Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Current Infrastructure Projects Progress

  • 21-01-2010 1:48am
    #1
    Registered Users, Registered Users 2 Posts: 1,107 ✭✭✭


    Below is a list of the expected opening dates for major schemes on the island of Ireland in increasing chronoligcal order:

    -2010

    31 March - M9: Waterford/Knocktopher
    Project Revised Completion Date (NRA) - End Q1

    31 March - M7: Nenagh-Limerick
    Project Revised Completion Date (NRA) - End Q1

    31 March - A4/A5: Realignments Annaghilla/Tullyvar
    Project Revised Completion Date (NIRS) - End March

    30 April - A26: Ballee Road East-M2 direct link, Ballymena
    Project Scheduled Completion Date (NIRS) - End April

    31 May - M7: Limerick Tunnel (LSRR Phase 2)
    Project Revised Completion Date (link) from End 2010

    31 August - A1: Beech Hill-Cloghogue (Newry Bypass)
    Project Revised Completion Date (link) from End 2010

    30 September - M3: Clonee/North of Kells
    Project Scheduled Completion Date (NRA) - End Q3

    30 September - M7: Castletown-Nenagh
    Project Revised Completion Date (NRA) - End Q3

    30 November - A2: Maydown-Derry airport
    Project Scheduled Completion Date (NIRS)

    30 November - A29: realignment, Carland
    Project Scheduled Completion Date (NIRS)

    31 December - M8: Portlaoise-Cullahill/Castletown
    Project Scheduled Completion Date (NRA) - End Q4

    31 December - M9: Carlow/Knocktopher
    Project Scheduled Completion Date (NRA) - End Q4

    31 December - M50: Upgrade Phase 2
    Project Scheduled Completion Date (NRA) - End Q4

    31 December - A4: Dungannon-Ballygawley
    Project Scheduled Completion Date (NIRS) - End Q4

    -2011

    31 March - N21: Castleisland Bypass
    Project Scheduled Completion Date (NRA) - End Q1

    30 June - M18: Gort-Crusheen
    Project Scheduled Completion Date (NRA) - End Q2

    I have used mainly the NRA & Wes Johnston;s NIRS site.
    Its a WIP, feel free to post any links with revised opening dates, or highlight any errors :D


Comments

  • Closed Accounts Posts: 454 ✭✭irishdub14


    whoo!! first one to post on infrastructure since downtime!! :):D


  • Registered Users, Registered Users 2 Posts: 1,107 ✭✭✭nordydan


    Any chance of stickying this? I see there was already a thread started on the M9 just to ask for the completion date


Advertisement