Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Article: Planned Dublin metro line to cost more than €5bn

  • 07-08-2007 11:22am
    #1
    Closed Accounts Posts: 1,133 ✭✭✭


    Two articles from today's Irish Times:
    Planned Dublin metro line to cost more than €5bn
    Frank McDonald, Environment Editor

    Dublin's proposed metro line linking Swords with St Stephen's Green is set to cost more than €5 billion, The Irish Times has established from documents released by the Department of Transport under the Freedom of Information Act.

    Although all monetary figures in the documents are blacked out, it is possible to discern that the estimated cost of the 17km metro north line was put at €4.58 billion in 2004 prices. With construction inflation and additional expenditure, it would now be well over €5 billion.

    The extra spending arises from the provision of an additional underground station at Parnell Square as well as a promise that the section of the route running through Ballymun would be underground, rather than on the surface as originally proposed.

    The price tag for the city's first metro line makes it by far the most expensive infrastructure project in the history of the State - at least three times more costly than the M50 (€1.6 billion) and six times more than either the two Luas lines or the Dublin Port Tunnel.

    As well as metro north, the Railway Procurement Agency (RPA) is pursuing plans for metro west, a 25km line linking Tallaght with Ballymun, via Clondalkin, Blanchardstown and a number of Luas lines, serving Citywest, Docklands and Cherrywood/Shanganagh.

    No estimates of the likely cost of these projects have been revealed by the Department of Transport or the RPA, ostensibly on the basis that the figures are commercially confidential.

    However, it is more likely that they are being suppressed for political reasons.

    The documents were released after an appeal to the Information Commissioner, following a Freedom of Information Act request in November 2005 seeking details on the Government's €34.4 billion Transport 21 investment programme.

    They show that Iarnród Éireann submitted a 10-year capital programme, with an overall price-tag of €3.4 billion, to electrify much of Dublin's suburban rail network and build an underground rail interconnector between Heuston Station and Spencer Dock.

    Iarnród Éireann has conceded that the original estimate for the interconnector, which would have intermediate stations at Thomas Street, St Stephen's Green and Pearse Station, would now be substantially dearer than the original €1.3 billion estimate in 2002.

    The Cabinet subcommittee on infrastructure gave priority to the metro north project, however, and the RPA recently submitted it to An Bord Pleanála for fast-track planning approval.
    Basic stations planned to keep cost of metro line to €4.58bn
    Frank McDonald, Environment Editor

    Underground stations with bare concrete walls, no canopies over entrances, no escalators from street to concourse levels and fewer ticket machines are among the "value engineering" elements of the planned Dublin metro line linking St Stephen's Green with Swords.

    According to documents released belatedly under the Freedom of Information Act, the Railway Procurement Agency (RPA) said these "trade-offs" were needed to cut the capital cost of the project to €4.58 billion - an estimate cited in one letter dated July 8th, 2005.

    Though all monetary figures in every document were blacked out to maintain strict confidentiality surrounding the metro project, it is possible to discern on close inspection that the overall cost of this 17km line was estimated by the RPA at €4.58 billion in 2004.

    The relevant letter from Julie O'Neill, secretary general of the Department of Transport, to David Doyle, deputy secretary general of the Department of Finance, noted that this figure comprised "direct construction cost, risk contingency, fees, insurance and VAT".

    In 2003, an RPA estimate that a metro line linking Dublin airport with the city city centre would cost as much as €4.8 billion led to protests from politicians and commentators who believed that the price was too high compared to other European cities, particularly Madrid.

    Two years later, Ms O'Neill explained that the more recent figure of €4.58 billion was "the estimated cost that a private bidder would have to spend to build the metro before taking financing costs into consideration", based on the RPA's more economical proposals.

    Since then, the estimated cost would have risen due to "construction inflation" as well as the commitment made by Fianna Fáil before last May's general election to route the line underground through Ballymun and the plan to provide an additional station at Parnell Square.

    Estimates of how much it will cost to go underground in Ballymun, rather than at surface level along its main street as originally proposed, range from €200 million to €400 million. The cost of the additional station, even with no frills, would be as much again.

    In its outline business case for metro, submitted to the Department of Transport in November 2002, the RPA said the benefit-to-cost ratio of a line from Swords to the city centre would range from 0.65:1 to 0.81:1, based on discount rates of 5 per cent and 3.5 per cent respectively.

    The equivalent benefit-to-cost ratios of a line from Swords to Bray were put at 0.91:1 or 1.14:1. In other words, the only metro that would pay off in economic terms would be a line running all the way from Swords to Bray (assuming a 3.5 per cent discount rate).

    By comparison, as RPA chief executive Frank Allen told the department in February 2005, the benefit-to-cost ratio of a city centre link between the two existing Luas lines would be 3.6:1 or three times more than the best scenario painted for the metro line's performance.

    But the agency was undeterred by its own projections. "It is important to recognise that standard cost-benefit analysis [CBA] includes only those benefits that can be easily monetised and as a result ignores some of the most important benefits of improved public transport.

