Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie

Dublin Metrolink (just Metrolink posts here -see post #1 )

Options
12223252728314

Comments

  • Closed Accounts Posts: 3,032 ✭✭✭DWCommuter


    Can anyone clarify the MN PPP model? Apart from design and build I assume the consortium will operate it as well. Do they claw back user revenue on top of the PPP repayments over 30 years?


  • Closed Accounts Posts: 3,032 ✭✭✭DWCommuter


    lods wrote: »
    I would just like a decision rather than all this double speak . I've no doubt FG and LV know what their going to do & all this seems like an illusion of examining the project . As bertie would say, it's all smoke and daggers!

    We'd all like a decision. But as FG, LAB and LV have only just arrived they are now being treated to the reality of the project. This has to be weighed up against the state of the country's finances. I'd say it will be soon enough. MN is not the voting machine some think it is. People are now worried about keeping the roof over their heads, paying the bills etc etc. Worrying about traffic congestion in Dublin has gone way down the list. That concern was a by product of wealth to many of us. The ultimate decision on MN will be based on whether or not we want to future proof Dublin in terms of public transport provision. But I doubt our politicians have the balls to think that way.


  • Closed Accounts Posts: 724 ✭✭✭dynamick


    DWCommuter wrote: »
    Can anyone clarify the MN PPP model? Apart from design and build I assume the consortium will operate it as well. Do they claw back user revenue on top of the PPP repayments over 30 years?

    It's a a DBFM contract so the operation of the metro will be a separate contract.

    The hope would be that the operations revenue would cover running costs as with the Luas.

    The decision to proceed with projects like MN will surely be taken with the IMF/EU. As the funding arrangements for the state for the next 4 years are currently under negotiation, I'd imagine we'll know in the next few weeks.


  • Registered Users Posts: 426 ✭✭Jack Noble


    dynamick wrote: »
    It's a a DBFM contract so the operation of the metro will be a separate contract.

    The hope would be that the operations revenue would cover running costs as with the Luas.

    The decision to proceed with projects like MN will surely be taken with the IMF/EU. As the funding arrangements for the state for the next 4 years are currently under negotiation, I'd imagine we'll know in the next few weeks.

    I thought it was a DBFMO contract - the two bidding consortia each contain an operator.

    Here's what it says on Transport 21 re the original tender and final selected bidders.
    Metro North is a PPP project and bidders will be asked to tender for the design, build, funding, maintenance and operation of the line. In February 2009 four bidding consortia submitted their first round tenders for the PPP contract for Metro North to the RPA. The consortia are a mix of international and Irish companies. These submissions were evaluated by the RPA and in June 2009 the latter announced that it had shortlisted two bidding consortia, Celtic Metro Group and Metro Express, to proceed to the final stage of the PPP procurement process.

    Metro Express has Transdev/RATP (Paris Metro) and Celtic Metro has MTR (Hong Kong metro).

    Here is what RPA posted on Metro North Facebook page re repayments and operations:
    Metro North is being brought forward as a PPP and a large part of the funding will be raised by the private sector. Government does not start to pay this money back until Metro North is open to passengers. The payments to the private sector are also linked to performance of the system with significant deductions made if the service is not provided. This mix of the public and private sectors working hand in hand has proved to be extremely successful in Ireland and other European countries.


  • Registered Users Posts: 4,905 ✭✭✭Aard


    Fortunately, I think the EU do take kindly to infrastructural investment.


  • Advertisement
  • Closed Accounts Posts: 724 ✭✭✭dynamick


    The RPA’s Metro North and West (and potentially Luas
    Line F) projects include the provision of rolling stock
    as well as maintenance of the entire system including
    the control room as part of the DBFM with a separate
    Operator responsible for the provision of drivers and
    for revenue collection, fare evasion and customer
    services
    http://www.nationaltransport.ie/downloads/project_management_guidelines_for_PPP.pdf


  • Registered Users Posts: 426 ✭✭Jack Noble


    dynamick wrote: »

    That's interesting because it is contrary to everything that has been said about Metro North operations to date - by both the RPA and Dot/T21.

    The original Metro North tender was for DBFMO and that is the basis on which the consortia submitted their bids.

    The T21 quote I linked to above is from a page that was last updated in February 2011.

