Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Cost of a House

  • 09-10-2016 5:09pm
    #1
    Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭


    There are plenty of people asking questions left, right and centre on this section of boards about how much this or that will cost.

    Here is the price of a house in the Midwest Region of Ireland. This was not the lowest returned tender: in fact it was 2nd with the 3rd only €2.5k out.

    The project involves the construction of a two storey dwelling, new garage, septic tank and percolation area and all associated site-works.

    Total cost of the house was €361k including Vat @ 13.5%

    Floor area was 2444 sq. ft so €148/SQ Ft including VAT and €130/SQ FT ex VAT

    If you take the Garage out it becomes €121 sq/ft ex vat and €136 sq/ft incl Vat.

    The building is broken down as follows:

    (06) PRELIMINARIES €17,000.00
    (19) SUBSTRUCTURE €33,072.80
    (21) EXTERNAL WALLS €39,493.05
    (22) INTERNAL WALLS €3,865.50
    (23) FLOORS €6,178.50
    (24) STAIRS, RAMPS €10,500.00
    (27) ROOFS €12,502.72
    (31) EXTERNAL WALL COMPLETIONS €16,363.00
    (32) INTERNAL WALL COMPLETIONS €10,300.50
    (37) ROOF COMPLETIONS €934.40
    (41) WALL FINISHES EXTERNALLY €10,474.85
    (42) WALL FINISHES INTERNALLY €13,773.10
    (45) CEILING FINISHES €6,334.90
    (47) ROOF FINISHES €20,009.10
    (59) BUILDING SERVICES - (MAINLY PIPED & DUCTED) €32,300.00
    (69) BUILDING SERVICES - (MAINLY ELECTRICAL) €11,000.00
    (30) SITE ENCLOSURES €17,367.20
    (40) ROADS, PATHS PAVINGS €7,806.55
    (50) SITE SERVICES - (MAINLY PIPED & DUCTED) €23,660.30
    (69) SITE SERVICES - (MAINLY ELECTRICAL) €1,025.00
    GARAGE

    Subtotal €293,961.47
    VAT@ 13.5% €39,684.80
    Total €333,646.27


    Please note these are pure build costs only.
    They are for your information only. I will not accept any liability for the reliance on the information herein.. if you chose to act on any of this information you are aware that you are taking this risk.


Comments

  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (06) PRELIMINARIES

    PROJECT

    The project involves the construction of a two storey dwelling, new garage, septic tank and percolation area and all associated site-works

    The total internal floor area of the proposed dwelling is 227sqm (2444sq ft)



    PRELIMINARIES

    Allow for all preliminary costs associated with this project as per pricing document summery to include: 1.00 Item 17,000.00 17,000.00

    ^^^Site Supervision/Foreman

    ^^^Scaffolding

    ^^^Facilities & Obligations on site

    ^^^All Health & Safety Requirements incl PSCS

    ^^^All public and employer insurances


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (19) SUBSTRUCTURE
    (19) SUBSTRUCTURE

    EXCAVATIONS & EARTHWORKS

    EXCAVATIONS

    Topsoil

    ^^^Average depth 150mm 293.00 m2 2.00 586.00

    Reduced level

    Generally

    ^^^Average depth < or = 2m 70.00 m3 5.95 416.50

    Foundation Trenches

    Generally

    ^^^Average depth < or = 2m 58.00 m3 5.95 345.10

    Disposal

    Excavated Material

    ^^^Deposit excavated material off site 127.00 m3 15.00 1,905.00

    Filling

    Imported material; crushed limestone to clause 804 of the DOE specification for granular sub base materials; compacting in 150mm thick layers

    Make up levels

    ^^^excavations < or = 250mm 10.00 m3 22.40 224.00

    ^^^underside of concrete floor slab < or = 250mm 41.00 m3 22.40 918.40

    Surface Treatments

    Blinding Filling

    Sand blinding laid and compacted on hardcore filling

    ^^^25mm th 128.00 m2 1.00 128.00



    CONCRETE WORK

    INSITU CONCRETE

    Blinding

    ^^^50mm sand / cement blinding to underside of the foundations 7.00 m3 87.00 609.00

    Filling

    Concrete filling to cavities with sand and cement mix

    ^^^150mm wide 9.00 m3 87.00 783.00

    Foundations

    C30N reinforced concrete foundations; poured on or against earth of unblinded hardcore

    ^^^Generally 39.00 m3 95.50 3,724.50

    Sub Floor Slab

    C30/20N concrete floor slab; poured on radon barrier

    ^^^< or = 150mm th 20.00 m3 95.50 1,910.00

    Screed

    C30/20N concrete floor screed; poured on insulation

    ^^^< or = 150mm th 96.00 m3 95.50 9,168.00

    Surface Finishes

    ^^^Generally 128.00 m2 3.00 384.00

    Reinforcement

    Fabric

    ^^^Grade A393 mesh to concrete strip foundations 128.00 m2 8.00 1,024.00

    ^^^Grade A142 mesh to concrete floor slabs 255.00 m2 4.00 1,020.00



    BRICKWORK & BLOCKWORK

    BLOCKWORK

    Walls in Trenches

    Solid concrete load bearing blockwork to IS 20 Type A having limestone aggregate and a compressive strength of 5N/mm2 bedded and jointed in premixed mortor; tied together using stainless steel wall ties @ 750mm c/c horizontally and 450mm vertically

    ^^^100mm th 29.00 m2 18.00 522.00

    ^^^350mm th 76.00 m2 38.00 2,888.00

    Extra over on blockwork for:

    ^^^Quinlite B7 thermal blockS; 1no row of 100mm thick block. 121.00 m 10.00 1,210.00

    ANCILLERIES TO BLOCKWORK

    Forming Cavities

    Between new walls

    ^^^125mm wide 76.00 m2 2.00 152.00

    Damp Proof Courses

    DPC; horizontal; with 100mm minimum laps

    ^^^width < or = 225mm 209.00 m 0.50 104.50

    SUNDRIES

    Damp Proof Membrane

    Monarflex RMB 400 radon barrier laid on sand blinding with 400mm sealed laps at all joints and turned up at floor and wall junction and carried across cavity; installed in strict accordance with the manufacture instructions

    ^^^Horizontal > 300mm 166.00 m2 5.40 896.40

    ^^^Vertical < or = 300mm 54.00 m2 5.40 291.60

    Insulation

    Xtratherm XT / UF rigid insulation; foil faced; laid in accordance with manufactures instructions

    ^^^120mm th 128.00 m2 18.30 2,342.40

    Rigid foil faced PIR insulation to all door opes; in accordance with manufacturers instructions

    ^^^50mm th 11.00 m 7.00 77.00

    Rigid foil board insulation to floor slab perimeter to prevent cold bridging

    ^^^30mm th 89.00 m 5.00 445.00

    Builders Work

    ^^^Forming or cutting holes in 350mm th blockwork; including all required lintels as necessary 4.00 nr 30.00 120.00



