Road Construction Projects - Start & End Dates

1234568

Comments

  • Registered Users Posts: 7,797 ✭✭✭munchkin_utd


    spacetweek wrote: »
    Yis got the Charlestown Bypass - be thankful! j/k
    +1
    not to mention that the M17 will finish a bare 40km from the biggest town in Mayo, Castlebar, and only 20km from Claremorris and Ballyhaunis.
    And Westport is "behind" Castlebar so also benefits from the motorway linkup as they have to go via Castlebar where they are only 40km from the Motorway.

    when that is finished you will suddenly see mayo people clambering to have the road to Tuam from Mayo being upgraded as the N5 will become irrelevant to a swathe of the south of the county!


  • Posts: 0 Tobias Fit Hunter


    +1
    not to mention that the M17 will finish a bare 40km from the biggest town in Mayo, Castlebar, and only 20km from Claremorris and Ballyhaunis.
    And Westport is "behind" Castlebar so also benefits from the motorway linkup as they have to go via Castlebar where they are only 40km from the Motorway.

    when that is finished you will suddenly see mayo people clambering to have the road to Tuam from Mayo being upgraded as the N5 will become irrelevant to a swathe of the south of the county!

    The ballindine section to Milltown(all in Galway) is the worst piece of road between sligo and Limerick, so i will be looking for it to be done. Five people killed on it in the just the last year alone.
    The Mayo section is relatively okay, then they need to start on the curry to colloney section:D


  • Registered Users Posts: 10 Storm2


    M17 won't be tolled based on the information I've researched.


  • Registered Users Posts: 6,106 ✭✭✭antoobrien


    Storm2 wrote: »
    M17 won't be tolled based on the information I've researched.

    This has been discussed a few times on the M17/18 project thread.

    There is no planning permission for a toll (let alone 2 as has been suggested) and changing the plans now would probably require extra land to be purchased.

    Unless they go the M50 route with barrier free tolling,there will be no toll on this road. The barrier free option is costing the M50 operators a lot of money to run, so its unlikely that this will be a viable option for a new concession.


  • Banned (with Prison Access) Posts: 25,234 ✭✭✭✭Sponge Bob


    N17 Castletown bends scheme ( between Tuam and Milltown) starting this month. About 1km long. This scheme was originally tendered in 2008 but abandoned and retendered.

    http://www.galwaynews.ie/25158-major-works-begin-n17
    Realignment works between Tuam and Milltown at the Castletown junction are expected to begin in two weeks time.
    Contracts were signed this week and work on the road is expected to be finished by the end of the year.

    The Milltown-Ballindine stretch is earmarked for two schemes, probably not this year though.


  • Advertisement
  • Moderators, Science, Health & Environment Moderators Posts: 4,917 Mod ✭✭✭✭spacetweek


    Has Enfield-Edenderry started yet? The contract was award a few weeks ago.


  • Registered Users Posts: 77 ✭✭tomflynn


    Completed 2012
    N5 Longford Bypass (2.6km): Opened Aug. 2012

    Under Construction 2012
    M1 Swords Improvement Scheme J3 (Drinan) to J4 (Lissenhall) (4km): Completion Dec. 2012
    N3 Belturbet Bypass (6.7km): Completion May 2013
    N4 The Downs Grade Separation (5km): Completion Dec. 2012
    M7/N24 Ballysimon Junction Improvements: Completion ???
    N17 Castletown Realignment (2.3km): Completion Oct. 2012
    N21 Killarney Pole to Barnagh Road Safety Scheme (3.4km): Completion ???
    N22/N69/N70 Tralee Bypass (13.5km): Completion April 2013
    N25 Cork Southern Ring Road Interchanges (3km): Completion July 2013
    N52 Carrick Bridge to Clonfad (Dalystown) (5.6km): Completion Dec. 2012
    N52 Rathconnell to Macetown Realignment (1.5km): Completion Sept. 2012
    N53 Road Improvement Scheme Barronstown to Newtownbalregan (3.5km): Completion ???
    N55 Dundavan to Mullaghoran Road Realignment Scheme (3km): Completion May 2013
    N87 Ballyconnell Relief Road (1.8km): Completion Aug. 2012 ???

    ‘Expected’ To Commence Construction During Final Quarter 2012
    N5 Ballaghadereen Bypass (13.5km): Contract To Be Awarded Sept. 2012
    N7/N11 Newlands Cross / Arklow-Rathnew (EIB/BoI PPP Funding) (N7/N11: 1.8km / 16.5km): Commencing October, 2012.