    "It is largely for this reason that major international transport projects have been justified with CBA results of less than 1:1," it said. However, the only two examples cited in the report were London's Docklands Light Railway (0.5:1) and Jubilee Line extension in London (1:1).

    In both cases, according to the RPA, the investment was justified on the basis of wider benefits of regeneration and social inclusion in London's docklands. Similarly, it argued, Dublin's economy, society and environment would benefit from building a metro serving the airport.

    But the report conceded that an airport-city centre line "has a relatively poor economic performance". This was to be expected as it included "the most expensive part of metro . . . without yet reaching the range of markets" that would be served by extending it to Bray.

    Although the government had decided in January 2002 to proceed with a metro linking Swords with Bray, the southern leg of this route - now partly served by the Sandyford Luas line - was not included in its Transport 21 investment programme unveiled in November 2005.

    Instead, a second orbital metro line linking Tallaght with Ballymun, via Clondalkin and Blanchardstown, made it into the €34.4 billion programme - even though none of the documentation released by the Department of Transport shows that it was subjected to any study.

    In its outline business case for the Swords-Bray metro line, the RPA estimated that it would carry 59 million passengers per year, of which nearly nine million would be going to or coming from Dublin airport - representing just 20 per cent of all airport-related journeys.

    According to the RPA, metro patronage "is highly dependent on the extent of system phasing and implementation of a sustainable urban development strategy which supports public transport" - notably the adoption of "road demand management" (ie, congestion charging).

    As its November 2002 report said, the RPA "has not included road demand management in its central economic case. If the Government implements a road demand management strategy before metro opens, it will substantially improve the metro business case".

    Even though the projected 59 million passengers a year would be about three times what the Dart carries, the agency predicted that patronage could rise by up to 20 per cent annually and 30 per cent at peak times if road congestion charging was introduced in Dublin.

    With the metro expected to cause land values to rise in the area it serves, the RPA said the best way of capturing at least some of these gains to offset costs would be to use Section 49 of the 2000 Planning Act to levy all new developments within a 1km radius of each station.

    In its cost-cutting "revised proposal" for the first phase, submitted in June 2003, it drew attention to the proposed savings, saying they "do give rise to certain trade-offs (ie, lower station specification than in metros in cities such as Copenhagen and elsewhere)".

    The RPA also pointed out that the introduction of 24-hour working, if permitted in Dublin, would reduce the tunnelling construction timetable by three months, and it recommended "24-hour tunnelling in areas where its impact will be low" - mainly non-residential areas.

    "Economic analysis shows the revised metro proposal to be much stronger in cost-benefit terms", according to the agency. The benefit-to-cost ratio had now risen to 1.31:1, compared to the much lower ratios projected in the outline business case of November 2002.

    The RPA also proposed that the Government should simply announce an alignment for the airport-city centre route, without prior public consultation, saying that "a Government announcement of the route would reduce the risk of [legal] challenge" in the High Court.

    At the time, it was assumed that the proposed metro line would be approved without further delay by the Cabinet sub-committee on infrastructure, so that it could be built over four years from 2006 to 2009 as a public-private partnership (PPP) project.

    "Cost estimates were prepared in anticipation of a Government decision in December 2002 and subsequently, following submission of the revised proposal, a Government decision in mid-2003. Estimates need to be adjusted to take account of escalation in capital costs since then".

    As the RPA noted in March 2005: "Twenty months have now passed since submission of the revised proposal, and RPA has stood down its engineering, financial and legal consultants. It is estimated that remobilising this team will take four months.

    "Adding this remobilisation to the 20 months equates to a 24-month overall delay from when the revised proposal was submitted. This time needs to be added to the programme envisaged in June 2003, thus giving a revised construction end-date of December 2011".


«13

Comments

  • Closed Accounts Posts: 3,082 ✭✭✭Chris_533976


    Underground stations with bare concrete walls, no canopies over entrances, no escalators from street to concourse levels and fewer ticket machines are among the "value engineering" elements of the planned Dublin metro line linking St Stephen's Green with Swords.

    Uh oh. Irishness at it again. Well done lads. Build the stations, but screw the passenger with simple things.


  • Closed Accounts Posts: 122 ✭✭Prof_V


    A couple of observations:

    The benefit-to-cost ratios published in the Oireachtas Joint Committee on Transport's report were 1.31:1 for the Airport line (as quoted for June 2003 in the article) and 1.59:1 for the Swords extension (alone), both at 5% discount rate. This is for the plan as it stood in late 2003; since then, there've been changes that would increase costs, but also some that would raise benefits (such as interchange with the Maynooth line, better access to the airport, Parnell Square station etc.)

    It's not clear what year the patronage figures quoted here were projected for. The above report quotes 26.35 million for a city-Swords line in 2010. The RPA now uses 34 million, presumably for a later year (the report implied a rise of nearly one-third between 2010 and 2016) though additional stations and interchanges, plus other T21 projects, would also drive the number up).

    "Just" 20% of air passengers is actually a pretty decent rail share by international standards; even bigger airports with rail services in several directions rarely manage better than 25%.