    RADON INSTALLATION

    Excavations & Earthworks

    Excavating Trenches to receive pipework

    ^^^Average depth 500 - 1000mm 8.00 m 4.00 32.00

    Beds & Surrounds

    Type 1 granular material bed and surround to 100mm diameter pipework

    ^^^450 x 450mm 8.00 m 3.00 24.00

    Pipes

    uPVC pipework spigot and socket jointed laid in trenches

    ^^^100mm diameter 8.00 m 7.50 60.00

    Extra over on pipes for which they occur

    Fittings

    ^^^90 degree bends to suit 100mm diameter pipework 2.00 nr 12.00 24.00

    ^^^Cowel/capping piece to suite 100mm diameter pipework 2.00 nr 8.00 16.00

    SUNDRIES

    Plant & Equipment

    Radon Sumps

    ^^^Approved radon sumps; including all excavations and fixing complete 2.00 nr 100.00 200.00

    Builders Work

    ^^^Forming or cutting holes in 310mm th blockwork; including all required lintels as necessary 2.00 nr 30.00 60.00



    AIR DUCTS FOR STOVE

    Pipes

    ^^^150mm uPVC pipe; spigot and socket jointed; laid in trenches 6.00 m 7.80 46.80

    ^^^150mm uPVC pipe; spigot and socket jointed; vertical 2.00 m 7.80 15.60

    Pipe Accessories

    ^^^easy sweep bends 2.00 nr 12.00 24.00

    ^^^galvanised steel grill cover 2.00 nr 8.00 16.00

    Sundries

    Builders Work

    ^^^Forming or cutting ope in 350mm th blockwork to 100mm diameter pipes; including all required lintels 2.00 nr 30.00 60.00



    UNDERGROUND DRAINAGE

    Builders Work

    ^^^Contractor to allow for all necessary underground drainage 1.00 Item 300.00 300.00



    (19) SUBSTRUCTURE 33,072.80


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (21) EXTERNAL WALLS
    CONCRETE WORK

    INSITU CONCRETE

    Threshold

    Concrete threshold details; complete with drip detail; wrapped in and including DPC; including all formwork and fixing complete; all in accordance with the Architects details

    ^^^200 x 200mm 6.00 m 28.00 168.00

    Chimney Caps

    Concrete chimney cap; reinforced concrete; throating around full perimeter; including all formwork and fixing complete; all in accordance with Architects details

    ^^^1700 x 750mm 1.00 m3 175.00 175.00

    ^^^1500 x 750mm 1.00 m3 175.00 175.00

    PRECAST CONCRETE

    Lintels

    Precast prestressed concrete lintels; bedded and jointed in premix mortor; 200mm bearing to eachside of opening

    ^^^140 x 100mm 41.00 m 9.00 369.00

    ^^^140 x 140mm 47.00 m 15.00 705.00

    Threshold

    Concrete threshold; wrapped in and including DPC; all in accordance with the Architects details

    ^^^100 x 350mm 6.00 m 15.00 90.00

    Cills

    Precast concrete deep faced cills; centrally placed and neatly and finely finished; bedded and jointed in premixed mortor; projecting 100mm to each side of opening

    ^^^325 x 75mm 31.00 m 15.00 465.00



    BRICKWORK & BLOCKWORK

    BLOCKWORK

    Walls

    Solid concrete load bearing blockwork to IS 20 Type A having limestone aggregate and a compressive strength of 5N/mm2 bedded and jointed in premixed mortor; tied together using stainless steel wall ties @ 750mm c/c horizontally and 450mm vertically

    ^^^350mm th 357.00 m2 38.00 13,566.00

    Extra over on blockwork for:

    ^^^Quinlite B3 thermal blockS; 1no row of 100mm thick block. 17.00 m 10.00 170.00

    CHIMNEYS

    Generally

    Solid concrete blocks; dense aggregate; size 400x215x100; solid stretcher bond; bedding and jointing in cement mortar (1:6); flush pointing

    ^^^400mm th 28.00 m2 75.00 2,100.00

    Liners

    Schiedel ceramic chimney flue liner fitted in accordance with the manufactures instructions;

    ^^^Spigot and socket; 200mm diameter 15.00 m 28.00 420.00

    Flashings

    Code 5 lead chimney tray flue op- 1no; 50mm upstand to sides and edge; incorporating drainage facility and integral lead flashing

    ^^^150-300mm girth 2.00 nr 35.00 70.00

    ANCILLERIES TO BLOCKWORK

    Forming Cavities

    Between new walls

    ^^^150mm wide 357.00 m2 2.00 714.00

    Closing cavities

    Jambs with "L" blocks

    ^^^150mm wide 112.00 m 4.00 448.00

    Top of wall with slate cavity closer

    ^^^150mm wide 91.00 m 6.00 546.00

    Bed reinforcement to all window and door opes

    ^^^width < or = 225mm 546.00 m 14.00 7,644.00

    Damp Proof Courses

    Stepped DPC cavity tray over window opes;

    ^^^width >225mm 29.00 m2 15.00 435.00

    Vertical DPC to external wall corners

    ^^^width > 225mm 19.00 m2 15.00 285.00

    Horizontal to cills; with 100mm minimum laps

    ^^^width > 225mm 13.00 m2 1.00 13.00

    Vertical to jambs; with 100mm minimum laps

    ^^^width < or = 225mm 112.00 m 0.50 56.00

    SUNDRIES

    Insulation

    Xtratherm Cavity Therm PIR full fill cavity insulation; fitted in accordance with manufacturers instructions

    ^^^145mm thick 357.00 m2 18.25 6,515.25

    Xtratherm Close-R cavity closer; fitted in accordance with manufactures instructions

    ^^^100 x 100mm 100.00 m 8.00 800.00

    ^^^100 x 125mm 31.00 m 10.00 310.00

    ^^^100 x 140mm 56.00 m 12.00 672.00

    Cavitytherm preformed insulated cavity tray channel; fitted in accordance with manufacturers instructions; as per drawing 608

    ^^^150mm thick cavity 17.00 m



    STRUCTURAL STEELWORK

    Lintels

    Steelite lintels as per engineers drawings and specification

    ^^^350mm wide 15.00 m 110.00 1,650.00



    AIRTIGHTNESS

    MEMBRANES

    Pro-clima Intello Plus or equivalent airtightness membrane fixed between joists and plasterboard and Concrete slab and plasterboard with all joints taped with Pro-clima Uni tape

    ^^^> 300mm 3.00 m2 8.00 24.00

    Generally

    SIGA Fentrim IS2 tapes to be applied to all external window and door surrounds to achieve airtightness requirements

    ^^^< or = 300mm 178.00 m 5.10 907.80



    (21) EXTERNAL WALLS 39,493.05


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (22) INTERNAL WALLS
    CONCRETE WORK

    PRECAST CONCRETE

    Lintels

    Precast prestressed concrete lintels; bedded and jointed in premix mortor; 200mm bearing to eachside of opening

    ^^^100 x 75mm 21.00 m 7.50 157.50



    BRICKWORK & BLOCKWORK

    BLOCKWORK

    Walls

    Solid conc blockwork to IS 20 Type A having limestone aggregate and a compressible strength of 10N/mm2 bedded and jointed in premixed mortor.