    Future PPP Schemes
    M17/18 Gort to Tuam (56.2km): Commencing 2013
    M11 and N25 Enniscorthy and New Ross Bypasses (43km): Commencing 2014


  • Registered Users Posts: 7,797 ✭✭✭munchkin_utd


    Completed 2012
    N5 Longford Bypass (2.6km): Opened Aug. 2012
    N55 Corduff Stage 3 Road Realignment Scheme (0.7km) Opened Aug. 31st 2012
    N87 Ballyconnell Relief Road (1.8km): Opened Aug. 31st 2012

    Under Construction 2012
    M1 Swords Improvement Scheme J3 (Drinan) to J4 (Lissenhall) (4km): Completion Dec. 2012
    N3 Belturbet Bypass (6.7km): Completion May 2013
    N4 The Downs Grade Separation (5km): Completion Dec. 2012
    M7/N24 Ballysimon Junction Improvements: Completion ???
    N17 Castletown Realignment (2.3km): Completion Oct. 2012
    N21 Killarney Pole to Barnagh Road Safety Scheme (3.4km): Completion ???
    N22/N69/N70 Tralee Bypass (13.5km): Completion April 2013
    N25 Cork Southern Ring Road Interchanges (3km): Completion July 2013
    N52 Carrick Bridge to Clonfad (Dalystown) (5.6km): Completion Dec. 2012
    N52 Rathconnell to Macetown Realignment (1.5km): Completion Sept. 2012
    N53 Road Improvement Scheme Barronstown to Newtownbalregan (3.5km): Completion ???
    N55 Dundavan to Mullaghoran Road Realignment Scheme (3km): Completion May 2013


    ‘Expected’ To Commence Construction During Final Quarter 2012
    N5 Ballaghadereen Bypass (13.5km): Contract To Be Awarded Sept. 2012
    N7/N11 Newlands Cross / Arklow-Rathnew (EIB/BoI PPP Funding) (N7/N11: 1.8km / 16.5km): Commencing October, 2012.

    Future PPP Schemes
    M17/18 Gort to Tuam (56.2km): Commencing 2013
    M11 and N25 Enniscorthy and New Ross Bypasses (43km): Commencing 2014


  • Moderators, Science, Health & Environment Moderators Posts: 4,917 Mod ✭✭✭✭spacetweek


    Why is "expected" in quotes? Are you a born cynic? :)


  • Registered Users Posts: 6,106 ✭✭✭antoobrien


    spacetweek wrote: »
    Why is "expected" in quotes? Are you a born cynic? :)

    In fairness how many times have we been told that NX/N11 will be starting "next quarter"?

    I think a lot of people are in the "I'll believe it when I see them digging" camp when it comes to a lot of these projects.


  • Advertisement
  • Registered Users Posts: 272 ✭✭Goofy


    Under Construction 2012
    M7/N24 Ballysimon Junction Improvements: Completion ???

    I drove through this a week or 2 ago and it looks complete to me.


  • Moderators, Science, Health & Environment Moderators Posts: 4,917 Mod ✭✭✭✭spacetweek


    Following from a post in a different thread, i've gone over my own records and noticed that the following schemes were all suspended in 2011 but have since been reactivated:

    N2 Slane BP [note: refused PP but will likely be re-submitted]
    N3 North of Kells - Cavan [surprised by this; doesn't seem very important]
    N4 Collooney / Castlebaldwin [note: planned as SC instead of dual]
    N5/N26/N58 Turlough to Bohola
    N5 Westport to Turlough
    M7 Naas - Newbridge 4 to 6 lanes
    N8 Jct 19 Dunkettle Interchange
    N11/N25 Oilgate to Rosslare Harbour
    N17 Collooney to Tobercurry
    N21 Adare BP
    N22 Ballyvourney to Macroom
    N24 Pallasgreen to Cahir
    N25 Waterford to Glenmore
    N52 Ardee Bypass
    N56 Dungloe to Glenties (one part already u/c)
    N56 Mountcharles to Inver
    N59 Clifden to Oughterard
    N59 Moycullen Bypass
    N59 Westport to Mulranny
    N69 Listowel By Pass
    N81 Tallaght to Hollywood Cross
    N86 Tralee to An Daingean

    N6 Jct 20-22 Galway City Outer BP [note: still marked as suspended but likely to be reactivated once court battle is over]


  • Moderators, Science, Health & Environment Moderators Posts: 4,917 Mod ✭✭✭✭spacetweek


    Just for the record, the following are still suspended but strongly needed:
    N4 Mullingar - Longford - Rooskey
    N4 Carrick on Shannon to Dromod
    N14 Letterkenny to Lifford
    N15 Ballybofey / Stranorlar Bypass
    M20 Limerick-Cork (Northern Section)
    M20 Limerick-Cork (Southern Section)
    N21 Adare to Abbeyfeale
    N22 Cork Northern Ring Road (M8-M20)
    N24 Carrick-on-Suir BP
    N25 Carrigtwohill to Midleton
    N28 Ringaskiddy to Cork


