posts: 1,753 ✭✭✭KrisW1001


    The M50 carries about five times the traffic that this road does, so it needs full GSJs.

    The junction types on this road are compact Grade-separated Junctions - they have much shorter on- and off- ramps, and that limits the amount of space dedicated to leaving and joining traffic on the mainline. They are grade-separated primarily to prevent right-turners blocking or conflicting with through-traffic. They're used where most of the movement is along the main road, with only small amount of traffic joining and leaving.

    On the other hand, where the movements are evenly split between traffic staying on the road and traffic joining and leaving, then a large roundabout is a better use of the land and funds, and will make traffic flow better. That reason is stated in the text DumbBrunette posted. It's not an after-the-fact argument; it's sound engineering.

    Just because it was wrong to put roundabouts on high-traffic roads, it does not mean it's wrong to use them on a scheme like this with less than 20k AADT. A full motorway/motorway junction would certainly improve traffic flow at these points (maybe shaving a whole 30 seconds off transit times through the junction), but it would do so at 5-10 times the cost of a roundabout while using much more land.


  • Registered Users Posts: 1,034 ✭✭✭riddlinrussell


    KrisW1001 wrote: »
    The M50 carries about five times the traffic that this road does, so it needs full GSJs.

    The junction types on this road are compact Grade-separated Junctions - they have much shorter on- and off- ramps, and that limits the amount of space dedicated to leaving and joining traffic on the mainline. They are grade-separated primarily to prevent right-turners blocking or conflicting with through-traffic. They're used where most of the movement is along the main road, with only small amount of traffic joining and leaving.

    On the other hand, where the movements are evenly split between traffic staying on the road and traffic joining and leaving, then a large roundabout is a better use of the land and funds, and will make traffic flow better. That reason is stated in the text DumbBrunette posted. It's not an after-the-fact argument; it's sound engineering.

    Just because it was wrong to put roundabouts on high-traffic roads, it does not mean it's wrong to use them on a scheme like this with less than 20k AADT. A full motorway/motorway junction would certainly improve traffic flow at these points (maybe shaving a whole 30 seconds off transit times through the junction), but it would do so at 5-10 times the cost of a roundabout while using much more land.

    Great points, a Compact GSJ is not 'The same as a GSJ, just smaller', capacity is impacted by the space provided for exiting the mainline, the junctions created on the over/underbridge etc


  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    Took a walk on the Greenway today past the works on the N59 north of Westport. Pic here of the cutting being dug through Barleyhill to bypass the notorious bends at that location. The cutting will come down to approximately the level of the existing road, and an embankment will be built up in the foreground to meet it.

    553541.jpg


  • Registered Users Posts: 375 ✭✭Reuben1210


    KrisW1001 wrote: »
    The M50 carries about five times the traffic that this road does, so it needs full GSJs.

    The junction types on this road are compact Grade-separated Junctions - they have much shorter on- and off- ramps, and that limits the amount of space dedicated to leaving and joining traffic on the mainline. They are grade-separated primarily to prevent right-turners blocking or conflicting with through-traffic. They're used where most of the movement is along the main road, with only small amount of traffic joining and leaving.

    On the other hand, where the movements are evenly split between traffic staying on the road and traffic joining and leaving, then a large roundabout is a better use of the land and funds, and will make traffic flow better. That reason is stated in the text DumbBrunette posted. It's not an after-the-fact argument; it's sound engineering.

    Just because it was wrong to put roundabouts on high-traffic roads, it does not mean it's wrong to use them on a scheme like this with less than 20k AADT. A full motorway/motorway junction would certainly improve traffic flow at these points (maybe shaving a whole 30 seconds off transit times through the junction), but it would do so at 5-10 times the cost of a roundabout while using much more land.

    Thanks for this - Is there an argument at all in the context of this road that GSJ should be used instead of roundabouts to 'future proof' the road in the case of large economic activity and population increases in years to come?


  • Advertisement
  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    Compact GSJs wouldn't achieve that, as they actually have a lower capacity than the 80 metre diameter roundabouts being used at Castlebar west and some of the other at grade junctions.

    Of course, you could make an argument for motorway style freeflow junctions to be provided, but per the TII standards these are not supposed to be used on Type 2 DCs, and as stated above, they would be relatively expensive.
    Reuben1210 wrote: »
    Thanks for this - Is there an argument at all in the context of this road that GSJ should be used instead of roundabouts to 'future proof' the road in the case of large economic activity and population increases in years to come?


  • Registered Users Posts: 375 ✭✭Reuben1210


    Sorry I maybe misunderstood the difference between a free-flow and a GSJ?


  • Registered Users Posts: 829 ✭✭✭DumbBrunette


    Not all GSJs are necessarily freeflow, for example the compact GSJs to be used on this scheme are similar to those at Claremorris, Knock and Charlestown, all of which have stop signs for traffic joining the mainline.

    The old M50 junctions (prior to the upgrade 10 years ago) were also grade separated, but they weren't freeflow as traffic had to stop for roundabouts and traffic lights.
    Reuben1210 wrote: »
    Sorry I maybe misunderstood the difference between a free-flow and a GSJ?


  • Registered Users, Registered Users 2 Posts: 7,036 ✭✭✭Pete_Cavan


    I get the idea behind having a roundabouts at gateways into the major towns where "heavier turning movement flows are likely". What I dont get is why Castlebar west is considered to be the junction which requires the roundabout. Traffic coming from east or south of the town, likely to be the vast majority of the traffic, is going to use one of the other junctions. It is only really traffic coming from Westport which would use that western junction, and even then some of that will continue round to use one of the other junctions if travelling to the centre or eastern side of Castlebar.


  • Registered Users, Registered Users 2 Posts: 5,600 ✭✭✭veryangryman


    Tullamore bypass is the perfect example of why roundabout junctions should be a nono for any road that goes anywhere near a large town. Can't ever get a straight run at it without being backed up on at least 2 of the roundabouts at any time of the day


  • Advertisement
Advertisement