Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

PV+battery with change over switch

  • 15-04-2024 10:34am
    #1
    Registered Users, Registered Users 2 Posts: 476 ✭✭


    Hi, Just a few questions to help with my understanding on this. My solar installer as an add on option of a change over switch (and its not cheap) to allow off grid use during a power cut. However I have already allowed for a change over switch as part of my electrical installation with a generator hook up so my switch will allow switching between mains and generator.

    I asked the rep can I operate off grid using this and he said no that I would need a second change over switch but to me this doesn't make sense. Unless I am mistaken all the PV install would be on the consumer side so once I switched to the generator port then this would switch away from grid and isolate the system making it safe to use the solar? I guess the only possible issue is how does the system know I "changed over".

    Alternatively since the PV I assume drops when it no longer senses the grid supply based on a CT clamp? If the CT clamp was placed on the output of the change over switch rather than input wouldn't that allow the generator to trick the system into running which would still be beneficial since the generator would not have to work as hard plus probably a bit better for sensitive electronics. Only issue there would be ensuring no back feeding into the generator I guess.

    Any feedback or alternatives would be interesting to help my understanding, thanks.



Comments

  • Registered Users, Registered Users 2 Posts: 8,073 ✭✭✭10-10-20


    The issue is that unlike a true fuel powered generator, the inverter's AC input needs to be isolated off the house-supply so that if you were to attach a gen-set or even the output of the inverter's gen port that you wouldn't be back-feeding the inverter with it's own AC waveform. So a rudimentary change-over switch would not suffice, as I understand it you'd need a proper ATS wired up like so:

    The inverter will isolate or power off once the voltage or frequency start to slide out of the prescribed limits and this is done at the inverter input side and not at the CT. The inverter would then "know" on the basis of having no valid voltage at the required frequency on the AC in, but would see and be powered-from the battery voltage.



  • Registered Users, Registered Users 2 Posts: 476 ✭✭SodiumCooled


    Thanks for the explanation. Sorry if I am mixing things up a but wouldn't my change over switch come before that first MCB meaning the inverter would be fed from a generator? Or is that wiring diagram specific to the ATS?



  • Registered Users, Registered Users 2 Posts: 8,073 ✭✭✭10-10-20


    Well my first comment was going to ask for a circuit diagram... that's only how we'll know. Don't want to be assuming at all here.



  • Registered Users, Registered Users 2 Posts: 476 ✭✭SodiumCooled


    It's a new build so wires are run but nothing terminated yet but my understanding on how the CoS will be wired is that that the main tails from the meter go to the CoS first and then onto the consumer unit. I wouldn't have thought solar installers would have any part in touching the main electrical installation so would only be working on the consumer unit side hence my comment?

    To clarify the solar install "first fix" hasn't been done yet.

    There is two parts really to my question - the first was if I can run the system the second is there potential issues I could cause by adding the generator to the mix.



  • Registered Users, Registered Users 2 Posts: 8,073 ✭✭✭10-10-20


    Ah, so this isn't in situ already for an existing gen-set - ok understood. Then it's not obvious to me why you'd need an additional change-over switch unless they assumed that you had two independent sources. Might be one to post in the Electrical forum.



  • Advertisement
  • Registered Users, Registered Users 2 Posts: 476 ✭✭SodiumCooled


    Thanks and apologies I should have clarified its a new build in the opening post.



  • Registered Users, Registered Users 2 Posts: 476 ✭✭SodiumCooled


    So just to update on this in case it’s useful for anyone else. Having spoken with the solar installers electrician a week or two back the fairly simple solution to this is to cascade two change over switches. One will switch between gene and solar and the second between the first change over switch and esb. A second cable run from the inverter to the consumer unit was all that was really needed to implement this.

    With the gene running it will charge the battery also.



  • Registered Users, Registered Users 2 Posts: 1,113 ✭✭✭corglass


    Any pics?



  • Registered Users, Registered Users 2 Posts: 476 ✭✭SodiumCooled


    It’s not done yet, will be a few months away as not ready for second fix yet - just cabling has been run at this point.

    when I say second run from the inverter location to the consumer unit this will be the “off grid” output from the inverter that will go into the first change over switch with the generator.



  • Registered Users, Registered Users 2 Posts: 8,073 ✭✭✭10-10-20




  • Advertisement
Advertisement