    ^^^100mm thick 151.00 m2 18.00 2,718.00

    ^^^350mm thick 4.00 m2 38.00 152.00

    ANCILLERIES TO BLOCKWORK

    Forming Cavities

    Between new walls

    ^^^100mm wide 4.00 m2 2.00 8.00



    FLOOR, WALL & CEILING FINISHES

    Partitions (Service Cavity)

    70mm Gypframe C Studs at 600mm c/c; slab one side of partitions with 12.5mm gyproc plasterboard fixed with 25mm gyproc drywall screws at 300mm c/c with 3mm Gypsum skim coat finish; include for taping all joints and for scrim reinforcement to all wall and

    ^^^First Floor Service Riser; 2470mm high 2.00 nr 270.00 540.00

    ^^^Ground Floor Service Riser; 2625mm high 1.00 nr 290.00 290.00



    (22) INTERNAL WALLS 3,865.50


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (23) FLOORS

    CONCRETE WORK

    PRECAST CONCRETE

    Floor

    Precast Concrete floor; 150mm Thick Widespan Slabs

    ^^^>300mm wide 112.00 m2 34.80 3,897.60

    Formwork

    Edges of suspended slabs and landings;

    Height Not exceeding 250mm

    ^^^Formwork generally 3.00 m 12.00 36.00

    INSITU CONCRETE

    Floor Screed

    ^^^50mm th concrete floor screed laid on floor slab 8.00 m3 97.00 776.00

    Surface finishes

    ^^^Powerfloat surface of unset concrete 99.00 m2 4.10 405.90

    SUNDRIES

    Insulation

    Rigid foil board insulation to floor slab perimeter to prevent cold bridging

    ^^^30mm th 89.00 m 7.00 623.00



    AIRTIGHTNESS

    MEMBRANES

    Generally

    Siga Majpell or equally approved Airtightness Membrane to be fitted around ends of precast floor slabs turned down wall 150mm taped and sealed to blockwork; installed in accordance with the manufactures instructions

    ^^^> 300mm 55.00 m2 8.00 440.00

    (23) FLOORS 6,178.50


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (24) STAIRS, RAMPS

    (24) STAIRS, RAMPS

    GENERALLY

    PC Sum

    ^^^Allow the PC Sum of Ç10,000.00 for the supply and installtion of the Stairs and Guardrails complete 1.00 PCSUM 10,000.00 10,000.00

    Sundries

    Builder Work

    ^^^Contractor to allow for attendances for the above works 1.00 Item 500.00 500.00



    (24) STAIRS, RAMPS 10,500.00


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (27) ROOFS

    WOODWORK

    STRUCTURAL & FIRST FIXINGS

    Carcassing timbers to roof

    ^^^100 x 75mm wallplate 89.00 m 9.87 878.43

    Extra over for:

    ^^^Galvanised steel holding down straps at 1.5m c/c 60.00 nr 5.00 300.00

    ^^^100 x 44mm; timber runner 71.00 m 7.10 504.10

    ^^^50 x 50mm; hardwood batten fixed to external wall to support gutters 93.00 m 5.00 465.00

    ^^^Contractor to allow for the supply and installation of pre-fabricated roof trusses as per tender drawings 1.00 Item 10,355.19 10,355.19



    (27) ROOFS 12,502.72


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (31) EXTERNAL WALL COMPLETIONS

    METALWORK: Non Structural

    Supply and install Munster Joinery uPVC Double glazed range or equal and approved; colour and finish to be selected by the client; including all associated iron mongery; to achieve U Value of 1.2(W.m2.K); including all necessary in glazing thermal broken

    Composite Items: Windows

    ^^^700 x 2775mm (overall size including frame) as per schedule 801 1.00 Nr 15,200.00 15,960.00

    ^^^900 x 1100mm (overall size including frame) as per schedule 801 6.00 Nr

    ^^^900 x 1300mm (overall size including frame) as per schedule 801 12.00 Nr

    ^^^900 x 1500mm (overall size including frame) as per schedule 801 4.00 Nr

    ^^^1800 x 1500mm (overall size including frame) as per schedule 801 4.00 Nr

    ^^^2700 x 2100mm (overall size including frame) as per schedule 801 2.00 Nr

    Supply and install Munster Joinery Ultra-Tech Door range range or equal and approved with uPVC side screens; Double glazed units; colour and finish to be selected by the client; including all associated iron mongery; to achieve U Value of 1.2(W.m2.K); inc

    Composite Items: Doors & Screens

    ^^^2200 x 2100mm (overall size including frame) as per schedule 801 1.00 Nr

    ^^^2450 x 2100mm (overall size including frame) as per schedule 801 1.00 Nr

    Supply and install Munster Joinery Ultra-Tech Door range range or equal and approved; Double glazed units where required; colour and finish to be selected by the client; including all associated iron mongery; to achieve U Value of 1.2(W.m2.K); including a

    Composite Items: Doors

    ^^^900 x 2100mm (overall size including frame) as per schedule 801 1.00 Nr



    (31) EXTERNAL WALL COMPLETIONS 16,363.00


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (32) INTERNAL WALL COMPLETIONS

    WOODWORK

    BOARDING & SECOND FIXINGS

    Archtraving

    MDF archtraving; fixed to door frame with hidden fixings; with neatly mitred angles

    ^^^100 x 18mm 23.00 m 7.50 172.50

    COMPOSITE ITEMS

    Doors

    Deanta Shaker Style doors doors; 44mm thick in 50mm Tulip wood door frames including intumescent mastic/rockwool fireproofing to maintain fire resistance between partitions and door frame; as per schedule 820

    ^^^950 x 2100mm (overall size); as per schedule 820 12.00 Nr 665.00 7,980.00

    ^^^1800 x 2100mm (overall size); as per schedule 820 1.00 Nr 918.00 918.00

    Attic access door; seals on all frames to prevent drafts

    ^^^600 x 2100mm (overall size) as per floor plan 411 1.00 Nr 450.00 450.00

    Ironmongery

    ^^^Allow PC Sum of Ç60 per door leaf for the supply and installation of selected ironmongery 13.00 Nr 60.00 780.00



    (32) INTERNAL WALL COMPLETIONS 10,300.50


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (37) ROOF COMPLETIONS

    METALWORK - NON STRUCTURAL

    Composite items; Rooflights

    Velux CK004 rooflights; thermally broken double glazed units with laminated inner pane and toughened outter pane an low argon filled cavity

    ^^^550x 980mm units 1.00 nr 914.00 914.00



    AIRTIGHTNESS

    MEMBRANES

    Generally

    SIGA Fentrim IS2 tapes to be applied to all external window and door surrounds to achieve airtightness requirements

    ^^^< or = 300mm 4.00 m 5.10 20.40



    (37) ROOF COMPLETIONS 934.40


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (41) WALL FINISHES EXTERNALLY

    FLOOR, WALL & CEILING FINISHES

    IN-SITU FINISHES

    Walls

    Prepare surfaces scud, scratch and render to smooth sand / cement render finish to recieve paint finish to external walls; including all angle and stop beads

    ^^^< or = 300mm wide 134.00 m 4.90 656.60

    ^^^> 300mm wide 343.00 m2 18.75 6,431.25

    Extra over for

    ^^^Bellcast above recessed plinth 89.00 m 12.00 1,068.00

    ^^^25mm th; Raised plaster corbel to eaves 97.00 m 15.00 1,455.00

    Plinth

    Recessed plaster plinth; including all angle and stop beads

    ^^^150-300mm girth 72.00 m 12.00 864.00



    (41) WALL FINISHES EXTERNALLY 10,474.85


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (42) WALL FINISHES INTERNALLY

