Advertisement
Help Keep Boards Alive. Support us by going ad free today. See here: https://subscriptions.boards.ie/.
If we do not hit our goal we will be forced to close the site.
Current status: https://keepboardsalive.com/
Annual subs are best for most impact. If you are still undecided on going Ad Free - you can also donate using the Paypal Donate option. All contribution helps. Thank you.
If we do not hit our goal we will be forced to close the site.
Current status: https://keepboardsalive.com/
Annual subs are best for most impact. If you are still undecided on going Ad Free - you can also donate using the Paypal Donate option. All contribution helps. Thank you.
https://www.boards.ie/group/1878-subscribers-forum
Private Group for paid up members of Boards.ie. Join the club.
Private Group for paid up members of Boards.ie. Join the club.
M17/M18 - Gort to Tuam [open to traffic]
Comments
-
-
-
-
-
-
Advertisement
-
-
-
-
-
-
Advertisement
-
-
-
-
-
-
-
-
-
-
-
Advertisement
-
-
-
-
-
-
-
-
-
-
Advertisement
-
Advertisement
26/05/17
26/05/17
northbound lane
all signs are now up on the roadbridge section
killeelaun flyover
28/05/17
those rumours are false there is nothing wrong with the bridge,most of the roadbridge lads are gone to co longford,the are only a handful left to finish of the two roundabouts it will be the August bank holiday weekend before the bypass opens
roundabout sign
500 metres
400 metres
200 metres
60kmph
end of motorway
the kilmore roundabout
looking towards gort
the m18 27.5kms they have layed 25 kms of tarmac,and they have done 21 kms of the jersey barrier and 3kms of the wearing course as of the 30/05/17
31/05/17
the m18 1km form rathmorissy looking towards rathmorrisy 30/09/16
31/05/17
24/10/16
11/11/16
16/02/17
31/04/17
31/05/17
laraghmore looking towards rathmorrisy
the m17 25.5kms they now have the jersey barrier complete,the have 16kms of the wearing course done on the southbound lane also sisk have started on the northbound lane and they have 3kms of the wearing course done
kilseagh looking towards tuam 18.5kns
the m17 25.5kms the now have 19kms of wearing course done on the southbound lane and the have 5kms of the wearing course done on the northbound lane the m17/m18 will open at the same time as there will be to much meassing around rathmorissy,most of the signs are done on the m17 they just have to do the signs around annagh hill