    I suspect the 2002 material reflects, at least in part, the fact that what was envisaged then was closer to a heavy metro. (Also, don't forget this was at the time when it was being confidently predicted that Luas would only carry half the numbers projected).

    As for the comparison between Metro and the Luas extension, it's hardly apples-to-apples. Minor extensions, unless they're completely crazy, are always going to have very good cost-benefit performance. And, of course, said extension will also now cost considerably more than would have been predicted two years ago.


  • Registered Users, Registered Users 2 Posts: 1,274 ✭✭✭gjim


    It's not clear what year the patronage figures quoted here were projected for. The above report quotes 26.35 million for a city-Swords line in 2010. The RPA now uses 34 million, presumably for a later year (the report implied a rise of nearly one-third between 2010 and 2016) though additional stations and interchanges, plus other T21 projects, would also drive the number up).
    I'd love to see the actual figures and calculations. I mean, even 34 million journeys at 2 euros operational profit a pop (and that's being extremely generous) isn't going to make any sort of dint in a 5 billion capital cost financially.
    As for the comparison between Metro and the Luas extension, it's hardly apples-to-apples. Minor extensions, unless they're completely crazy, are always going to have very good cost-benefit performance. And, of course, said extension will also now cost considerably more than would have been predicted two years ago.
    Yeah but there's a basic flaw in this analysis (for extensions) as it ignores the loss of utility on the rest of the line. For example, the Green line is now basically jammed to the extent that it's almost useless for commuters going into town at rush hour if you live closer than Cowper. Extending the line will, in isolation, be justified in terms of the cost and benefit of the extension. However, it won't take into account that the line will now be useless to people any closer than Windy Arbour.

    I hope their analysis isn't as simplistic as this but it would explain why the priority seems to be on extensions rather than new lines. For example, adding 8km to the Sandyford end of the Green line might cost marginally less than building a new 8km line somewhat in parallel, say through Harold's cross toward Templeogue but the latter would have the capacity to carry twice as many passengers in and out of town than the former.


  • Closed Accounts Posts: 122 ✭✭Prof_V


    gjim wrote:
    I'd love to see the actual figures and calculations. I mean, even 34 million journeys at 2 euros operational profit a pop (and that's being extremely generous) isn't going to make any sort of dint in a 5 billion capital cost financially.
    That's not quite what economic (as opposed to financial) CBA is about; essentially it's comparing the benefits to society - journey time savings, reduced congestion and accidents, (sometimes) reduced pollution, etc. etc. with the capital and operating costs of a project. Very few rail projects - essentially just extremely minor schemes plus a few special cases like certain bulk freight lines - will cover their capital costs from fare income. (Of course, the fact that DART was expected to do this is another story...)


  • Registered Users, Registered Users 2 Posts: 612 ✭✭✭McSpud


    gjim wrote:
    Yeah but there's a basic flaw in this analysis (for extensions) as it ignores the loss of utility on the rest of the line. For example, the Green line is now basically jammed to the extent that it's almost useless for commuters going into town at rush hour if you live closer than Cowper. Extending the line will, in isolation, be justified in terms of the cost and benefit of the extension. However, it won't take into account that the line will now be useless to people any closer than Windy Arbour.

    Apparently by not including the extension to Swords the RPA are hiding those costs but also not recognising that the Metro as currently planned will not match demand as only similar capacity to the Luas Green.

    Iarnroid Eireann could just extend the Dart & Arrow services but then how could the RPA justify their jobs with nothing to manage?

    :rolleyes:


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 18,126 ✭✭✭✭Idbatterim


    €5 billion! €5 billion!, i think that figure is so insane, so incomprehensible that it might as well be €10 billion, €15 billion. For that amount why not just run a non stop bus service with flyovers etc into the city centre via the port tunnel to connect to connolly, from where you can make a connection? Heres an idea stop messing around with Dublin Airport, build a completely new airport from scrath somewhere in North County Dublin on the coast I.e no need for planes to fly over land. Also fuel could be transported by tanker ships directly to the airport. Also the council currently have a cap of 35 mpa on the airport, when T2 is completed the DAA want to reduce the capacity of T1 from 25 million to 15 million and want to spend several hundred million to do this!!! Extend the dart line to the new airport, it would also have access to the M1, then with the interconnector, you could travel from the airport to connolly, stephens green and heuston all the major current and future interchanges. Then rezone the thouands of acres of Airport and surrounding area that cant be developed due to the airport, into retail, industrial and residential developments, worth probably a figure thats almost incomprehensible. In alot of ways the proposed metro is being built to serve the airport, Say T2 is to cost €1 billion, the metro at €5 billion will probably cost more to build than a new adequate airport on a greenfield site!


  • Registered Users, Registered Users 2 Posts: 17,213 ✭✭✭✭therecklessone


    Idbatterim wrote:
    Heres an idea stop messing around with Dublin Airport, build a completely new airport from scrath somewhere in North County Dublin on the coast I.e no need for planes to fly over land.

    I'm guessing you haven't thought that one through...


  • Closed Accounts Posts: 5,366 ✭✭✭luckat


    It'd be handy if they'd just run the 16A more often while they're building the dratted thing.

