Odd situation Building Surveyor v Builder

  • 26-07-2021 07:58PM
    #1
    Registered Users, Registered Users 2 Posts: 3,643 ✭✭✭


    Hi just wanted some views on this please


    Work being carried out at home and doorway is being widened from one room into another. Our building surveyor got a structural engineer to inspect and 150mm thick concrete heads minimum were recommended. The builder installed 150mm x 100mm heads on their flat so the thickness is only 100mm.


    The building surveyor won't sign it off saying it doesn't meet engineer's spec but builder says it's fine.


    Any thoughts?



Comments

  • Registered Users, Registered Users 2 Posts: 3,788 ✭✭✭Wildly Boaring


    As a structural engineer I'm completely on your surveyors side. I'm biased. But if an engineer went to the bother of speccing something why would it "be fine".

    If it collapses and kills someone the builder will just point at the fella who signed it off


    Edit. When something is specced by a structural engineer it is not recommended. It is the design.

    Also assume the engineer was explicit that they were to be 150mm deep lintels.



  • Registered Users, Registered Users 2 Posts: 3,643 ✭✭✭Ginger83


    Yes he said 150mm minimum thickness. The building surveyor in fact asked him to do an inspection beforehand.

    The builder says he will get a cert from the concrete company to say they are fine.

    We don't want any conflict but nobody gets paid without the job being signed off.



  • Registered Users, Registered Users 2, Paid Member Posts: 2,981 ✭✭✭scwazrh


    Building surveyor is the one signing off so what he says goes .No point arguing the point on a small project.He specified the requirements and the builder did his own thing so it’s the builders cost to rectify.



  • Moderators, Society & Culture Moderators Posts: 42,150 Mod ✭✭✭✭Gumbo


    Surveyor is in the right here, and fair dues for him in going the route of getting the structural design instead of the cowboy approach that it "will be fine".

    Builder is also talking BS, and the concrete supplier will not sign off on the use of this in your specific situation.



  • Registered Users, Registered Users 2 Posts: 47,486 ✭✭✭✭muffler


    Agree with the above. Stick with the surveyor.