Current Infrastructure Projects Progress

  • 21-01-2010 1:48am
    #1
    Registered Users Posts: 1,104 ✭✭✭


    Below is a list of the expected opening dates for major schemes on the island of Ireland in increasing chronoligcal order:

    -2010

    31 March - M9: Waterford/Knocktopher
    Project Revised Completion Date (NRA) - End Q1

    31 March - M7: Nenagh-Limerick
    Project Revised Completion Date (NRA) - End Q1

    31 March - A4/A5: Realignments Annaghilla/Tullyvar
    Project Revised Completion Date (NIRS) - End March

    30 April - A26: Ballee Road East-M2 direct link, Ballymena
    Project Scheduled Completion Date (NIRS) - End April

    31 May - M7: Limerick Tunnel (LSRR Phase 2)
    Project Revised Completion Date (link) from End 2010

    31 August - A1: Beech Hill-Cloghogue (Newry Bypass)
    Project Revised Completion Date (link) from End 2010

    30 September - M3: Clonee/North of Kells
    Project Scheduled Completion Date (NRA) - End Q3

    30 September - M7: Castletown-Nenagh
    Project Revised Completion Date (NRA) - End Q3

    30 November - A2: Maydown-Derry airport
    Project Scheduled Completion Date (NIRS)

    30 November - A29: realignment, Carland
    Project Scheduled Completion Date (NIRS)

    31 December - M8: Portlaoise-Cullahill/Castletown
    Project Scheduled Completion Date (NRA) - End Q4

    31 December - M9: Carlow/Knocktopher
    Project Scheduled Completion Date (NRA) - End Q4

    31 December - M50: Upgrade Phase 2
    Project Scheduled Completion Date (NRA) - End Q4

    31 December - A4: Dungannon-Ballygawley
    Project Scheduled Completion Date (NIRS) - End Q4

    -2011

    31 March - N21: Castleisland Bypass
    Project Scheduled Completion Date (NRA) - End Q1

    30 June - M18: Gort-Crusheen
    Project Scheduled Completion Date (NRA) - End Q2

    I have used mainly the NRA & Wes Johnston;s NIRS site.
    Its a WIP, feel free to post any links with revised opening dates, or highlight any errors :D


Comments

  • Closed Accounts Posts: 454 ✭✭irishdub14


    whoo!! first one to post on infrastructure since downtime!! :):D


  • Registered Users Posts: 1,104 ✭✭✭nordydan


    Any chance of stickying this? I see there was already a thread started on the M9 just to ask for the completion date