    Last time I was on a plane I got the Airlink (too early in the morning for the 16A) out, and on the way back I came out and stood at the 16A stop, only to discover that there wasn't one for 50 minutes. Bleagh. I'll go back to driving to the airport.


  • Registered Users, Registered Users 2 Posts: 18,126 ✭✭✭✭Idbatterim


    what havent I thought out the recklessone?


  • Registered Users, Registered Users 2 Posts: 17,213 ✭✭✭✭therecklessone


    Idbatterim wrote:
    what havent I thought out the recklessone?

    Lets say for example you build your fictional airport. You put a runway in that is on an east/west axis, so that arriving flights can approach over the sea and touchdown as close to the coast as possible. Except for two small problems...

    1. You will have departures...they need to use the same runway as the arrivals...they need to depart into the wind...if the wind favours arrivals landing from the east, it favours departures to the west, i.e. over land.

    2. The wind changes, as it has a tendency to do. Now the wind favours the easterly runway, and you have aircraft flying downwind legs over land before turning on to finals.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 612 ✭✭✭McSpud


    luckat wrote:
    Last time I was on a plane I got the Airlink (too early in the morning for the 16A) out, and on the way back I came out and stood at the 16A stop, only to discover that there wasn't one for 50 minutes. Bleagh. I'll go back to driving to the airport.

    I attempted to use the Airlink just the once from O'Connell Street & never again.

    * Took me 5-10 minutes to find the stop but (lets just that down to me) no bus went past me
    * Timetable said was due at something like 7.30 but it never arrived & by 7.50 & no sign of bus i gave up & got the taxi.

    It might be acceptable for regular buses to be late but I assumed an air link would need to be on tighter schedule as 20-25 minutes will cause people to miss departures.

    :mad:


  • Closed Accounts Posts: 7,221 ✭✭✭BrianD


    The RPA are effectively CIE Mk II and fast becoming another bloated tax payer funded quango.

    The articles in todays papers are interesting as they finally confirmed to those who could not see it:

    Metro is just a fancy LUAS. I can't understand why the RPA can't call them LUAS lines - though I presume that Metro sounds sexier and more promising.

    how can those in the RPA justify their overpaid jobs by coming up with a glorified tramline that won't go to Swords (probably), has poor linkages with other tranport modes and is going to cost €5bn?!?

    Even if they do bring Metro North they are talking about a Swords-Bray metro. Odd last time I looked Bray already had a DART link to the city centre. So the RPA believe that duplication is a good thing?

    No frills stations? What's that about? How can culling a few ticket machines and escalators be a saving on a project that is already costing billions?!? Once again the RPA are demonstrating that they have no idea how to develop and manage a project.

    Though not the RPA's fault it is incredible that the Government has sat on an integrated DART project since 2004 (or in reality 1984). We could by now have a 3 line DART service in operation.


  • Registered Users, Registered Users 2 Posts: 4,316 ✭✭✭KC61


    McSpud wrote:
    I attempted to use the Airlink just the once from O'Connell Street & never again.

    * Took me 5-10 minutes to find the stop but (lets just that down to me) no bus went past me
    * Timetable said was due at something like 7.30 but it never arrived & by 7.50 & no sign of bus i gave up & got the taxi.

    It might be acceptable for regular buses to be late but I assumed an air link would need to be on tighter schedule as 20-25 minutes will cause people to miss departures.

    :mad:

    That's very odd as I've never experienced anything like that with the 747/748, and I'm a fairly regular user of same. They tend to be very reliable, and the inbound journey is now virtually guaranteed to take less than 25 minutes to O'Connell Street through the use of the Port Tunnel.


  • Registered Users, Registered Users 2 Posts: 4,316 ✭✭✭KC61


    luckat wrote:
    It'd be handy if they'd just run the 16A more often while they're building the dratted thing.

    Last time I was on a plane I got the Airlink (too early in the morning for the 16A) out, and on the way back I came out and stood at the 16A stop, only to discover that there wasn't one for 50 minutes. Bleagh. I'll go back to driving to the airport.

    There is also the 41 service from the Airport to City Centre, covering most of the 16A northside route. If you were going to south Dublin, it is possible to take the 747 to O'Connell Street and catch up with a departed 16A or catch a 16.


  • Registered Users, Registered Users 2 Posts: 14,761 ✭✭✭✭Winters


    First of all, the the poster who wanted to move Dublin airport... I think you'll find it's already in North County Dublin... and you would have to go much further afield to find any sort of available, suitable and big enough land bank to cater for 35+ million passengers.

    Moving Dublin airport is ludicrous. Just because it's poorly laid out doesnt mean it should be moved.

    As for the metro, the Porto Metro is the example that the RPA are using and seeing as the frequency shall range from one tram every 40 seconds/3mins etc then people shall not be waiting in stations that long. Look at the Porto stations for an example or what they are proposing.


  • Registered Users, Registered Users 2 Posts: 796 ✭✭✭jrar


    Underground stations with bare concrete walls, no canopies over entrances, no escalators from street to concourse levels and fewer ticket machines are among the "value engineering" elements of the planned Dublin metro line linking St Stephen's Green with Swords.



