Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie

NIR release tender for Eglinton - Castlerock improvements

Options
  • 05-07-2011 1:10pm
    #1
    Registered Users Posts: 66 ✭✭


    Seen on one of Translinks twitter accounts:
    The Coleraine to Londonderry railway line is situated in the North-western region of Northern Ireland. It is a rural line, which for long stretches closely follows the coast line. It is proposed to construct Continuously Welded Rail on an 18.5 mile long section of this route this route from the 69.5Mile Post to the 88 Mile Post. The works involves re-railing the track and converting it from jointed track to Continuously Welded Rail (CWR). New 113Alb/yd (also known as CEN56 Rail) rails will be welded to form the CWR. Ancillary items, such as pads and insulators will be renewed. Existing clips will be re-used where they are found to be serviceable. Ballast will be topped up where necessary. In some areas ballast retention measures will be constructed. Trackside drainage repairs will be carried out. Wet spot areas between sleeper beds will be dug out and reinstated.
    The Signalling and Telecomms system on this route is a Token Block System. Signalling & Telecomms works will typically be disconnections and reconnections which will be carried out by the Economic Operator.
    There are 34 public and private road crossings in the proposed work area. The surfaces of these will be removed to allow the works to progress through and must then re-instated.
    On completion of the works, the track will be fit for 70mph running between Castlerock and Eglinton.
    The site works will take place largely during overnight engineering possessions. The possessions will be available seven nights per week.
    The aim of this tender exercise is to appoint a suitably qualified Economic Operator in February 2012. The Economic Operator is expected to commence work in Spring 2012 and to have the re-railing work completed by Autumn / Winter 2012. A follow-up Maintenance Tamp of the re-railed section will take place in 2013.

    http://www.translink.co.uk/Corporate/Tenders/Coleraine-to-Londonderry-Track-Safety-Improvement-Works---Main-Contractor/

    Does this mean improvements will now occur during 2013 aspreviously anticipated?

    Local media made a big hype over the route being closed at the start of the City of Culture year. And how it was "discrimination" even though these plans had been applauded and planned long before the City applied for the status! :rolleyes:

    It also appears that the works will only be carried out at night? So the route will still be operational during the day!


Comments

  • Registered Users Posts: 2,677 ✭✭✭AngryLips


    Wow, NI infrastructure investment to benefit predominantly Catholic areas. Is this an infrastructure 'peace dividend'?


  • Registered Users Posts: 3,284 ✭✭✭dubhthach


    AngryLips wrote: »
    Wow, NI infrastructure investment to benefit predominantly Catholic areas. Is this an infrastructure 'peace dividend'?

    AngryLips that's a totally inappropriate response for this forum. If you wish to discuss the political situation in "Norn Iron" you can do so in the Politics forum.

    --

    NITransport, thanks for the link.


  • Registered Users Posts: 5,309 ✭✭✭dowlingm


    It's a pity some of the crossings won't be grade separated or closed during this work given the low speed of the line (partially due to the aforementioned wet spots) but Translink are only getting dribbles of cash beyond the commissioning of the C4Ks and the depot, thus the deferral of work on Dublin-Belfast.


Advertisement