    Here is the original RPA press release on the procurement process which may clear up confusion. It appears that while one consortium will be selected for the Metro North project, there will be two separate contracts - 'Infrastructure' and 'Operations'.
    http://www.rpa.ie/en/projects/metro_north/build_and_operation_permission/Pages/MetroNorthProcurement.aspx

    The project will be carried out on the basis of a design, build, finance and maintain contract (the "Infrastructure Contract") having a term of the construction period plus 25 years from the commencement of passenger services. The project will also include an operations contract (the “Operating Contract”) which will be effective from the commencement of passenger services.


  • Closed Accounts Posts: 724 ✭✭✭dynamick


    I don't understand that to mean that one consortium will get both contracts.

    There is a line to be drawn between operations and maintenance. From the NTA quote above it seems that the ops contract will be limited to :
    • provision of drivers
    • revenue collection
    • fare evasion
    • customer services

    Other day to day tasks in running the trains will be carried out by the main construction contractor.


  • Registered Users Posts: 426 ✭✭Jack Noble


    dynamick wrote: »
    I don't understand that to mean that one consortium will get both contracts.

    There is a line to be drawn between operations and maintenance. From the NTA quote above it seems that the ops contract will be limited to :
    • provision of drivers
    • revenue collection
    • fare evasion
    • customer services

    Other day to day tasks in running the trains will be carried out by the main construction contractor.

    Then why do the bidding consortia contain operation companies?

    Is it not the case that:

    If Celtic Metro win, then MTR will get the 'operations' contract as part of the deal?

    If Metro Express win, then Transdev/RATP will be the selected operator?

    I've just found the RPA original tender from March 2007 - and now I'm even more confused. It refers to separate contracts.

    Here it is

    http://www.etenders.gov.ie/search/show/search_view.aspx?ID=MAR079793
    Title attributed to the contract by the contracting entity: Metro North
    (Dublin) - Infrastructure Contract.
    RPA seeks expressions of interest for the provision of a new metro line
    serving the Greater Dublin area between Lissenhall and St Stephen's Green
    ('Metro North').
    RPA intends to award separate contracts for:
    (i) an infrastructure contractor and rolling stock supplier (the
    'infrastructure contract'); and
    (ii) an operator (the 'operating contract')
    (together the 'Metro North Contracts').
    Interested infrastructure contractors are invited to respond to this
    notice.
    Interested operators are invited to respond to a separate notice
    establishing a qualification system for operators.

    Strange that DoT refer to a DBFMO contract on T21 but the reality seems to very different, as you have said Dynamick.


  • Closed Accounts Posts: 724 ✭✭✭dynamick


    btw: Ever seen MTR in operation? It's an amazingly competent company decades ahead of European rail operators.

    MTR or RATP will run the control room for MN


  • Advertisement
  • Registered Users Posts: 569 ✭✭✭lods


    Leo Varadkar just interviewed on RTE , says he's proceeding with Metro North, Enabling workings starting immediately .:mad:


  • Registered Users Posts: 2,849 ✭✭✭Van.Bosch


    lods wrote: »
    Leo Varadkar just interviewed on RTE , says he's proceeding with Metro North, Enabling workings starting immediately .:mad:

    April Fool?


  • Registered Users Posts: 426 ✭✭Jack Noble


    Van.Bosch wrote: »
    April Fool?

    Golden rule for today is believe nothing said or printed this morning!:o


  • Registered Users Posts: 569 ✭✭✭lods


    :D


  • Registered Users Posts: 426 ✭✭Jack Noble


    lods wrote: »
    :D

    Twould be very funny all the same, lods, if Leo did announce it this afternoon!

    Although I doubt you would laugh quite as much as the rest of us:D


  • Registered Users Posts: 569 ✭✭✭lods


    Jack Noble wrote: »
    Twould be very funny all the same, lods, if Leo did announce it this afternoon!

    Although I doubt you would laugh quite as much as the rest of us:D
    Now that would really be an April fool:P


  • Closed Accounts Posts: 9,376 ✭✭✭ei.sdraob


    Hmm jokes aside I do see the need for a metro, I would think that Dublin Airport is a confusing mess if you are the first time in Ireland, as in trying to figure out how you get to city center, especially if you dont know English. Hell as someone who used the ariport many of times i was still stumped by car parking arrangements spending an hour looking for a carpark :(

    In Geneva in comparison you can take a train/metro (mostly underground), tram or buses from airport for free, they even go as far as letting the visitors use the public transport (trams, buses, boats) etc for free
    I wonder what it would do to tourism here if we had free transport.


  • Registered Users Posts: 426 ✭✭Jack Noble


    Joking aside, this report sounds a very ominous warning for Metro North, Dart Underground and other PPP projects.