  • Registered Users Posts: 77 ✭✭tomflynn


    Completed 2012
    N2 Monaghan to Emyvale Phase 1
    N5 Longford Bypass
    M7/N24 Ballysimon Junction Improvements
    N17 Castletown Realignment
    N52 Carrick Bridge to Clonfad (Dalystown)
    N52 Rathconnell to Macetown Realignment
    N55 Corduff Stage 3 Road Realignment Scheme
    N87 Ballyconnell Relief Road
    (and some other National Secondary Road Safety Realignment Schemes)

    Under Construction 2013
    M1 Swords Improvement Scheme J3 (Drinan) to J4 (Lissenhall) (4km)
    N2 Monaghan to Emyvale Phase 2 and 4 (c. 5km)
    N3 Belturbet Bypass (6.7km)
    N4 The Downs Grade Separation (5km)
    N5 Ballaghadereen Bypass (13.5km)
    N17 Carrownurlaur Realignment Scheme (1.4km)
    N21 Killarney Pole to Barnagh Road Safety Scheme (3.4km)
    N22/N69/N70 Tralee Bypass (13.5km)
    N40 Cork Southern Ring Road Interchanges (3km)
    N52 Congar to Ballyluskey (2.2km)
    N53 Road Improvement Scheme Barronstown to Newtownbalregan (3.5km)
    N55 Dundavan to Mullaghoran Road Realignment Scheme (3km)

    Commencing 2013? my own guesses tbc

    PPP Projects:
    N7/N11 Newlands Cross / Arklow-Rathnew (N7/N11: 1.8km / 16.5km)
    M17/M18 Gort to Tuam (56.2km)
    Both of the above PPP are 2013 Ministerial priorities; see point 4 via link.

    Other potential projects:
    M7 Widening Naas to M7/M9 Interchange ???
    M8/N8/N25/N40 Dunkettle Interchange ???
    N52 Ardee Bypass 4.5km ???
    N56 Scheme ???

    Definitely selection of Minor Works Schemes:
    Overrun from Minor Works Construction Starts 2012
    Progress to construction of Minor Works at Planning Stage 2012

    In terms of 2013 commencements I cannot see anything else at present.

    Corrections to any of the above (completed, under construction, commencements) most welcome.


  • Registered Users Posts: 6,106 ✭✭✭antoobrien


    The widening of the M9-N7 interchange looks to have started based on posts in the M7 thread and AAroadwatch traffic alert, probably worth adding.

    Should also add in the N67 improvement Ballinderreen - Kinvara was under construction last year (as of October, the last time I was out that direction, it was in construction).


  • Registered Users Posts: 728 ✭✭✭robert muldoon


    antoobrien wrote: »
    The widening of the M9-N7 interchange looks to have started based on posts in the M7 thread and AAroadwatch traffic alert, ptobably worth adding.

    Should also add in the N67 improvement Ballinderreen - Kinvara was under construction last year (as of October, the last time I was out that direction, it was in construction).

    Just as there is no confusion, the widening of the M9 - M7 interchange is a totally different project to the proposed widening of M7 to 3 lanes from Naas to M9, this project will probably commence this year in conjunction ot the new Kerry Foods development in Millenium Park as I believe it's part of the deal


  • Registered Users Posts: 5,517 ✭✭✭veryangryman


    Now that we have some projects upcoming or under construction, is it worth renaming the thread to include estimates for completion dates?


  • Moderators, Business & Finance Moderators, Motoring & Transport Moderators, Society & Culture Moderators Posts: 67,098 Mod ✭✭✭✭L1011


    Now that we have some projects upcoming or under construction, is it worth renaming the thread to include estimates for completion dates?

    Yes.

    Its quite outdated as it stands - one of the projects is complete at this stage!


  • Registered Users Posts: 728 ✭✭✭robert muldoon


    I heard yesterday that the purchase of lands for the bye pass of Sallins is near conclusion,this all links in to the widening of M7 to M9

    anyone else hear anything on this project?


  • Moderators, Science, Health & Environment Moderators Posts: 4,917 Mod ✭✭✭✭spacetweek


    I heard yesterday that the purchase of lands for the bye pass of Sallins is near conclusion,this all links in to the widening of M7 to M9

    anyone else hear anything on this project?
    Nope, but the Osberstown interchange (used be called Millennium Park) is apparently going to be part of it, according to Kildare Co Co.


  • Advertisement
  • Registered Users Posts: 783 ✭✭✭mydiscworld


    Do we have an up-to-date list of all projects

    - under construction

    - with full planning permission, awaiting funding to commence

    - part planned/on hold pending further Government decision ?