    Yep, why do it right first time when you can always go back and re-do it in the future at a cost which turns out to be many multiples of the original.....it sounds like the rail equivalent of the M50 junctions !


  • Banned (with Prison Access) Posts: 3,073 ✭✭✭mickoneill30


    jrar wrote:
    Underground stations with bare concrete walls, no canopies over entrances, no escalators from street to concourse levels and fewer ticket machines are among the "value engineering" elements of the planned Dublin metro line linking St Stephen's Green with Swords.

    Any idea where you're getting that info from. It would be nice to give links when you're making statement like that.

    From http://www.rpa.ie/?id=327

    Q. Will there be escalators and lifts in the stations?

    A. Yes. All stations will be fully accessible. There will be lifts from street level to platform level in all stations and escalators where required.


  • Registered Users, Registered Users 2 Posts: 14,761 ✭✭✭✭Winters


    The mined stations will have escalators and the open box constructed stations will more than likely have steps. Every station shall also have lifts, that's law. It all depends on the depth from the surface though.

    The RPA are just simplifying the station designs. We, the tax payers, cant give out about the cost as well as demanding ornate luxurious stations!

    http://en.wikipedia.org/wiki/Image:Esta%C3%A7%C3%A3o_trindade_Metro_do_Porto.jpg

    http://en.wikipedia.org/wiki/Image:Porto_metro_cdm.jpg

    http://en.wikipedia.org/wiki/Porto_Metro

    Interesting to note:
    As of 2007, the total cost of Porto Metro mass transit public transport system stands on 3,500 million euros - over 1% of Portugal's GDP. The first phase of the project alone, which was led by the mayors of several Grande Porto (Greater Porto) municipalities including Valentim Loureiro as a chairman of the state-owned company, was 140% more expensive than initially planned which means a slippage of over 1,500 million euros. The Porto Metro state-owned company has reported losses every year, reaching a record loss of 122 million euros in 2006


  • Registered Users, Registered Users 2 Posts: 4,316 ✭✭✭KC61


    Any idea where you're getting that info from. It would be nice to give links when you're making statement like that.

    From http://www.rpa.ie/?id=327

    Q. Will there be escalators and lifts in the stations?

    A. Yes. All stations will be fully accessible. There will be lifts from street level to platform level in all stations and escalators where required.

    The lack of escalators etc. was in the Irish Times article yesterday.


  • Closed Accounts Posts: 1,331 ✭✭✭MarkoP11


    It think it is very important to note Frank McDonald is working off information requested under FOI in November 2005 which was only recently released, a lot has changed since

    It is important to note there where 4 distinct stages in the metro

    1. Gold plated 2002 version which had a publically admitted cost of 4.8 billion
    2. The cut down version after the panic of seeing the 4.8 billion one, this is the one Frank is chasing from 2004
    3. The one put out to public consultation which is a lot more like option 1 than 2, option 3 is somewhere between 1 and 2 in terms of specification. Most of the capacity issues are solved here
    4. What is being built with the better interchange at Drumcondra and O'Connell Bridge, brings us to a fairly decent modern metro with good interchange

    End result is we are back at the 5 billion tag, but this is a PPP so the actual cost in real terms is about 2 billion but the cost to the state over the PPP is about 2.5 times that

    I will shamelessly plug the fact this has been discussed before and I know it caused some serious trouble in the DoT and the RPA though there was a sly grin down in IE as a result.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 1,274 ✭✭✭gjim


    Hi Prof_V. Yes you are right regarding "economic" CBA. However, I'm always suspicious of such numbers. There are presented as hard scientific data but in reality they are a distillation a whole load of guesses, estimates and figures pulled out someone's ass.

    With a capital cost for this project of 5 billion and the given projected passenger numbers, each passenger trip would be required to deliver over 8 euro in economic benefits a trip to cover the cost of capital at 5% (in reality, if a PPP is involve the cost of capital will be double this). Now if you're the RPA it's in your interest to factor in as many benefits as possible. Even taking two obvious benefits: time savings for passengers and the environmental savings how are these quantified? There is so much leeway in coming up with figures for these benefits, the result of such analysis, in isolation, is pretty meaningless.

    The only way to ensure the figures aren't complete nonsense is to use the very same analysis to look at the benefits of similar or comparable projects. Given the Luas cost 800 million and handles over 20 million journeys a year, I can't see the airport metro comparing very well. If this analysis supports the 5 billion euro metro line, then I suspect the same analysis would support spending 4 billion on the two disconnected Luas lines which we know for sure is nonsense. How about even using the same analysis to compare this metro with the old idea of the DART spur, costed a few years back at 400 million? Or even a simple high frequency bus service going via the Port Tunnel? Given the option of the single Metro north project or increasing the size of the Luas network 6 fold, which offers superiour benefits given the costs would be roughly similar?


