New Building Control Regs

1171819202123»

Comments

  • Moderators, Society & Culture Moderators Posts: 42,167 Mod ✭✭✭✭Gumbo


    No worries: I saw this: and splitting the house into 2 houses:)

    See it now.
    Yes, full planning, site area, drainage, parking, private open space, separation etc etc required.


  • Registered Users, Registered Users 2 Posts: 65 ✭✭mccarrd2


    I am planning on an attic conversion. It requires planning because of dormer windows. As it requires planning, does this automatically mean I need to submit a commencement notice and therefore comply with all the regs that go with it?


  • Subscribers Posts: 42,859 ✭✭✭✭sydthebeat


    There are generally three types of commencement notice that are applicable to a domestic situation.

    Small works / extensions less than 40sq m need a "commencement notice without documentation"

    Extensions over 40 sq m and new detached new builds can choose whether to submit a 'opt in' commencement notice, which is a full "commencement notice with documentation" or a "commencement notice with opt out documentation"

    So if your extending by under 40 sq m is a relatively simple application

    If you're extending by more, then you've a choice to make.


  • Moderators, Society & Culture Moderators Posts: 42,167 Mod ✭✭✭✭Gumbo


    mccarrd2 wrote: »
    I am planning on an attic conversion. It requires planning because of dormer windows. As it requires planning, does this automatically mean I need to submit a commencement notice and therefore comply with all the regs that go with it?

    Yes. CN required.
    You still need to comply with building regs for works that don’t need a commencement notice too by the way.


  • Registered Users, Registered Users 2 Posts: 156 ✭✭descol


    Hi Boarders

    I have a question regarding extensions and the new Regs

    I understand that the new regulations require that where major renovations (defined as a renovation where more than 25% of the surface envelope of the building undergoes renovation) are carried on a building, the whole building or dwelling should achieve a cost optimal energy performance insofar as it is technically, functionally and economically feasible. The cost optimal energy performance level for a typical dwelling is equivalent to a B2 BER.

    If there is a new grd floor rear extension of say 35 sqm to a Semi D - do the new regs require that the existing semi D needs to be upgraded to to meet a B2 BER Rating ?

    thanks in advance
    descol


  • Advertisement
  • Moderators, Society & Culture Moderators Posts: 42,167 Mod ✭✭✭✭Gumbo


    descol wrote: »
    Hi Boarders

    I have a question regarding extensions and the new Regs

    I understand that the new regulations require that where major renovations (defined as a renovation where more than 25% of the surface envelope of the building undergoes renovation) are carried on a building, the whole building or dwelling should achieve a cost optimal energy performance insofar as it is technically, functionally and economically feasible. The cost optimal energy performance level for a typical dwelling is equivalent to a B2 BER.

    If there is a new grd floor rear extension of say 35 sqm to a Semi D - do the new regs require that the existing semi D needs to be upgraded to to meet a B2 BER Rating ?

    thanks in advance
    descol

    What is the opinion of your designer?
    There's working samples of what you may do within Part L.


  • Registered Users, Registered Users 2 Posts: 25 doggy Bear


    Hi everyone.
    I need some advice.
    I am selling my home and the buyer wants to see a Certificate of Compliance for work I had done inside the house in 2013.
    The problem is: I don't have one!
    I had hired a builder that a friend recommended to knock down a wall to make the kitchen bigger and install an RSJ, which he did.
    But he never gave me a certificate or anything like that.
    Am I liable?
    What can be done now to sort this issue out?
    Your help would be really appreciated.
    Cheers.


  • Subscribers Posts: 42,859 ✭✭✭✭sydthebeat


    Have you a solicitor working for you?
    They will advise you in these matters


  • Moderators, Society & Culture Moderators Posts: 42,167 Mod ✭✭✭✭Gumbo


    doggy Bear wrote: »
    Hi everyone.
    I need some advice.
    I am selling my home and the buyer wants to see a Certificate of Compliance for work I had done inside the house in 2013.
    The problem is: I don't have one!
    I had hired a builder that a friend recommended to knock down a wall to make the kitchen bigger and install an RSJ, which he did.
    But he never gave me a certificate or anything like that.
    Am I liable?
    What can be done now to sort this issue out?
    Your help would be really appreciated.
    Cheers.

    Engage an engineer/architect/surveyor/relevant professional.
    They will issue an opinion on compliance but may want certain elements of works opened up to inspect the structure.


  • Registered Users, Registered Users 2 Posts: 114 ✭✭01Surveyor


    From your description of the works as 'inside the house' it doesnt sound like its a planning Architects Opinion on Compliance (AOC) that you are being asked for. If the works were done before 1 March 2014 the Building Control Amendment Regulations 2014 (BCAR) dont apply so you cant be asked to provide any BCAR Certs. What remains is to provide an AOC relating to compliance with the Building Regulations. In this case its probably best to approach a local structural engineer and get the builder to provide him with whatever details he requires to allow him to provide an Opinion on Compliance based on a visual inspection and the details provided by the contractor.
    You are lucky that the works are not post 1 March 2014 as there is no remedy for missing BCAR paperwork.
    BTW since 1993 there is no longer any such thing as a certificate of compliance in this context.
    Hope that helps
    Good Luck.

    ps. Just saw Gumbo's much more succinct post essentially saying the same thing.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 3 banzer


    Hi,

    I have a query that maybe someone can shed some light on.
    -Building on a house started in 2007 (under building regulations of that year)
    -It stalled for a few years
    -Looking to resume now in 2020

    Does it do so under the regulations of today, or those that were in play when building commenced in 2007?