    It won't matter how committed the governement is to building rail and road schemes if the money to do it is not available.

    http://www.independent.ie/business/irish/bailout-puts-rail-projects-in-jeopardy-2603945.html
    THE future of Metro North and other key infrastructure projects has been thrown into doubt because of the fallout from the EU/IMF bailout.
    Key roads and rail projects are unlikely to go ahead unless "financial credibility" is restored and the international markets are assured that the State can make repayments, the Department of Transport has warned.
    And even if the projects eventually get the green light, they will end up costing taxpayers millions of euro more than planned for.
    This is because Ireland will be forced to pay a premium to borrow money on the international markets in the wake of the ongoing banking and economic crisis.
    In a 322-page briefing note to new minister Leo Varadkar, which was published last night, officials warn that the markets will be "reluctant" to lend unless the debt crisis is stabilised.
    This means that public private partnership contracts -- where the private sector bankrolls a project and the State repays the cost over time -- are at risk of being permanently shelved.

    Here's the briefing note given to Varadkar and released by DoT last night.

    http://www.transport.ie/upload/general/13086-MINISTERS_BRIEF_SCANNED_VERSION-0.PDF

    EDIT: Just checked the document - pretty much every detail on Metro North has been blacked out and there is very little on DartU and nothing new.


  • Registered Users Posts: 20,397 ✭✭✭✭FreudianSlippers


    Jack Noble wrote: »
    Joking aside, this report sounds a very ominous warning for Metro North, Dart Underground and other PPP projects.

    It won't matter how committed the governement is to building rail and road schemes if the money to do it is not available.

    http://www.independent.ie/business/irish/bailout-puts-rail-projects-in-jeopardy-2603945.html



    Here's the briefing note given to Varadkar and released by DoT last night.

    http://www.transport.ie/upload/general/13086-MINISTERS_BRIEF_SCANNED_VERSION-0.PDF

    EDIT: Just checked the document - pretty much every detail on Metro North has been blacked out and there is very little on DartU and nothing new.
    The point that I've made on this thread multiple times is that the money has to be available for these projects - beg, borrow or steal.

    We are never going to recover economically on our relatively small exports (our only positive growth sector) and by funnelling more money into the banks.

    We need to get our internal economy going again. How do we do that?
    Simply put, we need to build some serious shít and we need to do it now.
    We have a massive number of unemployed people (a lot of whom are builders or in the trade) and construction companies laying people off every day.
    We need to tender the works for Metro North, DU and other projects and start on them as soon as physically possible. Fast-track the planning and get moving.

    Not having money is no excuse. We are borrowing out the arse to fund our banks, when realistically if we get people back to work building MN and DU et al we will be effectively recapitalising our banks and our country as a whole by getting currency moving. We are facing two distinct choices here. Build or don't build. I don't think you'll find any credible economists that will suggest not building infrastructure now is a good way to begin recovery.


  • Registered Users Posts: 426 ✭✭Jack Noble


    The point that I've made on this thread multiple times is that the money has to be available for these projects - beg, borrow or steal.

    We are never going to recover economically on our relatively small exports (our only positive growth sector) and by funnelling more money into the banks.

    We need to get our internal economy going again. How do we do that?
    Simply put, we need to build some serious shít and we need to do it now.
    We have a massive number of unemployed people (a lot of whom are builders or in the trade) and construction companies laying people off every day.
    We need to tender the works for Metro North, DU and other projects and start on them as soon as physically possible. Fast-track the planning and get moving.

    Not having money is no excuse. We are borrowing out the arse to fund our banks, when realistically if we get people back to work building MN and DU et al we will be effectively recapitalising our banks and our country as a whole by getting currency moving. We are facing two distinct choices here. Build or don't build. I don't think you'll find any credible economists that will suggest not building infrastructure now is a good way to begin recovery.

    Agree 100% - but we can't magic the money out of thin air. That's the problem the new government faces thanks to the legacy of the FF-PD/Green years.


  • Advertisement
  • Registered Users Posts: 20,397 ✭✭✭✭FreudianSlippers


    Jack Noble wrote: »
    Agree 100% - but we can't magic the money out of thin air. That's the problem the new government faces thanks to the legacy of the FF-PD/Green years.
    They certainly can. We're already borrowing billions from Europe and IMF, I'm sure if the current government went forward with a proposal to create jobs via infrastructure construction in Dublin which would link the airport to the city centre, financial district and companies like Google and could show financial support from private enterprise - they would be more than happy to lend more money.