  • Closed Accounts Posts: 1,133 ✭✭✭Slice


    I think the lack of consistency in planning arising from continued political interference is the main point of the article. It's an unfortunate combination of over-sensitivity to ever-changing public opinion and a propensity to let the planning of major infrastructure proceed based on narrow or ill-informed considerations that's the issue with Government. It's why 3 years after the opening of the Luas we are still looking at the exact same set of circumstances with Metro that caused Luas to spend more time on the drawing board than under construction. Remember how first they were meant to link up, then they weren't, then the Green line was meant to go underground, then it wasn't and now it's going to be linked up. There is no excusing this type of carry-on at the expense of a city that's coming to a standstill and what's worse is that there is no accountability for those who are causing all the delays.

    Here is today's IT editorial;
    Metro project raises questions

    The disclosure in yesterday's Irish Times that Dublin's first metro line, from St Stephen's Green to Swords, will cost at least €5 billion and probably much more by the time it is finished is quite stunning. The 17km route, much of it underground, would be the biggest single investment in public infrastructure in the history of the State.

    Yet the staggering price tag for Metro North has only surfaced because one of the figures in documents released to this newspaper under the Freedom of Information Act was not blacked out sufficiently to obscure it. And this was nearly two years after the request for access to the documents was first made, a day after the government unveiled its Transport 21 programme in November 2005.

    Serious questions must be asked about the priority being assigned to the metro project, as opposed to other schemes in the €34.4 billion investment programme, such as the strategically important underground rail interconnector between Heuston Station and Spencer Dock. The real danger is that Metro North and Metro West, which would link Tallaght with Ballymun via Clondalkin and Blanchardstown, will gobble up so much money that there won't be enough left to fund the interconnector, which alone offers the prospect of integrating Dublin's disparate transport "system" by linking suburban rail services with the Dart and Luas lines.

    The cost-benefit analysis of Metro North, as a stand-alone project, is not impressive. Even with "value engineering", such as the no-frills stations currently proposed, the benefit-to-cost ratio is put at 1.31:1 - nearly three times lower than the equivalent calculation by the Railway Procurement Agency of a city centre link between the Tallaght and Sandyford Luas lines. Yet why should Dublin settle for underground stations with bare concrete walls, no canopies over entrances and only a lift and staircase from street to concourse levels? If the metro is to be built, it should be built well. As architect Norman Foster said in a recent television programme on his breathtaking Millau Viaduct in France, the things that make connections - bridges, airport terminals, stations - are more important than buildings in forming people's perceptions of the public realm.

    Metro North would only make sound economic sense if it continued southwards from St Stephen's Green to Ranelagh, Sandyford, Cherrywood and Bray - in effect, supplanting the Luas Green Line. Pursuing it as a discrete project is highly questionable, particularly as it would do little or nothing for people living on the extremities of Dublin's commuter belt. And it has never been adequately explained why a metro is needed at all rather than, say, an extensive light rail network - such as in Bordeaux, where the city has been transformed by a tramway system that will end up costing only €1 billion.

    Whatever about the sensitivities associated with public-private partnership (PPP) projects, the public is entitled to know, at least in ballpark terms, what major pieces of infrastructure are likely to cost. It is wrong for the Government to keep taxpayers in the dark.


  • Closed Accounts Posts: 3,082 ✭✭✭Chris_533976


    Very good article that IT journal one.


  • Closed Accounts Posts: 1,331 ✭✭✭MarkoP11


    Wonder what the fuss is about the 5 billion, its been in the public domain since 2004, its here http://www.oireachtas.ie/viewdoc.asp?fn=/documents/Committees29thDail/jct/metro-report/document1.htm

    Frank McDonald as always does his homework and getting the exact numbers on paper is always good for the public, the fact it took 21 months to get the paperwork is shocking, the DoT are great at taking every last day in the FOI process

    Metro capital cost is about 2 billion, its the financing which makes it look like 5 billion


  • Registered Users, Registered Users 2 Posts: 6,315 ✭✭✭ballooba


    I've experience dealing with the RPA. They spend money like it's going out of fashion. It was the best christmas ever in my house. In September. Jokers.


  • Registered Users, Registered Users 2 Posts: 73 ✭✭niall2j


    MarkoP11 wrote:
    End result is we are back at the 5 billion tag, but this is a PPP so the actual cost in real terms is about 2 billion but the cost to the state over the PPP is about 2.5 times that

    Can I ask, if the mark up is so great for pursuing a PPP style delivery of the project, then what is the case for doing so? Would it not make more sense for the government to fund the full cost themselves and simply contracting out the operation of Metro North thus significantly reducing the overall cost from €5bn or so?

    Or would this provide an unacceptable drain on their available capital?


  • Closed Accounts Posts: 1,133 ✭✭✭Slice


    PPPs were brought in at the insistance of the PDs based on idealogical grounds; given the disaster of the PPP for the refurbishment of the London Underground and the demise of the PDs is it not time we put this little puppy to sleep??


  • Closed Accounts Posts: 122 ✭✭Prof_V


    gjim wrote:
    Now if you're the RPA it's in your interest to factor in as many benefits as possible. Even taking two obvious benefits: time savings for passengers and the environmental savings how are these quantified? There is so much leeway in coming up with figures for these benefits, the result of such analysis, in isolation, is pretty meaningless.

