Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

DART Underground delayed until 2018

2»

Comments

  • Registered Users Posts: 577 ✭✭✭Typewriter


    Sponge Bob wrote: »
    As is electrification to Drogheda and to Hazelhatch and to Dunboyne(I think)

    After all how can you run a Dart train without electricity ????

    http://www.railsceneireland.fotopic.net/p64668134.html



    ;)


  • Registered Users, Registered Users 2 Posts: 3,536 ✭✭✭Mark200



    Weird! I was at Pearse at the time that picture was taken.... I remember seeing that train.


  • Registered Users, Registered Users 2 Posts: 5,337 ✭✭✭dowlingm


    I'm of the view that Heuston electrification should be planned for in the post 2020 timeframe - eventually one would hope that electrification will encompass at least some non-interconnector trains.

    As for the 22K sets etc. - JC could have said "it's actually in the works" - instead she tried to make him look like some kind of spoofer. Perhaps one day IE will realise that RUI is a good thing for them - but not any time soon!


  • Registered Users, Registered Users 2 Posts: 1,132 ✭✭✭Stonewolf


    Electrification of the lines in question should be going ahead in advance of the interconnector. Or have we put off the order for all the new EMUs until 2018 too?


  • Closed Accounts Posts: 185 ✭✭oharach


    Sponge Bob wrote: »
    Interconnector always included the electrification component, the only major change since it was first announced is that the portion from Inchicore to Heuston need not be electrified if the Dart trains are in a tunnel from Inchicore to Heuston as was decided last year.

    It would be madness not to electrify Heuston – Inchicore. Otherwise there would be nowhere for DARTs to terminate during maintenance, or other closures of the tunnel.


  • Banned (with Prison Access) Posts: 25,234 ✭✭✭✭Sponge Bob


    Twould be a bit difficult to raise bridges in the 'gullet' eg this one


  • Closed Accounts Posts: 7 thetool


    if Fine Gail get in they will privateiseeverthing, including the civil service, all to keep them in the luxury they think they deserve!


  • Closed Accounts Posts: 724 ✭✭✭dynamick


    From today's Irish Times...
    Bids for Dart underground sought

    OLIVIA KELLY

    BIDS TO construct the Dart underground from Dublin’s Docklands to Inchicore have been sought by Iarnród Éireann just one week after the company announced a three-year delay in the project.

    The 7.6km underground line, which will link Heuston Station to the Dart line, was due to open in 2015. Iarnród Éireann last week said it did not now expect the project to be completed until 2018.

    A spokesman for the company yesterday said the original timeframe had been set in 2007 when the line was due to terminate at Heuston Station. The subsequent decision to extend it to Inchicore meant there would be 40 per cent more tunnelling than had been proposed.
    There is more...


Advertisement