    As it stands right now, we can either keep borrowing from them to prop up the banks for the foreseeable future, or we can borrow from them to get our economy moving again which will, in turn, benefit our crippled banks.
    This is an inherited problem, but they shouldn't be using the same tired inherited policies... the previous government's decisions were based on bad economics.
    It's almost dicta at this point: THERE IS NO SAVING YOUR WAY OUT OF RECESSION


    What I think people don't understand is that our banks are failing for multiple reasons, one key one is that there is very little movement of funds at this point. Banks rely on this movement of credit and debit to continue to fund themselves. The only way to properly repair this is to lower unemployment and start paying people who will put that money in banks, buy houses, etc. - the only way (practically) to get people back to work which will not create another property bubble is infrastructure!


  • Banned (with Prison Access) Posts: 558 ✭✭✭OurLadyofKnock


    Ireland (and many other countries) is being used as a tax farm to save globalisation. We have been reduced to nothing other than tax livestock. That's what is behind the current Voodoo Economics.

    The only chance Ireland has to recover it to build massive amounts of new infrastructure. There is no other option. Either we do this or Ireland becomes a nation which only produces massive bonuses for international banksters.

    I would go as far as saying if MN and DU and others are not started within the next year we are looking at a future which could lead to major civil and social unrest as most people will be still working for nothing other than high taxation.

    I am actually scared that this new ultra globalist (Bilderburg/Tri-Lateralist) FG government could do something truly moronic and dangerous and cancel MN and DU. I don't trust them - they are as insane as FF and just as easily swayed by pathological journalist talking bollox.

    We are building more than just a transport system - we are giving ourselves a chance of some kind of worth while future.


  • Registered Users Posts: 569 ✭✭✭lods


    ei.sdraob wrote: »
    Hmm jokes aside I do see the need for a metro, I would think that Dublin Airport is a confusing mess if you are the first time in Ireland, as in trying to figure out how you get to city center, especially if you dont know English. Hell as someone who used the ariport many of times i was still stumped by car parking arrangements spending an hour looking for a carpark :(

    In Geneva in comparison you can take a train/metro (mostly underground), tram or buses from airport for free, they even go as far as letting the visitors use the public transport (trams, buses, boats) etc for free
    I wonder what it would do to tourism here if we had free transport.

    Its not an Airport Metro. Bad signage is not a reason to have an Airport Metro
    EDIT: Just checked the document - pretty much every detail on Metro North has been blacked out and there is very little on DartU and nothing new

    Couldn't see it mentioned once :confused:
    The point that I've made on this thread multiple times is that the money has to be available for these projects - beg, borrow or steal.


    Steal seems to be the only option left open


  • Banned (with Prison Access) Posts: 25,234 ✭✭✭✭Sponge Bob


    Jack Noble wrote: »
    Joking aside, this report sounds a very ominous warning for Metro North, Dart Underground and other PPP projects.
    Thanks jack, I scanned and dirty OCRed it
    METRO NORTH
    Background
    • Metro North will provide a rapid, high capacity, high frequency link between the city centre
    and Estuary in Swords via Dublin Airport (journey time to Dublin Airport will be
    approximately 20 minutes; total route approximately 16.5 km).
    • The project is being procured as a Public Private Partnership (PPP) and the Railway
    Procurement Agency (RPA) has short-listed two PPP consortia under the PPP procurement
    process with a view to financial close in late 2012.
    • lt is estimated that Metro North will generate 4,000 direct construction jobs for a significant
    proportion of the main construction programme. In addition approximately 2000 indirect
    jobs will be created due to secondary spin off impacts. The enabling works for the project
    are estimated to generate close to 2,100job years of employment. This includes an estimate
    of 250 jobs to be created in 2011.
    Planning
    • The Railway Order for Metro North became enforceable on 23rd December 2010. As part of
    the Order, An Bord Pleanala (ABP) decided that that the depot for Metro North should be
    relocated to south of the airport. RPA has now concluded its public consultation exercise
    and the resulting preferred location selected. An Environmental Impact Statement will now
    be prepared and an application made to ABP for a Railway Order to permit its construction.
    A decision by ABP is anticipated by end Q3 2011.
    Business Case
    • During December 2010, the RPA provided the National Transport Authority (NTA) with an
    addendum to theirluly 2010 Business Case which updated key issues and parameters taking
    account of ABP conditions in the Railway Order; updated Cost Benefit Ratio 1.46:1 (was
    1.55:1) and internal Rate of Return 8.65% (was 9.1%); when account is taken of wider
    economic benefits, updated CBR 1.89:1 (was 2:1).
    • The Business Case for Metro North has been independently reviewed by Booz and Co. on
    behalf of the NTA. The review conciuded that Metro North is a value for money project
    supportive of wider transport objectives for the Greater Dublin Area and that the economic
    case for the project is strong.
    • A final business case will be prepared following selection of preferred bidder and before
    financial close.