    FLOOR, WALL & CEILING FINISHES

    Walls

    Gypsum hardcoat and a min 2.5mm Gypsum skimcoat finish; minimum 15mm thick to blockwork; finish as per manufacturers recommendations

    ^^^< or = 300mm wide 23.00 m 5.00 115.00

    ^^^> 300mm 672.00 m2 18.50 12,432.00

    Plasterboard liner to reveal; supported by timber batten; plaster finish to match all walls

    ^^^< or = 300mm wide 134.00 m 9.15 1,226.10



    (42) WALL FINISHES INTERNALLY 13,773.10


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (45) CEILING FINISHES

    FLOOR, WALL & CEILING FINISHINGS:

    Finishings

    12.5mm th Gypsum Plasterboard, taped, sealed; finished with a 3mm th Gypsum skim finish and left ready for painting

    > 300mm 160.00 m2 19.00 3,040.00

    Suspended Ceilings

    Ceilings; depth of suspension 150 - 500mm

    Gyproc Metal Frame suspended ceiling system with 12.5mm plasterboard lining and 3mm skimcoat finish; left ready for painting 99.00 m2 19.85 1,965.15



    AIRTIGHTNESS

    MEMBRANES

    Pro-clima Intello Plus or equivalent airtightness membrane fixed between joists and plasterboard and Concrete slab and plasterboard with all joints taped with Pro-clima Uni tape

    ^^^> 300mm 197.00 m2 6.75 1,329.75



    (45) CEILING FINISHES 6,334.90


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (47) ROOF FINISHES

    ROOFING. CLADDING & WATERPROOFING

    SLATE & TILING COVERING

    Slates

    Selected natural slates; on 32 x 50mm pressure impregnated slatting battens and counter battens; fixed with 65 x 3.35mm galvanized annular ring shank nails; on 'Tyvek Supro Plus, Pro-Clima' fully breathable underlay Felt; all fixed to roof timbers in acco

    ^^^> 300mm 239.00 m2 46.80 11,185.20

    Ridge tiles

    ^^^Clay plain ridge tiles; butt jointed in accordance with the manufactures instructions; bedded and jointed in 1:3 cement:sand mortar; finished neatly as the work proceeds 38.00 m 18.50 703.00

    Special Fittings

    Tegral slate vents or similar and approved; ventilating attic space

    ^^^Generally 2.00 nr 38.00 76.00

    Flashings

    Code 5 lead flashing and counter flashings to chimneys;

    ^^^0-150mm girth 7.00 m 27.00 189.00

    ^^^ditto to abutments with walls 8.00 m 27.00 216.00

    Code 5 lead flashing and counter flashings to valleys; on and including treated valley boards and tilting fillet

    ^^^ditto valleys; 150-300mm girth 10.00 m 26.80 268.00

    Soffit Vents

    Glidevale SV606 continuous vented soffit; fixed in accordance with the manufactures instructions

    ^^^Generally 97.00 m 5.00 485.00

    SUNDRIES

    Insulation

    300mm Rockwool Insulation fitted between and over joists. 200mm between and 100mm over.

    ^^^300mm th 197.00 m2 13.50 2,659.50



    DRAINAGE - DISPOSAL ABOVE GROUND

    Rainwater Goods

    Gutters

    Half rounbd cast aluminium rainwater gutter; powder coated finish; all in accordance with the manufactures instructions

    ^^^125mm diameter 65.00 m 29.80 1,937.00

    Downpipes

    Seamless aluminium downpipes; sprayed a selected colour; bracket and screw fixed to blockwork wall; all in accordance with the manufactures instructions

    ^^^80mm diameter 33.00 m 28.80 950.40

    E/O on gutter for which they occur

    All in aluminium

    ^^^Outlets 8.00 nr 85.00 680.00

    ^^^Stopends 14.00 nr 20.00 280.00

    ^^^bends 1.00 nr 20.00 20.00

    E/O on downpipes for which they occur

    All in aluminium

    ^^^Shoes 8.00 nr 20.00 160.00

    ^^^Swannecks 8.00 nr 25.00 200.00



    (47) ROOF FINISHES 20,009.10


  • Hosted Moderators Posts: 18,115 ✭✭✭✭ShiverinEskimo


    You're making a dogs dinner of thread.


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (59) BUILDING SERVICES - (MAINLY PIPED & DUCTED)

    MECHANICAL INSTALLATION

    GENERALLY

    PC Sum

    ^^^Allow the PC Sum of Ç25,000.00 for the supply and installtion of the mechanical sub-contract complete 1.00 PCSUM 25,000.00 25,000.00

    ^^^Allow the PC Sum of Ç5,000.00 for associated plumbing works 1.00 PCSUM 5,000.00 5,000.00

    Sundries

    Builder Work

    ^^^Allow for all builders in works in association with the mechanical installation 1.00 Item 800.00 800.00

    ^^^Contractor to allow for attendances for the above works 1.00 Item 1,500.00 1,500.00



    (59) BUILDING SERVICES - (MAINLY PIPED & DUCTED) 32,300.00


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (69) BUILDING SERVICES - (MAINLY ELECTRICAL)

    ELECTRICAL INSTALLATION

    GENERALLY

    PC Sum

    ^^^Allow the PC Sum of Ç10,000.00 for the supply and installtion of the electrical sub-contract complete 1.00 PCSUM 10,000.00 10,000.00

    Sundries

    Builder Work

    ^^^Allow for all builders in works in association with the mechanical installation 1.00 Item 500.00 500.00

    ^^^Contractor to allow for attendances for the above works 1.00 Item 500.00 500.00



    (69) BUILDING SERVICES - (MAINLY ELECTRICAL) 11,000.00


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (30) SITE ENCLOSURES

    DEMOLITIONS AND ALTERATIONS

    Site Clearance

    ^^^Removal of section of existing hedgerow to allow for the construction of new concrete entrance walls and gate 42.00 m 20.00 840.00

    ^^^Remove existing garden wall and gate to cottage, including grubbing up all foundations; dispose off site. 1.00 Item 520.00 520.00



    EXCAVATIONS & EARTHWORKS

    EXCAVATIONS

    Foundation Trenches

    Generally

    ^^^average depth < or = 2m 16.00 m3 5.95 95.20

    Disposal

    Excavated Material

    ^^^Deposite excavated material on site 16.00 m3 12.00 192.00

    Filling

    backfill with excavated material

    ^^^excavations 10.00 m3 9.00 90.00

    Create earth bank to front entrance to be landacaped by others;

    ^^^Embankment 24.00 m3 32.00 768.00



    CONCRETE WORK

    INSITU CONCRETE

    Blinding

    ^^^50mm lean mix concrete blinding to underside of the foundations 3.00 m3 80.00 240.00

    Foundations

    C35/20N reinforced concrete foundations; poured on or against earth of unblinded hardcore

    ^^^Generally 17.00 m3 87.00 1,479.00

    Reinforcement

    Fabric

    ^^^Grade A393 mesh to concrete strip foundations 56.00 m2 8.00 448.00



    STONEWORK

    Walls In Trenches

    Coursed rubble drystone walls and piers

    ^^^500mm th 16.00 m2 145.00 2,320.00

    ^^^500mm th Curved 3.00 m2 175.00 525.00

    Walls

    ^^^500mm th 27.00 m2 145.00 3,915.00

    ^^^500mm th curved 15.00 m2 175.00 2,625.00

    Piers

    ^^^750 x 750mm 4.00 nr 640.00 2,560.00



    METALWORK

    Gates

    ^^^Allow for supply and installation of new gate as per drawing 621 1.00 Item 750.00 750.00



