Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Help Keep Boards Alive. Support us by going ad free today. See here: https://subscriptions.boards.ie/.
If we do not hit our goal we will be forced to close the site.

Current status: https://keepboardsalive.com/

Annual subs are best for most impact. If you are still undecided on going Ad Free - you can also donate using the Paypal Donate option. All contribution helps. Thank you.

Resource smoothing vs. resource leveling

  • 05-08-2024 01:30PM
    #1
    Registered Users, Registered Users 2 Posts: 74 ✭✭


    In simple terms, what is the difference between these two? Is one better than the other by default? (beginner here)



Comments

  • Registered Users, Registered Users 2 Posts: 120 ✭✭scottygee


    Resource leveling involves adjusting the project timeline to prevent overloading a resource. For example, if an IT technician is assigned too many tasks to complete within regular hours, the project manager might extend the timeline to prevent overworking them. By redistributing tasks and adjusting timelines, resource leveling ensures deadlines are met without sacrificing work quality or overwhelming the team. It focuses on making the most of your resources' time and capabilities.

    On the other hand, resource smoothing aims to keep workloads consistent, avoiding the ups and downs caused by task dependencies or other factors. This method is particularly useful when there's a strict deadline because it ensures that work is spread evenly, maximizing resource efficiency. It prevents spikes in workload and helps maintain a steady pace.

    Many argue that the best approach is to combine both techniques. This combination allows for a balanced workload while still meeting project deadlines, leveraging the strengths of each method to optimize both time and resource management. But generally, the choice depends on project constraints and goals.