    and for comparison.
    DART UNDERGROUND
    Background to Project
    • The DART Underground programme is made up of 2 elements —
    • the development of an underground tunnel between Docklands and Inchicore
    which will serve a number of key locations in the city centre with underground
    stations.
    • A series of related works including the Resignalling of the Northern and
    Maynooth lines, electrification to Drogheda, Maynooth and Hazelhatch, the
    Kildare Route Project involving four tracking on the Kildare line (which was
    completed in 2010) and the expansion of the DART fleet and associated depot
    facilities.
    • The DART Underground Programme will deliver a second high capacity DART line which
    will run underground through the heart 0f Dublin City Centre, The twin bore tunnels will
    be approximately 7.6 Km in length and will connect the Northern and Kildare rail lines,
    with underground stations strategically located at Spencer Dock, Pearse, St. Stephen*s
    Green, Christchurch and Heuston Station, as well as a new surface DART station at
    Inchicore, opening up new areas for travel by train.
    • It is set to be developed with a capacity for up to 20 trains each direction per hour,
    allowing up to 64,000 commuters to use the line hourly with capacity for DART services
    to operate up to every 3 minutes and will dramatically increase frequency and capacity
    for commuters on DART Northern, Maynooth and Kildare lines and relieve the current
    congestion at Connolly Station.
    • Crucially, DART Underground will link all rail systems - DART, Commuter, InterCity, Luas
    and Metro (eg Metro North at St Stephens Green) to form an integrated and seamless
    transport network that will increase the numbers travelling on the GDA rail system to
    over 100 million passengersjourneys annually.
    Current Position
    • The tunnel element of the Programme was being developed as a Public Private
    Partnership (PPP)- as a design, build, finance, maintain (DBFM) project. However, given
    reduced funding available under the "National Recovery Plan 2011-2014/’ it will not
    now be possible to deliver the tunnel element of the DART Underground Programme in
    the immediate period.
    • Some resignalling and associated works, part of the overall DART Underground
    Programme, which have capacity benefits in and of themselves will proceed over the
    next four years and this will prepare the network for the delivery of the underground

    tunnel once financial resources permit. The National Transport Authority (NTA) is
    currently examining the scope for the delivery of these associated works in the period to
    2014.
    Planning
    • An Bord Pleanala commenced the oral hearing for the DART Underground on 22 November
    2010. The Railway Order could be made by the end of 2011.
    Business Case
    • The economic case for the DART Underground Programme is very strong with a benefit to
    cost ratio of 2.4. This result is robust to a series of sensitivity tests. The wider economic
    benefits (WEBs) of the programme are particularly high.
    • The business case for DART Underground was independently reviewed by Goodbody
    consultants in 2010. They concluded that the Business Case supported a decision to proceed
    with the Dart Underground project.

    and the Capital Envelopes, €800m of they capital envelope is GONE as in already spent/allocated in the form of retention payments.
    CAPITAL INVESTMENT PROGRAMME
    Economic Difficulties and Reduced Allocations
    Transport 21 (T21) was the 10-year capital investment framework established in 2005 to provide
    for the development of transport infrastructure. At the launch of T21, a €34 billion investment
    package was announced which comprised €26 billion to be provided by the Exchequer and €8
    billion by Public Private Partnership {PPP) funding.
    In the first 5 years of T21 Exchequer expenditure amounted to a total of over €10.5 billion.
    T21 Expenditure 2006-2010* _'__
    vear w 2007 2008 W 2010 Total
    €billion 1.937 2.357 2.504 2.124 1.730 10.652
    In addition, the 1“ PPP roads programme resulted in private sector funding of approx. €2 billion
    Arising from the allocation under the National Recovery Plan in November 2010, a breakdown of
    the reduced transport capital investment programme for 2011-2014 is as follows:
    _ 2011 2012 2013 2014 mai
    €m €rn €m €m €m
    Public Transport 394 392 527 493 1,806
    swans @ sas 510 asc 2,865
    Other 54 S2 38 28 172
    mai 1,438 Q 1,075 1,001 4,aaa
    Note - Summary of Reductions:
    The original exchequer allocation provided for T21 has been subject to a number of adjustments totalling
    approx. €7 billion between 2008-2014 as follows:
    2008-2010: total reductions of approx. €1 billion were implemented.
    2011-2014: total reductions of almost €6 billion have been proposed for the four years covered by the
    National Recovery Plan.
    Committed Expenditure
    Of the €4.843 billion allocated for 2011-2014, it is estimated that in the region of €1.7 billion of
    this is contractually committed. Approximately €1.3 billion of this relates to committed
    expenditure for national roads including approx. €800 million relating to closeout payments for
    national roads projects recently completed. Over €300 million relates to committed
    expenditure for public transport projects.
    In addition, a significant portion of the overall transport capital investment programme is
    essential for on-going annual expenditure programmes such as railway safety (€400 million),
    road rehabilitation / maintenance (approx. €9OO million for regional & local roads), Coastguard
    1 Expenditure between 2008 — 2010 reflected various cuts in the capital allocation for T21 projects
    totalling approx. €1 billion.