    (30) SITE ENCLOSURES 17,367.20


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (40) ROADS, PATHS PAVINGS

    DRIVEWAY & PAVING

    EXCAVATIONS & EARTHWORKS

    Reduced Level

    Generally

    ^^^Average depth < or = 2m 126.00 m3 5.95 749.70

    Disposal

    Excavated Material

    ^^^Deposit excavated material off site 126.00 m3 14.80 1,864.80

    Filling

    Imported material; crushed limestone to clause 804 of the DOE specification for granular sub base materials; compacting in 150mm thick layers

    Make up levels

    ^^^excavations < or = 250mm 115.00 m3 21.40 2,461.00

    SURFACE PAVINGS, FENCING & LANDSCAPING

    Roads and Pavings

    Well compacted layer of washed 20mm chip limestone gravel 459.00 m2 5.95 2,731.05



    (40) ROADS, PATHS PAVINGS 7,806.55


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (50) SITE SERVICES - (MAINLY PIPED & DUCTED)

    STORM DRAINAGE

    EXCAVATIONS & EARTHWORKS

    Excavating trenches

    Pipes < or = 250 mm nominal diameter; include for grading bottom, necessary earthwork supports, disposal of excavated material and filling in with selected materials

    ^^^Average depth 500 - 1000mm deep 161.00 m 6.50 1,046.50

    Beds & Surrounds

    Type 1 pea gravel bed and surround to pipework

    ^^^300 x 300mm 161.00 m 4.10 660.10

    Pipes

    uPVC

    uPVC pipe; spigot and socket jointed; laid in trenches

    ^^^100mm diameter 161.00 m 9.00 1,449.00

    Pipe Accessories

    ^^^uPVC rain water gully traps 12.00 nr 68.00 816.00

    ^^^Acco 100 multi drain to doors 6.00 m 53.60 321.60

    ^^^Acco heavy duty drain to entrance gate 5.00 m 75.00 375.00

    ^^^AJ's 11.00 nr 108.90 1,197.90

    SUNDRIES

    Soak Pits

    Washed gravel stone filled soakaway; including all excavations, disposal terrim etc

    ^^^5000mm diameter 2500mm deep 2.00 nr 650.00 1,300.00

    Rainwater Harvesting

    Supply and install Kingspan domestic Envireau integrated rainwater harvesting system

    ^^^Supply 1.00 Item 2,287.00 2,401.35

    ^^^Installation 1.00 Item 1,200.00 1,200.00

    Builders Work

    ^^^Testing and commissioning of all systems 1.00 Item 300.00 300.00



    FOUL DRAINAGE

    EXCAVATIONS & EARTHWORKS

    Excavating trenches

    Pipes < or = 250 mm nominal diameter; include for grading bottom, necessary earthwork supports, disposal of excavated material and filling in with selected materials

    ^^^Average depth 500 - 1000mm deep 85.00 m 6.50 552.50

    Beds & Surrounds

    Type 1 granular bed and surround to pipes under grass area

    ^^^450 x 450mm 85.00 m 4.10 348.50

    Pipes

    uPVC pipe; spigot and socket jointed; laid in trenches

    ^^^100mm diameter 85.00 m 9.00 765.00

    Percolation pipes; 110mm diameter

    ^^^110mm diameter 163.00 m 8.50 1,385.50

    uPVC S&V pipe;bracket fixed to blockwork internally

    ^^^100mm diameter 12.00 m 9.00 108.00

    Pipe Accessories

    ^^^AJ's 3.00 nr 113.50 340.50

    Manholes

    Manhole to be 215mm th blockwork walls internally rendered and haunched; with 225mm th reinforced concrete cover slab forming 500 x 500mm ope in cover slab; with galvanised steel heavey duty cover and frame

    ^^^internal diameter 600 x 600mm; avg depth 1.00 - 1.50m 1.00 nr 375.00 375.00

    SUNDRIES

    Inspection Chamber

    ^^^Precast concrete inspection chamber; including all excavation and fitting complete 1.00 nr 675.00 675.00

    Septic Tank

    ^^^Precast concrete septic tank 1.00 nr 2,980.00 2,980.00

    Percolation area

    ^^^Percolation pipes (163m measured above) with clean gravel surround 150mm to sides and top and 250mm underneath capped with terram and covered with 300mm topsoil all in accordance with EPA manual wastewater treatment systems for single houses; all requi 1.00 Item 2,150.00 2,150.00

    Builders Work

    ^^^Testing and commissioning 1.00 Item 300.00 300.00



    WATERMAIN

    EXCAVATIONS & EARTHWORKS

    Excavating trenches

    Pipes < or = 250 mm nominal diameter; include for grading bottom, necessary earthwork supports, disposal of excavated material and filling in with selected materials

    ^^^Average depth 500 - 1000mm deep 27.00 m 5.20 140.40

    Beds & Surrounds

    Type 1 granular bed and surround to pipes under grass area

    ^^^450 x 450mm 27.00 m 4.10 110.70

    Pipework

    Hydrocare water main to relevant IS standard

    ^^^50mm diameter 27.00 m 7.00 189.00

    Pipe accessories

    Fitting

    ^^^Bends 2.00 nr 8.00 16.00

    ^^^Warning tape 27.00 m 0.25 6.75

    Chambers

    215mm th blockwork chambers; heavy duty cast iron cover and frame; including all excavations, disposal, grating bottoms, earthwork supports and backfilling

    ^^^450 x 450 x 600mm deep 1.00 nr 175.00 175.00

    ^^^ditto sluice valve 1.00 nr 175.00 175.00

    ^^^Water meter 1.00 Item 150.00 150.00

    Builders Work

    ^^^Connection to existing water main 1.00 Item 150.00 150.00

    ^^^Road opening licence 1.00 Item 1,500.00 1,500.00



    (50) SITE SERVICES - (MAINLY PIPED & DUCTED) 23,660.30


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    (69) SITE SERVICES - (MAINLY ELECTRICAL)

    ELECTRICAL INSTALLATION

    EXCAVATIONS & EARTHWORKS

    Excavating trenches

    Pipes < or = 250 mm nominal diameter; include for grading bottom, necessary earthwork supports, disposal of excavated material and filling in with selected materials

    ^^^Average depth 500 - 1000mm deep 33.00 m 6.50 214.50

    Beds & Surrounds

    Type 1 granular bed and surround to pipes under grass area

    ^^^450 x 450mm 33.00 m 4.10 135.30

    Pipes

    uPVC pipe; spigot and socket jointed; laid in trenches

    ^^^100mm diameter pipes; include draw wire 33.00 m 9.00 297.00

    Pipe accessories

    ^^^Warning tape 33.00 m 0.25 8.25

    Access junctions; Wavin or other equal and approved; jointing to pipes in accordance with the manufacturer's instructions

