Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Roads update Q1 2019

  • 10-04-2019 1:40am
    #1
    Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,522 Mod ✭✭✭✭


    Here's everything that's happened in Q1 2019

    N2 Ashbourne-Kilmoon Cross: Consultants to be appointed shortly to progress Phases 1-4
    N2 Clontibret-NI border: Phase 1 now underway by Jacobs
    N2 Ardee-Castleblayney: Phase 1 now underway by Jacobs
    M4 Maynooth-Leixlip: Consultants to be appointed by May to progress Phases 1-4
    N4 Collooney-Castlebaldwin: Construction started in February, with completion in 2021.
    N5 Ballaghaderreen-Scramoge: Approved by An Bord Pleanala in January, with CPO published in March by Roscommon County Council. Archaelogical work to start shortly.
    M7 Naas/Newbridge bypass upgrade: Completion of the widening works between J9 and J11 Is expected in the next month, with J9a to open in May. The R407 Sallins bypass will open in September
    N8/N25/N40 Dunkettle Interchange: Advance works continue on site, with full works to start in summer 2019. Completion is expected in summer 2022.
    M11/N11 J4-J14 upgrade: A project timeline has now been published with options to be published in July and submission to An Bord Pleanala in Q4 2020.
    M11 Gorey-Enniscorthy: It has been confirmed this will open in Q3 2019
    N11/N25 Oilgate-Rosslare Harbour: Consultants to be appointed shortly for Phases 1-4
    N13/N56 Letterkenny relief road: Emerging preferred route was published in February with selection of preferred route in Q2 2019.
    N14 Letterkenny-Lifford:Emerging preferred route was published in February with selection of preferred route in Q2 2019.
    N15/N13 Ballybofey/Stranorlar bypass: Emerging preferred route was published in February with selection of preferred route in Q2 2019.
    M20 Cork-Limerick: Consultants appointed for TII PMG Phases 1-4 in March. There has been no timeline for delivery published yet.
    M21 Limerick-Foynes: ABP submission deferred to Q2 2019
    N21 Abbeyfeale relief road: Consultants to be appointed shortly for Phases 1-4
    N21 Newcastelwest relief road: Consultants to be appointed shortly for Phases 1-4
    N22 Macroom-Ballyvourney: Advance works continue on site, with a construction start before end 2019 expected.
    N25 New Ross bypass: Opening of scheme now deferred to 2020.
    N56 Mountcharles-Inver: Tender for the final 2.5km of this scheme was published in March.
    N86 Tralee-Dingle: Tender issued for consultants for Phases 5-7 for 8km split between Ballynasare-Annascaul and Doonore South-Ballygarret


Comments

  • Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,522 Mod ✭✭✭✭marno21


    Phase 7 - Completion
    N86 Camp-Ballygarret [1.1km T3SC] [open to traffic]
    N86 Ballynasare-Lispole [2.7km T3SC] [open to traffic]

    Phase 6 - Construction
    N4 Collooney-Castlebaldwin [14km T2DC + 1km T1SC] [construction underway; 2021 completion]
    M7 Naas/Newbridge bypass widening [May 2019 completion]
    M7 J9-J11 junction works [13.5km D3M] [May 2019 (J9A) + 2019 (J10) completion]
    N8/N25/N40 Dunkettle Interchange [prelim works underway, full start summer 2019]
    M11 Gorey-Enniscorthy [27km D2M] [Q3 2019 completion]
    N25 New Ross PPP [4km T1DC + 10km T2DC] [2020 completion]
    N56 Mountcharles-Drumbeigh [2.5km T1SC] [May completion]
    N56 Kilkenny-Letterilly [2019 completion]
    N59 Kilmeena

    Phase 5 II - Tender
    N5 Westport-Turlough [20km T2DC + 5km SC] [Q3 2019 start]
    N22 Macroom-Ballyvourney [22km T2DC] [Q3 2019 start]
    N52 Ardee bypass [5km T2SC] [Q3 2019 start]
    N56 Drumbeigh-Inver [2.5km T1SC] [mid 2019 start]
    N56 Letterilly-Kilraine [7.5km T3SC] [2019 start]
    N59 Dungloe-Cloghbolie [7.5km T3SC] [2019 start]
    N59 Maam Cross-Bunnakill [2019 start]
    N59 Kilmeena-Westport [Q3 2019 start]