    »¢: `*y` ~`·— ,,.- *1·—=eti.·:ée;§:;y:.s’ is ‘ " ""’ . * *2* fl·&;2l;n=?‘>:»F::;;t3:42.;; *— . —~`-, :.
    · ‘`
    Assistant Secretary: John Murphy
    Principal Officer: Doreen Keaney
    Principal Advisor: Dominic Mullaney
    CAPITAL INVESTMENT PROGRAMME
    Economic Difficulties and Reduced Allocations
    Transport 21 (T21) was the 10-year capital investment framework established in 2005 to provide
    for the development of transport infrastructure. At the launch of T21, a €34 billion investment
    package was announced which comprised €26 billion to be provided by the Exchequer and €8
    billion by Public Private Partnership {PPP) funding.
    In the first 5 years of T21 Exchequer expenditure amounted to a total of over €10.5 billion.
    T21 Expenditure 2006-2010* _'__
    vear w 2007 2008 W 2010 Total
    €billion 1.937 2.357 2.504 2.124 1.730 10.652
    In addition, the 1“ PPP roads programme resulted in private sector funding of approx. €2 billion
    Arising from the allocation under the National Recovery Plan in November 2010, a breakdown of
    the reduced transport capital investment programme for 2011-2014 is as follows:
    _ 2011 2012 2013 2014 mai
    €m €rn €m €m €m
    Public Transport 394 392 527 493 1,806
    swans @ sas 510 asc 2,865
    Other 54 S2 38 28 172
    mai 1,438 Q 1,075 1,001 4,aaa
    Note - Summary of Reductions:
    The original exchequer allocation provided for T21 has been subject to a number of adjustments totalling
    approx. €7 billion between 2008-2014 as follows:
    2008-2010: total reductions of approx. €1 billion were implemented.
    2011-2014: total reductions of almost €6 billion have been proposed for the four years covered by the
    National Recovery Plan.
    Committed Expenditure
    Of the €4.843 billion allocated for 2011-2014, it is estimated that in the region of €1.7 billion of
    this is contractually committed. Approximately €1.3 billion of this relates to committed
    expenditure for national roads including approx. €800 million relating to closeout payments for
    national roads projects recently completed. Over €300 million relates to committed
    expenditure for public transport projects.
    In addition, a significant portion of the overall transport capital investment programme is
    essential for on-going annual expenditure programmes such as railway safety (€400 million),
    road rehabilitation / maintenance (approx. €9OO million for regional & local roads), Coastguard
    1 Expenditure between 2008 — 2010 reflected various cuts in the capital allocation for T21 projects
    totalling approx. €1 billion.

