Roads update Q1 2019
Options
-
10-04-2019 2:40amModerators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,347 Mod ✭✭✭✭Join Date:Posts: 14043
Here's everything that's happened in Q1 2019
N2 Ashbourne-Kilmoon Cross: Consultants to be appointed shortly to progress Phases 1-4
N2 Clontibret-NI border: Phase 1 now underway by Jacobs
N2 Ardee-Castleblayney: Phase 1 now underway by Jacobs
M4 Maynooth-Leixlip: Consultants to be appointed by May to progress Phases 1-4
N4 Collooney-Castlebaldwin: Construction started in February, with completion in 2021.
N5 Ballaghaderreen-Scramoge: Approved by An Bord Pleanala in January, with CPO published in March by Roscommon County Council. Archaelogical work to start shortly.
M7 Naas/Newbridge bypass upgrade: Completion of the widening works between J9 and J11 Is expected in the next month, with J9a to open in May. The R407 Sallins bypass will open in September
N8/N25/N40 Dunkettle Interchange: Advance works continue on site, with full works to start in summer 2019. Completion is expected in summer 2022.
M11/N11 J4-J14 upgrade: A project timeline has now been published with options to be published in July and submission to An Bord Pleanala in Q4 2020.
M11 Gorey-Enniscorthy: It has been confirmed this will open in Q3 2019
N11/N25 Oilgate-Rosslare Harbour: Consultants to be appointed shortly for Phases 1-4
N13/N56 Letterkenny relief road: Emerging preferred route was published in February with selection of preferred route in Q2 2019.
N14 Letterkenny-Lifford:Emerging preferred route was published in February with selection of preferred route in Q2 2019.
N15/N13 Ballybofey/Stranorlar bypass: Emerging preferred route was published in February with selection of preferred route in Q2 2019.
M20 Cork-Limerick: Consultants appointed for TII PMG Phases 1-4 in March. There has been no timeline for delivery published yet.
M21 Limerick-Foynes: ABP submission deferred to Q2 2019
N21 Abbeyfeale relief road: Consultants to be appointed shortly for Phases 1-4
N21 Newcastelwest relief road: Consultants to be appointed shortly for Phases 1-4
N22 Macroom-Ballyvourney: Advance works continue on site, with a construction start before end 2019 expected.
N25 New Ross bypass: Opening of scheme now deferred to 2020.
N56 Mountcharles-Inver: Tender for the final 2.5km of this scheme was published in March.
N86 Tralee-Dingle: Tender issued for consultants for Phases 5-7 for 8km split between Ballynasare-Annascaul and Doonore South-Ballygarret9
Comments
-
Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,347 Mod ✭✭✭✭Join Date:Posts: 14043
Phase 7 - Completion
N86 Camp-Ballygarret [1.1km T3SC] [open to traffic]
N86 Ballynasare-Lispole [2.7km T3SC] [open to traffic]
Phase 6 - Construction
N4 Collooney-Castlebaldwin [14km T2DC + 1km T1SC] [construction underway; 2021 completion]
M7 Naas/Newbridge bypass widening [May 2019 completion]
M7 J9-J11 junction works [13.5km D3M] [May 2019 (J9A) + 2019 (J10) completion]
N8/N25/N40 Dunkettle Interchange [prelim works underway, full start summer 2019]
M11 Gorey-Enniscorthy [27km D2M] [Q3 2019 completion]
N25 New Ross PPP [4km T1DC + 10km T2DC] [2020 completion]
N56 Mountcharles-Drumbeigh [2.5km T1SC] [May completion]
N56 Kilkenny-Letterilly [2019 completion]
N59 Kilmeena
Phase 5 II - Tender
N5 Westport-Turlough [20km T2DC + 5km SC] [Q3 2019 start]