    The approach is more-or-less standardised (not yet to the same degree in Ireland as it is in, say, the UK, though). The relevant document is http://www.transport.ie/upload/general/5830-1.pdf. However, as this is dated 2004, it won't have applied to some of the RPA's early analyses, though I think there was some standardisation before then, particularly in respect of values of time.
    The only way to ensure the figures aren't complete nonsense is to use the very same analysis to look at the benefits of similar or comparable projects. Given the Luas cost 800 million and handles over 20 million journeys a year, I can't see the airport metro comparing very well.

    It's difficult to compare a journey on one system directly to a journey on the other. Metro is likely to have longer average journeys and higher time savings even for journeys of equivalent length. Remember too that the Metro will have a minimal permanent effect on road capacity compared with Luas, so there'll be a lot less in the way of traffic delays due to the system. This can be a significant disadvantage to street-running rail lines.

    Incidentally, I think the methodology is back-validated, as far as possible, in the ex-post assessment of completed projects (like Luas), but I'm unsure of this.

    I do accept your point about cost-benefit methodology affecting the result; for instance, the Cork suburban rail project had a benefit-cost ratio of 1.11 in the Strategic Rail Review but 2.4 in the parallel IÉ feasibility study. This is one of many reasons why you can't use CBA alone to make a decision.

    Just to stress again, too, that larger projects tend to have lower benefit-cost ratios. 1.31:1 isn't stellar by those standards (though, on the same figures, going to Swords would raise the ratio somewhat), but it's hardly poor.


  • Closed Accounts Posts: 122 ✭✭Prof_V


    Slice wrote:
    PPPs were brought in at the insistance of the PDs based on idealogical grounds; given the disaster of the PPP for the refurbishment of the London Underground and the demise of the PDs is it not time we put this little puppy to sleep??

    I'm inclined to agree with you as far as this particular project is concerned, but I'm not sure how applicable the London Underground example is. The PPPs (more than one for different sections of line) on the Docklands Light Railway, which are more directly comparable as greenfield projects, work better, though I've never seen any proof they were cheaper than public procurement.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 5,346 ✭✭✭dowlingm


    MarkoP11 - is the IE Northern Line option to the airport still available, and if so for how much?


  • Closed Accounts Posts: 1,133 ✭✭✭Slice


    MarkoP11 - is the IE Northern Line option to the airport still available, and if so for how much?

    in whispered tone: Shhh! P11 aren't in favour of that anymore!

    :)


  • Closed Accounts Posts: 1,331 ✭✭✭MarkoP11


    London underground is not a good example, its a PPP (well 3 actually) to rebuild a system which is falling apart which actually very little is known about its actual condition, so it was a almost blind bidding process. And of course there have been some serious surprises which have jacked costs up.

    Normal PPP is greenfield, government contracts a consortia to build it and the availability payment is set there and then and is only paid once its up and running once the PPP ends typically 20-30 years it reverts to the state

    So the private sector is motivated to deliver as fast as possible since they start to get paid then and also to keep costs down while meeting spec since then the make more cash since the interest bill is lower. Upside is the risk is offloaded to the private sector and thus doesn't hit the state coffers, 2 billion is a lot of cash to have around

    Few interesting points
    1. CBA whatever, the Metro will make a significant operating profit similar to the Luas
    2. Cork suburban rail will carry 8 million and do so at a operating profit

    Grange Rd to Airport may be off the agenda as the land might have been taken out of the dev plan. Its not being developed any more in light of the metro, if metro gets pulled it will be back. And it does cover its costs of course there now is the Metro east on the table as well so the North Fringe

    Slice take a break enough of the cheap shots, at least Platform 11 actually made a difference in metro north, a difference for the passenger


  • Moderators, Motoring & Transport Moderators Posts: 14,093 Mod ✭✭✭✭monument


    Metro North would only make sound economic sense if it continued southwards from St Stephen's Green to Ranelagh, Sandyford, Cherrywood and Bray - in effect, supplanting the Luas Green Line.

    So, has the RPA looked at this in any meaningful way?


  • Registered Users, Registered Users 2 Posts: 78,577 ✭✭✭✭Victor


    monument wrote:
    So, has the RPA looked at this in any meaningful way?
    I imagine the aswer is most certainly "yes". However, somewhere there are shenanigans stopping it coming forward.

    It makes a lot more sense to connect them up than not connect them up. Interconnection, simplicity of journey, duplication of infrastructure, cost, disruption and common sense all say continue southside.


  • Registered Users, Registered Users 2 Posts: 2,461 ✭✭✭popebenny16


    Slice wrote:
    in whispered tone: Shhh! P11 aren't in favour of that anymore!

    :)

    No, you're mixing up the concepts of "aren't in favour" with "it's not going to happen, lets make the best of the alternative" which as Marko points out is what we have helped to do. Cant recall your glorious contribution.

    I presume that you would like to join us in laying down across the Metro Tracks to prevent works being undertaken?