  • Moderators, Society & Culture Moderators Posts: 42,167 Mod ✭✭✭✭Gumbo


    banzer wrote: »
    Hi,

    I have a query that maybe someone can shed some light on.
    -Building on a house started in 2007 (under building regulations of that year)
    -It stalled for a few years
    -Looking to resume now in 2020

    Does it do so under the regulations of today, or those that were in play when building commenced in 2007?

    Planning is most likely expired.
    New planning required.
    New commencement notice to current regulations.

    All the above is based on what stage the works are currently at.


  • Subscribers Posts: 42,859 ✭✭✭✭sydthebeat


    banzer wrote: »
    Hi,

    I have a query that maybe someone can shed some light on.
    -Building on a house started in 2007 (under building regulations of that year)
    -It stalled for a few years
    -Looking to resume now in 2020

    Does it do so under the regulations of today, or those that were in play when building commenced in 2007?

    Depends on what level the works are at currently.

    If "substantially complete" it's arguable that existing certification will suffice, and compliance will be regs at time of commencement

    If not, then as per gumbos post above.


  • Registered Users, Registered Users 2 Posts: 25 doggy Bear


    Gumbo... The structural engineer came today, looked it over, and said it was fine. I will be issued with an Opinion of Compliance by next week. Thank you very much for your input.


  • Registered Users, Registered Users 2 Posts: 25 doggy Bear


    01Surveyor... same message to you as for Gumbo. The Opinion of Compliance will be issued shortly so thank you for your input!


  • Registered Users, Registered Users 2 Posts: 3 banzer


    sydthebeat wrote: »
    Depends on what level the works are at currently.

    If "substantially complete" it's arguable that existing certification will suffice, and compliance will be regs at time of commencement

    If not, then as per gumbos post above.

    Thanks gumbos and sydthebeat for your inputs.

    The walls are built and plastered
    The roof is on and tiled
    Doors and windows are in

    There is no electricity installed
    No heating installed (ie. no heat system chosen or radiators fitted)
    No internal work done


  • Moderators, Society & Culture Moderators Posts: 42,167 Mod ✭✭✭✭Gumbo


    banzer wrote: »
    Thanks gumbos and sydthebeat for your inputs.

    The walls are built and plastered
    The roof is on and tiled
    Doors and windows are in

    There is no electricity installed
    No heating installed (ie. no heat system chosen or radiators fitted)
    No internal work done

    That’s classed as substantially complete in my opinion so old regs apply. Original CN stands and no new planning required.

    But, always get it checked on the ground by a relevant professional.

    You’d be best placed to comply with as much of today’s regs as possible. Especially with regards to heating, renewables etc


  • Subscribers Posts: 42,859 ✭✭✭✭sydthebeat


    Gumbo wrote: »
    That’s classed as substantially complete in my opinion so old regs apply. Original CN stands and no new planning required.

    But, always get it checked on the ground by a relevant professional.

    You’d be best placed to comply with as much of today’s regs as possible. Especially with regards to heating, renewables etc

    ^
    this 100%

    If no 1st fix heating is installed, then aim as high as is practical

    2007 commencement would have been in accordance with 2005 Part L regs.
    since then there has been upgrades in 2008, 2011 and 2019

    a typical 2005 Part L house would be approx a C3 BER rating.
    a 2008 went to B2, 2011 went to A3 and 2019 is at A2

    you should be able to achieve B1 without any major impact to the build as it stands today


  • Registered Users, Registered Users 2 Posts: 3 banzer


    Thanks again for those inputs.


  • Registered Users, Registered Users 2 Posts: 5,728 ✭✭✭Charlie-Bravo


    Hi All, looking for direction regarding the BCMS system and use of Commencement Notice without documentation. Once a CN is submitted, is there anything else that needs to be done on the BCMS once the works are finished? Do you close out the job on the system in anyway? Thanks.

    -. . ...- . .-. / --. --- -. -. .- / --. .. ...- . / -.-- --- ..- / ..- .--.



  • Advertisement
  • Subscribers Posts: 42,859 ✭✭✭✭sydthebeat


    Nope


    just submit CN without documentation, wait for validation of CN... and away you go..... no need to contact them again



  • Registered Users, Registered Users 2 Posts: 9,706 ✭✭✭irishgeo


    Apologies if this has been asked before, i dont fancy wading through 23 pages

    I am about to finalise the purchase of new build in the next month or two in the west of ireland. Anything in the new regs that will protect me from the builder having used poor quality materials or blocks that have mica above the 1% limit.

    Or is this a question for the solicitor before final contracts are signed.



  • Moderators, Society & Culture Moderators Posts: 42,167 Mod ✭✭✭✭Gumbo


    Once he provides the BCAR certs to the solicitor that’s as far as you’ll get.

    hopefully the certified has done their job and proofed all materials used.