    Search & Rescue (€30 million), maintaining progress on accessibility (€5O million) and traffic
    management projects (€12O million).
    Existing Capital Investment Priorities 2011-2014
    Public Transport
    A total ofjust over €1.8 billion has been provided for public transport projects in the National
    Recovery Plan.
    • Metro North is the major component of the public transport allocation. Enabling works
    for Metro North are scheduled to commence in 2011 and the procurement process is
    continuing.
    • It will now not be possible to deliver the tunnel element of the DART Underground
    programme in the immediate period. However, provision has been made for funding
    some of the re-signalling and associated works, which have capacity benefits in and of
    themselves.
    · Funding will continue to be provided for vital public transport programmes such as
    railway safety, traffic management, accessibility and real time passenger information
    across the country. In Dublin the Luas extension to Citywest will be completed in 2011
    and a new public transport bridge at Marlborough Street will commence construction.
    • Planning will continue on a range of other public transport projects including Luas BXD,
    the cross-city link, Luas extensions to Lucan and Bray, Metro West and the DART
    Underground tunnel.
    • Funding will also be provided for the purchase of new buses for PSO services.
    • Further progress on Phase 2 of the Western Rail Corridor will be dependent on a review
    of the performance of Phase 1 and a full economic assessment of Phase 2.
    Roads .
    There is funding of €1,820 million for national roads and €1,045 million available for regional &
    local roads over the next four years.
    • NRA have adequate money for rehabilitation and minor works in 2011 and will go ahead
    with the planned 2011 starts including Belturbet, Longford and Tralee bypasses , N4
    Downes grade separation and the Cork Southern Ring Road junctions. Two PPP projects
    are also scheduled to start in 2011; the M17/18 Gort — Tuam PPP and lvl11/Newlands
    Cross PPP bypasses.
    • No major schemes are likely to start in 2012 or 2013 due to the shortage of funds. Due
    to the reduction in funding from 2013 NRA plans to focus on maintenance of existing
    assets and the incremental improvement of national secondary roads.
    Other Funding
    • €172 million has been earmarked for other projects over the next four years. Almost
    half of this will be provided to support Smarter Travel Policy measures, mainly
    comprising of investment in exemplary cycling and walking infrastructure.
    • Just over €50 million is being provided to Maritime and Irish Coast Guard projects; the
    main focus of this investment being the cost of a new build S92 Helicopter for the Irish
    Coast Guard (IRCG) Search and Rescue (SAR) helicopter service and payments in respect
    of remedial works being carried out at regional harbours.
    • In addition, €2O million in total is being provided in 2011 and 2012 to partially fund the
    Cross-Border A5 Road (North West Gateway to Aughnacloyj project.


  • Moderators, Motoring & Transport Moderators Posts: 14,072 Mod ✭✭✭✭monument


    Not sure if this is an April Fools joke or even related to MN...

    But what was described by the European Investment Bank as a high level delegation is currently visiting Ireland looking at a number of projects.

    Ireland recently was reported to be one of the worst for under using the EIB. Could the article a while back that it would fund more the €500m promised be true?


  • Banned (with Prison Access) Posts: 25,234 ✭✭✭✭Sponge Bob


    c.€170m of EIB funds which should have been partly or wholly drawn down by now is lying on a shelf since the M18 PPP Project effectively collapsed late last year (The Gort -Tuam Project) . Either that or it was used partly or wholly for the land purchasing in 2010 and now nobody will build the road on that land.

    I am sure the EIB are all ears :)

    Anyway the PPP section in the Dept of Finance has nothing to do except attend meetings nowadays.


  • Moderators, Motoring & Transport Moderators Posts: 14,072 Mod ✭✭✭✭monument


    Sponge Bob wrote: »
    c.€170m of EIB funds which should have been partly or wholly drawn down by now is lying on a shelf since the M18 PPP Project effectively collapsed late last year (The Gort -Tuam Project) . Either that or it was used partly or wholly for the land purchasing in 2010 and now nobody will build the road on that land.

    I am sure the EIB are all ears :)

    Anyway the PPP section in the Dept of Finance has nothing to do except attend meetings nowadays.

    Overall Ireland hasn't got much loans from the EIB compared to most EU states.


    From RTE today... it sounds like more loans (maybe not for MN at all, but more)...
    A senior official from the European Investment Bank has said the measures announced by the Government yesterday are 'very thorough' and will do a lot to renew international confidence in the Irish banking system.

    Plutarchos Sakellaris, European Investment Bank Vice President responsible for operations in Ireland, said it was important that the Irish Government met its obligation to carry out a stress test of banks here.

    A delegation from the EIB is in Ireland to meet the new Minister for Finance and others in order to match its lending programme to national development priorities.



    Anyway, here's the EIB press release:
    PRESS RELEASE

    1st April, 2011

    European Investment Bank to reinforce engagement in Ireland

    The European Investment Bank today outlined current support for projects in Ireland and emphasised commitment to the country during the economic crisis. During 2010 the long-term lending institution of the European Union provided EUR 241 million for the Whitegate Power Plant, Bord Gais’s first major electricity station, as well as investment in six schools across the country. Over the last five years the European Investment Bank has provided EUR 2.6 billion for investment in Ireland.