    100mm outlet; two 100mm inlets 2.00 nr 185.00 370.00



    (69) SITE SERVICES - (MAINLY ELECTRICAL) 1,025.05


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    GARAGE

    (19) SUBSTRUCTURE

    EXCAVATIONS & EARTHWORKS

    EXCAVATIONS

    Topsoil

    Topsoil for preservation

    ^^^Average depth 150mm 55.00 m2 2.00 110.00

    Reduced level

    Generally

    ^^^Average depth < or = 2m 16.00 m3 6.00 96.00

    Foundation Trenches

    Generally

    ^^^Average depth < or = 2m 11.00 m3 6.00 66.00

    Disposal

    Excavated Material

    ^^^Deposit excavated material off site 27.00 m3 15.00 405.00

    Filling

    Imported material; crushed limestone to clause 804 of the DOE specification for granular sub base materials; compacting in 150mm thick layers

    Make up levels

    ^^^excavations < or = 250mm 3.00 m3 24.00 72.00

    ^^^underside of concrete floor slab < or = 250mm 10.00 m3 24.00 240.00

    Surface Treatments

    Blinding Filling

    Sand blinding laid and compacted on hardcore filling

    ^^^25mm th 37.00 m2 1.00 37.00

    CONCRETE WORK

    INSITU CONCRETE

    Blinding

    ^^^50mm sand / cement blinding to underside of the foundations 2.00 m3 87.00 174.00

    Filling

    Concrete filling to cavities with sand and cement mix

    ^^^150mm wide 3.00 m3 90.00 270.00

    Foundations

    C30N reinforced concrete foundations; poured on or against earth of unblinded hardcore

    ^^^Generally 8.00 m3 97.00 776.00

    Floor Slab

    C30/20N concrete floor slab; poured on radon barrier

    ^^^< or = 150mm th 6.00 m3 97.00 582.00

    Surface Finishes

    Power floating surface of unset concrete

    ^^^Generally 37.00 m2 4.10 151.70

    Reinforcement

    Fabric

    ^^^Grade A393 mesh to concrete strip foundations 25.00 m2 8.00 200.00

    ^^^Grade A142 mesh to concrete floor slabs 37.00 m2 4.00 148.00

    BRICKWORK & BLOCKWORK

    BLOCKWORK

    Walls in Trenches

    Solid concrete load bearing blockwork to IS 20 Type A having limestone aggregate and a compressive strength of 5N/mm2 bedded and jointed in premixed mortor; tied together using stainless steel wall ties @ 750mm c/c horizontally and 450mm vertically

    ^^^350mm th 24.00 m2 38.00 912.00

    ANCILLERIES TO BLOCKWORK

    Forming Cavities

    Between new walls

    ^^^125mm wide 24.00 m2 2.00 48.00

    Damp Proof Courses

    DPC; horizontal; with 100mm minimum laps

    ^^^width < or = 225mm 55.00 m 0.50 27.50

    SUNDRIES

    Damp Proof Membrane

    Monarflex RMB 400 radon barrier laid on sand blinding with 400mm sealed laps at all joints and turned up at floor and wall junction and carried across cavity; installed in strict accordance with the manufacture instructions

    ^^^Horizontal > 300mm 50.00 m2 6.00 300.00

    ^^^Vertical < or = 300mm 13.00 m2 6.00 78.00

    Insulation

    Xtratherm XT / UF rigid insulation; foil faced; laid in accordance with manufactures instructions

    ^^^60mm th 37.00 m2 16.00 592.00

    Rigid foil faced PIR insulation to all door opes; in accordance with manufacturers instructions

    ^^^50mm th 4.00 m 7.00 28.00

    Rigid foil board insulation to floor slab perimeter to prevent cold bridging

    ^^^30mm th 32.00 m 5.00 160.00

    Builders Work

    ^^^Forming or cutting holes in 350mm th blockwork; including all required lintels as necessary 1.00 nr 30.00 30.00



    (21) EXTERNAL WALLS

    CONCRETE WORK

    INSITU CONCRETE

    Threshold

    Concrete threshold details; complete with drip detail; wrapped in and including DPC; including all formwork and fixing complete; all in accordance with the Architects details

    ^^^200 x 200mm 4.00 m 28.00 112.00

    PRECAST CONCRETE

    Lintels

    Precast prestressed concrete lintels; bedded and jointed in premix mortor; 200mm bearing to eachside of opening

    ^^^140 x 100mm 3.00 m 9.00 27.00

    ^^^140 x 140mm 3.00 m 15.00 45.00

    Cills

    Precast concrete deep faced cills; centrally placed and neatly and finely finished; bedded and jointed in premixed mortor; projecting 100mm to each side of opening

    ^^^325 x 75mm 2.00 m 15.00 30.00

    BRICKWORK & BLOCKWORK

    BLOCKWORK

    Walls

    Solid concrete load bearing blockwork to IS 20 Type A having limestone aggregate and a compressive strength of 5N/mm2 bedded and jointed in premixed mortor; tied together using stainless steel wall ties @ 750mm c/c horizontally and 450mm vertically

    ^^^350mm th 73.00 m2 38.00 2,774.00

    Extra over on blockwork for:

    ^^^Tying into existing building using 'ANCON STAIFIX' wall starter system or similar approved to manufacturers instructions 6.00 m 12.00 72.00

    ANCILLERIES TO BLOCKWORK

    Forming Cavities

    Between new walls

    ^^^150mm wide 73.00 m2 2.00 146.00

    Closing cavities

    Jambs with "L" blocks

    ^^^150mm wide 11.00 m 4.00 44.00

    Top of wall with slate cavity closer

    ^^^150mm wide 28.00 m 6.00 168.00

    Bed reinforcement to all window and door opes

    ^^^width < or = 225mm 55.00 m 14.00 770.00

    Damp Proof Courses

    Stepped DPC cavity tray over window opes;

    ^^^width >225mm 4.00 m2 15.00 60.00

    Vertical DPC to external wall corners

    ^^^width > 225mm 5.00 m2 15.00 75.00

    Horizontal to cills; with 100mm minimum laps

    ^^^width > 225mm 1.00 m2 1.00 1.00

    Vertical to jambs; with 100mm minimum laps

    ^^^width < or = 225mm 11.00 m 0.50 5.50

    SUNDRIES

    Insulation

    Xtratherm Cavity Therm PIR full fill cavity insulation; fitted in accordance with manufacturers instructions

    ^^^100 x 140mm 7.00 m 12.00 84.00

    STRUCTURAL STEELWORK

    Lintels

    Steelite lintels as per engineers drawings and specification

    ^^^350mm wide 4.00 m 110.00 440.00

    AIRTIGHTNESS

    MEMBRANES

    Generally

    SIGA Fentrim IS2 tapes to be applied to all external window and door surrounds to achieve airtightness requirements

    ^^^< or = 300mm 24.00 m 5.10 122.40



    (22) INTERNAL WALLS

    CONCRETE WORK

    PRECAST CONCRETE

    Lintels

    Precast prestressed concrete lintels; bedded and jointed in premix mortor; 200mm bearing to eachside of opening

    ^^^100 x 75mm 3.00 m 7.50 22.50

    BRICKWORK & BLOCKWORK

    BLOCKWORK

    Walls

    Solid conc blockwork to IS 20 Type A having limestone aggregate and a compressible strength of 10N/mm2 bedded and jointed in premixed mortor.

