Terminal 2 - Budget €200MIL , Cost €600MIL

  • 19-11-2010 09:22AM
    #1
    Registered Users, Registered Users 2 Posts: 175 ✭✭


    Want to know what people think of the news report this morning of the official opening of Terminal 2 and it's final cost of €600M, €400M over budget!!!

    How can such a project run so far over budget?

    I would like to hear from ye why and how this happened.

    EDIT: Jaysus u r right I would do the same, LOL!! Whoops forgot a few million there!!


«13

Comments

  • Registered Users, Subscribers, Registered Users 2 Posts: 13,722 ✭✭✭✭antodeco


    Want to know what people think of the news report this morning of the official opening of Terminal 2 and it's final cost of €600, €400 over budget!!!

    Jaysus, ill gladly build a terminal in my garden for €600. Bought a shed recently, and was nearly €800!


  • Banned (with Prison Access) Posts: 3,073 ✭✭✭mickoneill30


    From this Google cached content a couple of years ago they budgeted €600m.

    http://webcache.googleusercontent.com/search?q=cache:CtPVkkhL56UJ:www.dublinairport.com/about-us/airport-development/Terminal_2.html+daa+terminal+2&cd=3&hl=en&ct=clnk&gl=ie&client=firefox-a

    Which news report did you get the €200m from? Even O'Leary was saying they spent twice as much at €1.2b to get more airtime for Ryanair. If it was originally budgeted at €200m and it cost €600m I'd imagine he'd be all over it to help him advertise his company.


  • Registered Users, Registered Users 2 Posts: 175 ✭✭lyndonjones


    From this Google cached content a couple of years ago they budgeted €600m.

    http://webcache.googleusercontent.com/search?q=cache:CtPVkkhL56UJ:www.dublinairport.com/about-us/airport-development/Terminal_2.html+daa+terminal+2&cd=3&hl=en&ct=clnk&gl=ie&client=firefox-a

    Which news report did you get the €200m from? Even O'Leary was saying they spent twice as much at €1.2b to get more airtime for Ryanair. If it was originally budgeted at €200m and it cost €600m I'd imagine he'd be all over it to help him advertise Ryanair.

    RTE Morning Ireland stated the original budget at €200M+

    Even this web site, in 2007, states the how over budget it was running...

    http://www.finfacts.ie/irelandbusinessnews/publish/article_10007100.shtml


  • Registered Users, Registered Users 2 Posts: 13,244 ✭✭✭✭bnt


    TO cut a long story short: initial budgets are based on what you know at the time. A team of quantity surveyors plans out every job, every piece of gear, and what they cost. A hole costs €x to dig, a wall costs €y to put up, a crane costs €z per day, and so on. Then the building starts: there are unforeseen problems, things take longer than expected, they find weird ground conditions, and pretty soon the original schedule is a faint memory. If a team of builders can't get to the place where they're supposed to be building something, just because another job is running late, they still have to get paid.

    It's all about the planning: the better the planning, and the more you know going in, the fewer problems you'll have. So, if the original plans had a budget of €200 million ... the original plans were inadequate. :rolleyes:

    Government resting upon the will and universal suffrage of the people has no anchorage except in the people's intelligence.

    — Grover Cleveland



  • Registered Users, Registered Users 2 Posts: 1,797 ✭✭✭ChopShop


    There was no way it was ever going to cost 200M.


  • Advertisement
  • Closed Accounts Posts: 8,702 ✭✭✭squod


    bnt wrote: »
    TO cut a long story short: initial budgets are based on what you know at the time. A team of quantity surveyors plans out every job, every piece of gear, and what they cost. A hole costs €x to dig, a wall costs €y to put up, a crane costs €z per day, and so on. Then the building starts: there are unforeseen problems, things take longer than expected, they find weird ground conditions, and pretty soon the original schedule is a faint memory. If a team of builders can't get to the place where they're supposed to be building something, just because another job is running late, they still have to get paid.

    It's all about the planning: the better the planning, and the more you know going in, the fewer problems you'll have. So, if the original plans had a budget of €200 million ... the original plans were inadequate. :rolleyes:

    Actual reason; because they could!


  • Closed Accounts Posts: 844 ✭✭✭Elevator


    and to think O Leary was going to build it at no cost to the state but no fianna fail had to please DAA so they cold look after all their buddies with contracts and backhanders from the €600,000,000+!!

    the very sight of the new terminal nearly ruined my holiday last week


  • Closed Accounts Posts: 8,702 ✭✭✭squod


    Elevator wrote: »
    and to think O Leary was going to build it at no cost to the state but no fianna fail had to please DAA so they cold look after all their buddies with contracts and backhanders from the €600,000,000+!!

    the very sight of the new terminal nearly ruined my holiday last week

    Fly from Belfast like I do.


  • Closed Accounts Posts: 17,916 ✭✭✭✭orourkeda


    squod wrote: »
    Fly from Belfast like I do.

    no


  • Closed Accounts Posts: 844 ✭✭✭Elevator


    squod wrote: »
    Fly from Belfast like I do.

    Galway to dublin is too handy tho!


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 175 ✭✭lyndonjones


    bnt wrote: »
    TO cut a long story short: initial budgets are based on what you know at the time. A team of quantity surveyors plans out every job, every piece of gear, and what they cost. A hole costs €x to dig, a wall costs €y to put up, a crane costs €z per day, and so on. Then the building starts: there are unforeseen problems, things take longer than expected, they find weird ground conditions, and pretty soon the original schedule is a faint memory. If a team of builders can't get to the place where they're supposed to be building something, just because another job is running late, they still have to get paid.