    Michael Noonan, Irish Minister of Finance said: "I am pleased to say that my discussions with the European Investment Bank have outlined a range of projects where EIB funding can contribute to transport and education infrastructure, funding for small businesses and other key sectors across the country. I look forward to working with the EIB in its financing of key infrastructure projects to support economic growth in Ireland."

    Plutarchos Sakellaris, European Investment Bank Vice President responsible for operations in Ireland, said: “The European Investment Bank is committed to supporting Ireland during challenging economic times. We are working closely with public bodies, leading companies and SMEs to ensure continued key capital investment. We are confident that industry, transport, social infrastructure, health and education will continue to benefit from EIB support in the years to come.”

    Over 1500 Irish small and medium sized companies benefitted from funds provided by the European Investment Bank to local partner banks over the last five years.

    The European Investment Bank is evaluating possible loans for a number of projects in Ireland, including additional SME funding, transport and knowledge economy lending for education infrastructure.

    The EIB is considering lending up to EUR 90 million to finance construction work at University College Dublin in Ireland to finance the first and second phase of the total EUR 292 million university development, including a new science centre, refurbishment and new construction of student residences, construction of a new science building and law school law.

    Notes for Editors:

    • The European Investment Bank is the world’s largest multinational financial institution and last year lent EUR 72 billion for 460 projects around the world.
    • The European Investment Bank was created by the Treaty of Rome in 1958 as the long-term lending bank of the European Union. The task of the Bank is to contribute towards the integration, balanced development and economic and social cohesion of the EU Member States. The EIB raises substantial volumes of funds on the capital markets which it lends on favourable terms to projects furthering EU policy objectives. The EIB operates on a non-profit maximizing basis and lends at close to the cost of borrowing.
    • A high-level European Investment Bank Delegation is currently visiting Dublin to see how future lending can best match national priorities. Meetings will be held with Minister of Finance Michael Noonan, Central Bank Governor Patrick Honohan and Michael Tutty, Chairman of the Commission for Energy Regulation.


  • Closed Accounts Posts: 724 ✭✭✭dynamick


    EIB signed contracts 2000-2011

    Country|Billions
    Austria|12.78
    Belgium|9.86
    Bulgaria|2.43
    Cyprus|1.89
    Czech Republic|12.19
    Denmark|6.78
    Estonia|1.29
    Finland|8.59
    France|49.45
    Germany|76.46
    Greece|15.78
    Hungary|11.91
    Ireland|5.54
    Italy|74.7
    Latvia|1.78
    Lithuania|1.49
    Luxembourg|1.47
    Malta|0.33
    The Netherlands|9.58
    Poland|25.93
    Portugal|23.84
    Romania|6.66
    Slovakia|3.29
    Slovenia|3.39
    Spain|79.44
    Sweden|10.92
    United Kingdom|42.09
    Total Amount|499.88


  • Closed Accounts Posts: 3,032 ✭✭✭DWCommuter




  • Advertisement
  • Closed Accounts Posts: 3,032 ✭✭✭DWCommuter


    Jack Noble wrote: »
    Agree 100% - but we can't magic the money out of thin air. That's the problem the new government faces thanks to the legacy of the FF-PD/Green years.

    Which is why none of this will be built. It is indeed over and I laugh at the ineptitude of this country but yet feel very saddened that we are actually back before DART times because at least we could borrow money to build that.

    When I sat in Dublin Castle at the launch of T21, I looked at the top table and thought to myself, you really are a bunch of assholes re-spinning a lot of what was there before. I knew then that time had run out. At the time I was a very strict anti WRC campaigner and was rightly pissed off that phase one was to be sanctioned even though DU and MN were apparently in the mix. A glorified trainspotter (and WRC obsessive) tapped me on the back and said, " you got what you wanted too". I wanted to slap him in the head, because I could clearly see that the WRC phase one was a cheapo deal that would be done and that DU and MN were just re-invented with glossy graphics and would just become fantasy promises. I gave a very emotional interview to RTE news which wasn't used, but by christ if they had it now it would be more than relevant.

    Prior to that fateful day in November 2005, we could have been well advanced on DU and MN, but politicians procrastinated and lied in an outright fashion, because we just don't do visionary public transport in Ireland and we never will. They are happy now because they have the financial excuses. It reinforces the fact that even if the money was flowing they would still find excuses. We blew billions and billions in the good times and built little in terms of rail projects. Now we are blowing billions and billions of borrowed money just to keep the ship afloat. How can any of you possibly be positive about MN etc.???


This discussion has been closed.
Advertisement