    ^^^350mm thick 4.00 m2 38.00 152.00

    ANCILLERIES TO BLOCKWORK

    Forming Cavities

    Between new walls

    ^^^100mm wide 4.00 m2 2.00 8.00



    (27) ROOFS

    WOODWORK

    STRUCTURAL & FIRST FIXINGS

    Carcassing timbers to roof

    ^^^100 x 75mm wallplate 25.00 m 6.90 172.50

    Extra over for:

    ^^^Galvanised steel holding down straps at 1.5m c/c 18.00 nr 5.00 90.00

    ^^^175 x 44mm rafters 142.00 m 7.10 1,008.20

    ^^^175 x 44mm flat roof joists 11.00 m 7.10 78.10

    ^^^175 x 44 coller ties 23.00 m 7.10 163.30

    ^^^225 x 35mm ridge board 8.00 m 7.45 59.60

    ^^^225 x 44mm ceiling joists 92.00 m 7.45 685.40

    ^^^225 x 75mm purlins 15.00 m 8.00 120.00



    (31) EXTERNAL WALL COMPLETIONS

    WOODWORK

    BOARDING & SECOND FIXINGS

    Windows Boards

    Tulipwood window boards; including all necessary timber grounds; screw and pellet fixed to blockwork

    ^^^25mm th 2.00 m 9.00 18.00

    METALWORK: Non Structural

    Supply and install Munster Joinery uPVC Double glazed range or equal and approved; colour and finish to be selected by the client; including all associated iron mongery; to achieve U Value of 1.2(W.m2.K); including all necessary in glazing thermal broken

    Composite Items: Windows

    ^^^900 x 1100mm (overall size including frame) as per schedule 801 2.00 Nr

    Supply and install Munster Joinery Ultra-Tech Door range range or equal and approved; Double glazed units where required; colour and finish to be selected by the client; including all associated iron mongery; to achieve U Value of 1.2(W.m2.K); including a

    Composite Items: Doors

    ^^^900 x 2100mm (overall size including frame) as per schedule 801 1.00 Nr

    Supply and fit selected sheeted timber hardwood door; including all associated ironmongery; sealed all sides with suitable silicone sealant; all in accordance with ,manufacturers instructions

    Composite Items: Garage Doors

    ^^^2800 x 2100mm (overall size including frame) as per schedule 620 1.00 Nr 2,400.00 2,400.00



    (41) WALL FINISHES EXTERNALLY

    FLOOR, WALL & CEILING FINISHES

    IN-SITU FINISHES

    Walls

    Prepare surfaces scud, scratch and render to smooth sand / cement render finish to recieve paint finish to external walls; including all angle and stop beads

    ^^^< or = 300mm wide 18.00 m 6.00 108.00

    ^^^> 300mm wide 76.00 m2 19.00 1,444.00

    Extra over for

    ^^^Bellcast above recessed plinth 23.00 m 12.00 276.00

    ^^^25mm th; Raised plaster corbel to eaves 32.00 m 15.00 480.00

    Plinth

    Recessed plaster plinth; including all angle and stop beads

    ^^^150-300mm girth 23.00 m 12.00 276.00



    (42) WALL FINISHES INTERNALLY

    FLOOR, WALL & CEILING FINISHES

    Walls

    Gypsum hardcoat and a min 2.5mm Gypsum skimcoat finish; minimum 15mm thick to blockwork; finish as per manufacturers recommendations

    ^^^< or = 300mm wide 24.00 m 6.00 144.00

    ^^^> 300mm 60.00 m2 18.50 1,110.00



    (45) CEILING FINISHES

    FLOOR, WALL & CEILING FINISHINGS:

    Finishings

    12.5mm th Gypsum Plasterboard, taped, sealed; finished with a 3mm th Gypsum skim finish and left ready for painting

    > 300mm 36.00 m2 19.75 711.00



    (47) ROOF FINISHES

    ROOFING. CLADDING & WATERPROOFING

    SLATE & TILING COVERING

    Slates

    Selected natural slates; on 32 x 50mm pressure impregnated slatting battens and counter battens; fixed with 65 x 3.35mm galvanized annular ring shank nails; on 'Tyvek Supro Plus, Pro-Clima' fully breathable underlay Felt; all fixed to roof timbers in acco

    ^^^> 300mm 54.00 m2 45.90 2,478.60

    Ridge tiles

    ^^^Ridge tiles; butt jointed in accordance with the manufactures instructions; bedded and jointed in 1:3 cement:sand mortar; finished neatly as the work proceeds 8.00 m 18.50 148.00

    Flashings

    Code 5 lead flashing and counter flashings to chimneys;

    ^^^0-150mm girth 3.00 m 25.00 75.00

    Soffit Vents

    Glidevale SV606 continuous vented soffit; fixed in accordance with the manufactures instructions

    ^^^Generally 32.00 m 5.00 160.00

    DRAINAGE - DISPOSAL ABOVE GROUND

    Rainwater Goods

    Gutters

    Half rounbd cast aluminium rainwater gutter; powder coated finish; all in accordance with the manufactures instructions

    ^^^125mm diameter 21.00 m 29.80 625.80

    Downpipes

    Seamless aluminium downpipes; sprayed a selected colour; bracket and screw fixed to blockwork wall; all in accordance with the manufactures instructions

    ^^^80mm diameter 9.00 m 28.80 259.20

    E/O on gutter for which they occur

    All in aluminium

    ^^^Outlets 3.00 nr 85.00 255.00

    ^^^bends 4.00 nr 20.00 80.00

    E/O on downpipes for which they occur

    All in aluminium

    ^^^Shoes 3.00 nr 20.00 60.00

    ^^^Swannecks 3.00 nr 25.00 75.00


  • Registered Users, Registered Users 2 Posts: 5,245 ✭✭✭myshirt


    Looks expensive. Wow. What did the land cost you?


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    You're making a dogs dinner of thread.

    No - im not.. im going to fill those sections in.. your actually after mucking it up by posting in it

    Mods can you move his comment to the end of the garage section please? Or.. delete it!


  • Registered Users, Registered Users 2 Posts: 5,245 ✭✭✭myshirt


    Very detailed, thanks for the contribution. I posted mid-stream aswell, sorry.

    Are you happy with those tenders?


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    myshirt wrote: »
    Very detailed, thanks for the contribution. I posted mid-stream aswell, sorry.

    Are you happy with those tenders?

    Nah your grand, you were at the end. Just tried to keep the thread as concise as possible.

    Yep it would be within 2% of the average we get back for work like this..


  • Registered Users, Registered Users 2 Posts: 13,778 ✭✭✭✭fits


    Thanks for posting. We are pricing an 1800 sq ft house at the moment. By the looks of your figures, our budget will be tight.


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    fits wrote: »
    Thanks for posting. We are pricing an 1800 sq ft house at the moment. By the looks of your figures, our budget will be tight.

    Quite a few people get a shock to be honest.

    The problem with the construction industry the last few years that skewed prices was labour.

    Material prices have always been rising.
    Labour is gone scarce at the moment, so the old supply and demand problem is kicking in and the trades are getting more money so the whole cost is rising.

    It will continue to get worse too as very little people after leaving cert are taking up trades.