    It's all about the planning: the better the planning, and the more you know going in, the fewer problems you'll have. So, if the original plans had a budget of €200 million ... the original plans were inadequate. :rolleyes:

    Appreciate what you are saying but when you tender for a contract that figure should be realistic and have only a small amount of leeway for the unforseen issues as you mention

    This looks like a blank cheque was handed out.

    So who is at fault for the planning - DAA, Government?


  • Closed Accounts Posts: 20,009 ✭✭✭✭Run_to_da_hills


    Terminal 2: Built just on time to impress the IMF. :p


  • Closed Accounts Posts: 355 ✭✭GizAGoOfYerGee


    Has anyone actually been inside the new terminal? I have and it is incredible. It certainly looks like it cost 600m!

    Check out the bar for fecks sake. The couches cost €15,000 alone.

    http://www.independent.ie/multimedia/archive/00742/Aoife-09_I_742431s.jpg

    http://www.irishtimes.com/newspaper/images/2010/1119/1224283711308_1.jpg


  • Registered Users, Registered Users 2 Posts: 1,825 ✭✭✭Fart


    Has anyone actually been inside the new terminal? I have and it is incredible. It certainly looks like it cost 600m!

    Check out the bar for fecks sake. The couches cost €15,000 alone.

    http://www.independent.ie/multimedia/archive/00742/Aoife-09_I_742431s.jpg

    http://www.irishtimes.com/newspaper/images/2010/1119/1224283711308_1.jpg

    Phwoar!!!


  • Closed Accounts Posts: 8,594 ✭✭✭bonerm


    When did a construction project in this country ever come in on tender?


  • Closed Accounts Posts: 20,009 ✭✭✭✭Run_to_da_hills


    bonerm wrote: »
    When did a construction project in this country ever come in on tender?
    Most of the interconnectors in the country have come on time and within budget.


  • Closed Accounts Posts: 355 ✭✭GizAGoOfYerGee


    bonerm wrote: »
    When did a construction project in this country ever come in on tender?

    Luas Cherrywood.


  • Registered Users, Registered Users 2 Posts: 4,532 ✭✭✭WolfForager


    That is one pretty interior...


  • Closed Accounts Posts: 7,872 ✭✭✭strobe


    Money well spent in my opinion. I mean the scene with Arnie standing in the window of the office blasting all the cop cars to bits alone would have made it worth it. Plus the CGI was as good as anything put out today and it was made way back in '91. I dunno, some people will complain about anything.....


  • Closed Accounts Posts: 6,942 ✭✭✭missingtime


    Has anyone actually been inside the new terminal? I have and it is incredible. It certainly looks like it cost 600m!

    Check out the bar for fecks sake. The couches cost €15,000 alone.

    There is your answer right there op


  • Advertisement
  • Closed Accounts Posts: 9,273 ✭✭✭Morlar


    http://breakingnews.ie/ireland/oleary-disputes-cost-of-new-airport-terminal-482399.html

    Ryanair boss Michael O'Leary is still disputing the DAA's figures for the overall cost of Terminal 2.

    The Dublin Airport Authority said the project cost €600m but Michael O' Leary has said that is not the case and the overall cost is €1.2bn.

    The new terminal will be officially opened by the Taoiseach Brian Cowen later this morning with the first flight arriving in later.


  • Registered Users, Registered Users 2 Posts: 1,222 ✭✭✭bigneacy


    just be glad they weren't building a bank....


  • Registered Users, Registered Users 2 Posts: 20,396 ✭✭✭✭FreudianSlippers


    Millions. lol. Let's not worry about the small stuff at the moment eh?


  • Closed Accounts Posts: 844 ✭✭✭Elevator


    couches at 15,000 a pop!!!

    first thing I'm doing when I set foot in the terminal 2 building is slashing holes in their seating in silent protest and I'd urge everyone else that sets foot in the place to do the same!!

    they might think it's cool to refuse O' Learys offer of a free terminal 2 and blatently throw away tax payers money wrecklessly and that the public won't care

    how in...

    what the...

    who the...

    no, I am fcukin speechless here

    who signed off on this!?!


  • Registered Users, Registered Users 2 Posts: 20,396 ✭✭✭✭FreudianSlippers


    Elevator wrote: »
    couches at 15,000 a pop!!!

    first thing I'm doing when I set foot in the terminal 2 building is slashing holes in their seating in silent protest and I'd urge everyone else that sets foot in the place to do the same!!

    they might think it's cool to refuse O' Learys offer of a free terminal 2 and blatently throw away tax payers money wrecklessly and that the public won't care

    how in...

    what the...

    who the...

    no, I am fcukin speechless here

    who signed off on this!?!
    So that they have to spend extra money buying new couches.

    It is idiocy like this that has put us in the trouble we are in. How is petty vandalism going to solve anything?


  • Registered Users, Registered Users 2 Posts: 1,222 ✭✭✭bigneacy


    OisinT wrote: »
    It is idiocy like this that has put us in the trouble we are in.

    No. Its not.

    Its idiocy like this:
    Elevator wrote: »
    refuse O' Learys offer of a free terminal 2 and blatently throw away tax payers money wrecklessly


  • Posts: 26,920 ✭✭✭✭ [Deleted User]


    You think this is pathetic? Eyre Square in Galway was a much larger fiasco - took years to complete and ran way over budget.


  • Closed Accounts Posts: 4,444 ✭✭✭Absurdum


    The couches cost €15,000 alone.

    have you got a link for that?

    (not disputing it btw, just curious...)


  • Closed Accounts Posts: 7,395 ✭✭✭Paparazzo


    €600m and it looks like a crotch


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 334 ✭✭KazDub


    T2 wasn't paid out of our (tax payers) money. I've heard it again and again on the radio, the DAA doesn't take money out of the exchequer but does put millions in. It's their own money (loans, whatever) that paid for the terminal, and those fierce swanky looking couches!