  • Registered Users Posts: 77 ✭✭tomflynn


    Completed 2013
    M1 Swords Improvement Scheme J3 (Drinan) to J4 (Lissenhall)
    N2 Monaghan to Emyvale Phase 2 and 4
    N3 Belturbet Bypass
    N4 The Downs Grade Separation
    M7/M9 Interchange Widening
    N17 Carrownurlaur Realignment Scheme
    N21 Barnagh to Killarney Pole Phase 1 (Barnagh to Garryduff Cross).
    N22/N69/N70 Tralee Bypass
    N52 Congar to Ballyluskey
    N53 Road Improvement Scheme Barronstown to Newtownbalregan
    N55 Dundavan to Mullaghoran Road Realignment Scheme
    N59 Westport to Mulranny (Kilbride)
    N67 Ballinderreen - Kinvara Phase 1
    N87 Ballyconnell Relief Road
    (Some other local realignments)

    Under Construction 2014
    N5 Ballaghadereen Bypass (13.5km)
    N40 Cork Southern Ring Road Interchanges (3km)
    N7/N11 Newlands Cross / Arklow-Rathnew (N7/N11: 1.8km / 16.5km)
    Some other minor realignments? please fill in the gaps

    Commencing 2014
    M17/M18 Gort to Tuam PPP (56.2km) - sometime 2014, prior to local elections.

    Other projects 2014-2016
    :
    N25 New Ross Bypass PPP (contract signing 2015?)
    M11 Gorey to Enniscorthy PPP

    Other potential projects 2014-2016
    M7 Widening Naas to M7/M9 Interchange (2015 post Newlands Cross Upgrade?)
    M8/N8/N25/N40 Dunkettle Interchange
    N4 Collooney to Castlebaldwin
    N5 Westport to Turlough (perhaps a N4/N5 PPP Bundle prior to GE 2016)
    N6 Galway City Outer Bypass
    N28 Cork to Ringaskiddy (EU funding)
    N69 Limerick to Foynes (EU funding)

    Smaller Schemes
    N52 Ardee Bypass
    N56 Scheme Phase(s) (e.g. Mountcharles to Drumbeigh)
    N59 Scheme Phase(s)
    N67 Scheme Phase(s)
    N21 Barnagh to Killarney Pole Phase 2
    N52 Cloghan to Billistown
    Other minor safety realignments


  • Registered Users Posts: 4,663 ✭✭✭serfboard


    Thanks for the list. Shouldn't the N40 be marked as completed, though?


  • Moderators, Business & Finance Moderators, Motoring & Transport Moderators, Society & Culture Moderators Posts: 67,098 Mod ✭✭✭✭L1011


    I would expect the next phase of the Dungloe-Glenties N56 project to go to tender imminently, it was meant to late last year. Land is CPOed and extensive geotech work has been done. This is the hardest section of the route and the most badly needed, as its bypassing the Gweebarra Bends.


  • Registered Users Posts: 19,369 ✭✭✭✭road_high


    Add the N77 Ballynaslee realignment to that between Durrow and Ballyraggett Co. Kilkenny. Started in November '13.


  • Registered Users Posts: 4,098 ✭✭✭rameire


    N78 Athy Southern Distributor road has been given the green light
    The monies, from the Dept. of Public Expenditure and Dept. of Transport, will be released in a phased basis.

    is likely to cost €32 million.

    may have to wait a couple of years though

    Martin Heydon, says
    "the commitment is not only there to give ,money to Kildare County Council to progress the detailed design and go to planning, but also to have the money in place for 2015 and 2016, to see the road completed in full

    🌞 3.8kwp, 🌞 Split 2.28S, 1.52E. 🌞 Clonee, Dub.🌞



  • Registered Users Posts: 19,369 ✭✭✭✭road_high


    rameire wrote: »
    N78 Athy Southern Distributor road has been given the green light
    The monies, from the Dept. of Public Expenditure and Dept. of Transport, will be released in a phased basis.

    is likely to cost €32 million.

    may have to wait a couple of years though

    Martin Heydon, says

    Screams election stunt to me. Been talking about this for years and no action. They make an announcement and nothing happens for years. I hope I'm wrong of course :(


  • Registered Users Posts: 4,098 ✭✭✭rameire


    it does, but I hope.

    🌞 3.8kwp, 🌞 Split 2.28S, 1.52E. 🌞 Clonee, Dub.🌞



  • Registered Users Posts: 78,218 ✭✭✭✭Victor


    What should this thread be re-named to?

    Moderator


  • Advertisement
  • Moderators, Business & Finance Moderators, Motoring & Transport Moderators, Society & Culture Moderators Posts: 67,098 Mod ✭✭✭✭L1011


    START DATES: M17/M18 FINISH DATES: M11 N5 N7 N25 possibly? We did have finish dates in the past when we actually had road schemes worth waiting for...