N22 Macroom-Ballyvourney [22km T2DC] [Q3 2019 start]
N52 Ardee bypass [5km T2SC] [Q3 2019 start]
N56 Drumbeigh-Inver [2.5km T1SC] [mid 2019 start]
N56 Letterilly-Kilraine [7.5km T3SC] [2019 start]
N59 Dungloe-Cloghbolie [7.5km T3SC] [2019 start]
N59 Maam Cross-Bunnakill [2019 start]
N59 Kilmeena-Westport [Q3 2019 start]
Phase 5 - Advance works and land acquisition
N5 Ballaghaderreen-Scramoge [35km T1SC] [CPO & advance works underway]
N59 Moycullen bypass [4.5km T1SC] [tender expected H2 2019]
N59 Bunnakill-Oughterard [in queue; phased implementation]
N59 Derrada-Newport [advance works ongoing]
N59 Derrada-Mulranny [in queue; phased implementation]
N69 Listowel bypass [6km SC] [land acquisition; Q3 2019 start]
N86 Dingle-Lispole [10km T3SC] [in queue; phased implementation]
N86 Ballynasare-Annascaul [4.7km T3SC] [tender expected 2019]
N86 Gortbreagoge-Doonore South [3.3km T3SC] [in queue; phased implementation]
N86 Doonore South-Ballygarret [tender expected 2019]
N86 Camp-R560 [1.1km T3SC] [in queue; phased implementation]
Phase 4 - Statutory process
M6 Galway City Ring Road [12km M + 6km T1SC] [decision due mid 2019]
M28 Cork-Ringaskiddy [12km M] [decision due Q2 2019 from High Court]
Phase 3 - Design
N3 Clonee-M50
M21 Adare-Rathkeale-Foynes [submission to ABP Q2 2019]
Phase 2 - Route selection
N2 Slane bypass [preferred route announcement due]
M11 J4 Bray- J14 Coyne's Cross [options to be published July 2019]
N13/N56 Letterkenny Bypass + DC upgrade [emerging preferred route published]
N13/N15 Ballybofey/Stranorlar bypass [emerging preferred route published]
N14 Letterkenny-Lifford [emerging preferred route published]
N55 Athlone-Ballymahon [preferred route due early 2019]
N70 Milltown bypass [route options published]**
N72 Mallow Relief Road (design & planning consultants to be appointed]
Phase 1 - Feasibility study/project scope
N2 Clontibret-NI Border [traffic surveys underway]
N2 Ardee-Castleblayney [traffic surveys underway]
M20 Cork-Limerick [consultants appointed]
N2 Ashbourne-Kilmoon Cross [consultants to be appointed shortly]
N3 Virginia bypass
M4 Leixlip-Maynooth [consultants to be appointed by May]
N4 Mullingar-Roosky [consultants to be appointed shortly]
N4 Carrick on Shannon-Dromod
N11/N25 Oilgate-Rosslare Harbour [consultants to be appointed shortly]
N17 Knock-Collooney
N21 Abbeyfeale relief road [consultants to be appointed shortly]
N21 Newcastlewest bypass [consultants to be appointed shortly]
N22/N23 Farranfore-Killarney
N24 Waterford-Cahir
N24 Cahir-Limerick Junction
N25 Waterford-Glenmore
N25 Carrigtwohill-Midleton
M50 Dublin Port South Access Road
N52 Tullamore-Kilbeggan
N71 Bandon relief road extension**
Phase 0 - Pre-appraisal
The extended panel (to be advanced post 2027)
M1 Lissenhall-Balbriggan
N2 Kilmoon-Slane
N2 Slane-Collon
N3 Cavan-Butlersbridge
M4 Maynooth-Kilcock
N5 Turlough-Bohola
M7 Newbridge-Monasterevin
N13 Stranorlar-Letterkenny-Bridgend [10km T2DC]
N15 Sligo-Cliffony
N17 Tuam-Claremorris
N21 Rathkeale-Abbeyfeale [33km T2DC]
N22 Ballincollig-Macroom [24km T1DC]
N22/N40 Cork North Ring Road West
N24 Limerick-Caherconlish
N25 Midleton-Youghal
N25 Waterford-Dungarvan
N26 Ballina-Bohola Phase 2
N27 Cork Airport-N40
Dead until further notice
N2 Ardee-Collon
N15 Stranorlar-Lifford
N23 Castleisland-Farranfore
N24 Boher-Limerick Junciton
N30 Moneytucker-New Ross0