  • Registered Users, Registered Users 2 Posts: 13,778 ✭✭✭✭fits


    I didnt really get a shock. I am aware that costs are high. We just have to figure out a way to square that with the budget we have.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 1,712 ✭✭✭neil_hosey


    Really interesting and helpful ! More of these would give a lot of transparency and would be great help up front for alot of people. I plan on doing the same when I am finished.

    Quick question though, was the floor area equally spread 1200 ground floor and 1200 first floor?


  • Closed Accounts Posts: 8,722 ✭✭✭nice_guy80


    Currently getting prices for a 210 sq metre house in midlands

    coming in around €220,000-€230,000

    we own the site

    I don't know why people use square feet.
    feet and inches haven't been used in Ireland for 4 decades


  • Moderators, Home & Garden Moderators Posts: 10,146 Mod ✭✭✭✭BryanF


    nice_guy80 wrote: »
    Currently getting prices for a 210 sq metre house in midlands

    coming in around €220,000-€230,000

    we own the site

    I don't know why people use square feet.
    feet and inches haven't been used in Ireland for 4 decades

    I dont know why the only people who put up prices are those that are about to start..


  • Closed Accounts Posts: 8,722 ✭✭✭nice_guy80


    BryanF wrote: »
    I dont know why the only people who put up prices are those that are about to start..

    I'll come back when we're finished


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    The house that I posted in the OP came in bang on budget with no changes thankfully.


  • Registered Users, Registered Users 2 Posts: 1,712 ✭✭✭neil_hosey


    nice_guy80 wrote: »
    Currently getting prices for a 210 sq metre house in midlands

    coming in around €220,000-€230,000

    we own the site

    I don't know why people use square feet.
    feet and inches haven't been used in Ireland for 4 decades

    That is interesting where are you based?

    Similar sort of position as me in thst we own the site.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 145 ✭✭terrarev


    For what it's worth, I'm halfway through a 190sqm bungalow build in the west with a contract price of €262,000. That's build only of house and waste treatment, not including garage, connection/professional fees and the following PC Sum items:

    Kitchen + appliances
    Sanitary ware
    Supply of flooring (fitting included in contract)
    Painting
    Light Fixtures + Door handles.
    Furnitures/Finishings etc.

    The nature of the house (being a bungalow) and the fact there is a lot of steel involved in the build will push the price a bit in this case but the numbers listed in the OP do appear to be a good guide line from my experience.


  • Registered Users, Registered Users 2 Posts: 3,725 ✭✭✭Metric Tensor


    I notice 25k for a mechanical pc sum.

    Do you mind if I ask what eventually made it into this sum. MHRV? Heat Pumps? Rads or UF?

    Thanks mill for posting - confirms what I have been telling people!


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    I notice 25k for a mechanical pc sum.

    Do you mind if I ask what eventually made it into this sum. MHRV? Heat Pumps? Rads or UF?

    Thanks mill for posting - confirms what I have been telling people!

    Geothermal and underfloor heating throughout went in. It actually came in under the budget as that particular client went with a different supplier with whom they had a connection with. It was €20k all in, in the end.


  • Registered Users, Registered Users 2 Posts: 3,725 ✭✭✭Metric Tensor


    Thanks. I was thinking it was of a level that could only justify geothermal.

    I don't see a MHRV installation mentioned at all. Was there none in this build? It's in the vast majority of build's we do these days?


  • Registered Users, Registered Users 2 Posts: 4,396 ✭✭✭Tefral


    Thanks. I was thinking it was of a level that could only justify geothermal.

    I don't see a MHRV installation mentioned at all. Was there none in this build? It's in the vast majority of build's we do these days?

    Under the 23k there is another line item for 5k that is the supply install and commission of MHRV.


  • Advertisement
  • Closed Accounts Posts: 8,722 ✭✭✭nice_guy80


    neil_hosey wrote: »
    That is interesting where are you based?

    Similar sort of position as me in thst we own the site.

    westmeath

    its going to be selfbuild, probably timber frame insulated panels for walls & roof


  • Registered Users, Registered Users 2 Posts: 1,096 ✭✭✭anoble66


    I am coming into the final 8 weeks of a build in the midlands. 3000sq/ft, 2 storey, no garage, no landscaping, no wall / gates, builders drive only. Contract price came in at 235k, the build started Feb 1st this year. Contract price included argon filled triple glazing, pre-cast 2nd floor, pre-cast stairs, A2W HP, MHRV, electrics, domestic plumbing, internal joinery, plastering (internal / external), waste treatment / sewage, paths, 2k PC sum for bathrooms, 4k pc sum for stairs.

    After paying for kitchen & appliances, flooring, stair coverings, council contributions, water connection, esb connection, modest furnishings, solicitors, engineer fees, stove, bathrooms, we have spent a further 72k. So a total of 307000. This is going to get us to a point whereby we can move in, but by no means fully furnished.

    I would estimate a further 30k could easily be eaten into if I needed the wall / gates and some landscaping


  • Registered Users, Registered Users 2 Posts: 220 ✭✭Wegian


    I'm glad to see that I am not overpaying.

    Detail so far on our self build
    2 Storey
    2750 sqft
    Straightforward design

    Preliminaries - Planning / Solicitor / WS Connection: 9k
    Foundation Material: 12.2k
    Foundation Labour: 4.6k
    Blockwork Material: 17.3k
    Blockwork Labour: 9.5k

    I havent yet invoiced myself for labour to date :)


  • Registered Users, Registered Users 2 Posts: 9,380 ✭✭✭893bet


    17k for blockwork labour???


  • Registered Users, Registered Users 2 Posts: 220 ✭✭Wegian


    893bet wrote: »
    17k for blockwork labour???

    Blocks Material and Labour were the wrong way around
    Material includes hollowcore, lintels etc


  • Closed Accounts Posts: 1,356 ✭✭✭Right2Write


    Interesting collection of figures. Thanks for posting. Is there an attempted breakdown anywhere between materials and labour? I don't think so as that's not how it's priced.

    Good guide for anyone involved in self building and I mean real self building, where you do the work and labouring yourself!! I built a good sized two storey extension about 12 years ago, total floor about 100 sq metres. Cost between €40-€50,000. Including the roofing done by builder and that included re roofing existing part of house.

    Materials and specs have risen but there's a lot of money tied up in labour and management.


  • Registered Users, Registered Users 2 Posts: 10 wex13


    nice_guy80 wrote: »
    westmeath

    its going to be selfbuild, probably timber frame insulated panels for walls & roof

    Could you elaborate on house type/shape and what is or isnt included in quotes?


  • Registered Users, Registered Users 2 Posts: 80 ✭✭siralan


    Thanks for posting the BOQ Tefral, thats very helpful. I've found it very difficult to view actual Bills of Quantities online to nail down projections for a new build. Im debating whether to go self build or use contractor and part of the problem is knowing how much extra a contractor will be and where we can potentially make some savings ourselves.

    Can I ask if anyone has an actual cost of build up to wall plate level for shell only. In other words foundation, dead building, radon, floor insulation, sub-floor poured, rising walls, concrete first floor and concrete stairs if installed ? Ive looked at erecting the main structure in precast concrete and have a definitive cost on it (€54k for solid wall and external insulation is extra) This doesn't include the below ground elements (foundation, sub-floor and dead building if needed)