    Phase 5 - Advance works and land acquisition
    N5 Ballaghaderreen-Scramoge [35km T1SC] [CPO & advance works underway]
    N59 Moycullen bypass [4.5km T1SC] [tender expected H2 2019]
    N59 Bunnakill-Oughterard [in queue; phased implementation]
    N59 Derrada-Newport [advance works ongoing]
    N59 Derrada-Mulranny [in queue; phased implementation]
    N69 Listowel bypass [6km SC] [land acquisition; Q3 2019 start]
    N86 Dingle-Lispole [10km T3SC] [in queue; phased implementation]
    N86 Ballynasare-Annascaul [4.7km T3SC] [tender expected 2019]
    N86 Gortbreagoge-Doonore South [3.3km T3SC] [in queue; phased implementation]
    N86 Doonore South-Ballygarret [tender expected 2019]
    N86 Camp-R560 [1.1km T3SC] [in queue; phased implementation]

    Phase 4 - Statutory process
    M6 Galway City Ring Road [12km M + 6km T1SC] [decision due mid 2019]
    M28 Cork-Ringaskiddy [12km M] [decision due Q2 2019 from High Court]

    Phase 3 - Design
    N3 Clonee-M50
    M21 Adare-Rathkeale-Foynes [submission to ABP Q2 2019]

    Phase 2 - Route selection
    N2 Slane bypass [preferred route announcement due]
    M11 J4 Bray- J14 Coyne's Cross [options to be published July 2019]
    N13/N56 Letterkenny Bypass + DC upgrade [emerging preferred route published]
    N13/N15 Ballybofey/Stranorlar bypass [emerging preferred route published]
    N14 Letterkenny-Lifford [emerging preferred route published]
    N55 Athlone-Ballymahon [preferred route due early 2019]
    N70 Milltown bypass [route options published]**
    N72 Mallow Relief Road (design & planning consultants to be appointed]

    Phase 1 - Feasibility study/project scope
    N2 Clontibret-NI Border [traffic surveys underway]
    N2 Ardee-Castleblayney [traffic surveys underway]
    M20 Cork-Limerick [consultants appointed]

    N2 Ashbourne-Kilmoon Cross [consultants to be appointed shortly]
    N3 Virginia bypass
    M4 Leixlip-Maynooth [consultants to be appointed by May]
    N4 Mullingar-Roosky [consultants to be appointed shortly]
    N4 Carrick on Shannon-Dromod
    N11/N25 Oilgate-Rosslare Harbour [consultants to be appointed shortly]
    N17 Knock-Collooney
    N21 Abbeyfeale relief road [consultants to be appointed shortly]
    N21 Newcastlewest bypass [consultants to be appointed shortly]
    N22/N23 Farranfore-Killarney
    N24 Waterford-Cahir
    N24 Cahir-Limerick Junction
    N25 Waterford-Glenmore
    N25 Carrigtwohill-Midleton
    M50 Dublin Port South Access Road
    N52 Tullamore-Kilbeggan
    N71 Bandon relief road extension**

    Phase 0 - Pre-appraisal

    The extended panel (to be advanced post 2027)
    M1 Lissenhall-Balbriggan
    N2 Kilmoon-Slane
    N2 Slane-Collon
    N3 Cavan-Butlersbridge
    M4 Maynooth-Kilcock
    N5 Turlough-Bohola
    M7 Newbridge-Monasterevin
    N13 Stranorlar-Letterkenny-Bridgend [10km T2DC]
    N15 Sligo-Cliffony
    N17 Tuam-Claremorris
    N21 Rathkeale-Abbeyfeale [33km T2DC]
    N22 Ballincollig-Macroom [24km T1DC]
    N22/N40 Cork North Ring Road West
    N24 Limerick-Caherconlish
    N25 Midleton-Youghal
    N25 Waterford-Dungarvan
    N26 Ballina-Bohola Phase 2
    N27 Cork Airport-N40

    Dead until further notice
    N2 Ardee-Collon
    N15 Stranorlar-Lifford
    N23 Castleisland-Farranfore
    N24 Boher-Limerick Junciton
    N30 Moneytucker-New Ross


Advertisement