    :rolleyes: :rolleyes: :rolleyes:


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 911 ✭✭✭steve-o


    Victor wrote:
    I imagine the aswer is most certainly "yes". However, somewhere there are shenanigans stopping it coming forward.

    It makes a lot more sense to connect them up than not connect them up. Interconnection, simplicity of journey, duplication of infrastructure, cost, disruption and common sense all say continue southside.
    It would be a big challenge to find a place along the green line to dig the tunnel entrance and keep the Luas operational during construction. The route and design of the Cherrywood extension isn't very Metro friendly either.

    Extending Metro North in a south-west direction towards Rathmines, Harold's Cross and Tempelogue has been mooted before. Has it ever been given serious consideration? I wonder if there any areas in that direction that can be targeted for high density development around potential stations.


  • Closed Accounts Posts: 696 ✭✭✭Transport21 Fan


    McSpud wrote:

    Iarnroid Eireann could just extend the Dart & Arrow services but then how could the RPA justify their jobs with nothing to manage?

    :rolleyes:

    Have a chat with any of the former staff who worked for CIE and left to join the RPA.

    Everything out of CIE these days is all...Broadstone...Broadstone...Broadstone...

    This bothers me.

    If you were an ambitious engineer and you had a choice between reopening Broadstone and Sixmilebridge, or ordering parts for a real Metro - which option would you chose?

    Metrobest Knows Best.


  • Closed Accounts Posts: 696 ✭✭✭Transport21 Fan


    Cant recall your glorious contribution.


    I have it on good grounds that he took a photo of a weed spray train in south Wexford and uploaded it to IRN.


  • Closed Accounts Posts: 122 ✭✭Prof_V


    steve-o wrote:
    It would be a big challenge to find a place along the green line to dig the tunnel entrance and keep the Luas operational during construction.
    Alexandra College is probably the only halfway sensible location. This does, of course, mean about 3km of extra tunnel with limited potential for intermediate traffic (as it's close to the existing Green Line), so I don't think it makes sense until the Green Line gets so busy it has to be done.
    The route and design of the Cherrywood extension isn't very Metro friendly either.
    There's always the option of operating a Metro service to Sandyford only, sharing tracks between the portal and Sandyford with Luas services to the south end of the line.
    Extending Metro North in a south-west direction towards Rathmines, Harold's Cross and Tempelogue has been mooted before. Has it ever been given serious consideration?
    There's apparently a commitment to a feasibility study in T21 (insofar as anything is "in" or "out" of T21...).
    I wonder if there any areas in that direction that can be targeted for high density development around potential stations.

    Well, the industrial areas near the KCR. Also Cathal Brugha Barracks, if the Army decided it didn't need it, though I'd say a fair chunk of that would have to go over to open space because Rathmines is so badly served in that respect. The line would support densification in the centre of Tallaght, though this is already planned.


  • Closed Accounts Posts: 696 ✭✭✭Transport21 Fan


    Prof_V wrote:

    There's always the option of operating a Metro service to Sandyford only, sharing tracks between the portal and Sandyford with Luas services to the south end of the line.

    I was told this is the long-term plan anyways. They want MetroNorth to eventually run from Donabate to Sandyford, but we are talking about 2020.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 5,346 ✭✭✭dowlingm


    Terminating metronorth at St Stephen's Green will be seen in the future I think as a similar mistake to terminating Green Luas there and not O'Connell St.

    If Metronorth continues into Rathgar, Terenure, Templeogue it relieves the strain on the inner sectors of Green Luas and reduces congestion in a very narrow road corridor from Tallaght into the city centre.

    It would be expensive, no question, but a lot of the costs of metronorth are probably startup costs (vehicle depot, setting up training and procedures, control centre) which would not only benefit metrowest but any extensions of metronorth. The TBM is already in the ground so it's a question of pushing it on and dealing with the spoil (and the canal). From the Spawell roundabout on (emergence portal?) it might be able to run overground in the N81 median if there was a case to keep going and link to metrowest and a shared southern depot and the M50 was not a showstopper.

    Therefore you are left with the additional stations, tunnelling and vehicles and staff to support it. But at least this would then be in addition to rather than instead of Green Line which would stay LUAS and integrated to the forthcoming BX and D alignments to Liffey Junction.


  • Closed Accounts Posts: 696 ✭✭✭Transport21 Fan


    Yes indeed, and it's amazing how so many people are forgetting that a lot of the price tag of MetroNorth (and Luas for that matter) are capital start-up costs hence why the Interconnector was costed so much cheaper. CIE already had most of the kit.


  • Registered Users, Registered Users 2 Posts: 78,577 ✭✭✭✭Victor


    steve-o wrote:
    It would be a big challenge to find a place along the green line to dig the tunnel entrance and keep the Luas operational during construction. The route and design of the Cherrywood extension isn't very Metro friendly either.
    There are numerous sites - Iveagh Gardens/Adelaide Road, the old John Player site, Alexandra College.
    Extending Metro North in a south-west direction towards Rathmines, Harold's Cross and Tempelogue has been mooted before. Has it ever been given serious consideration? I wonder if there any areas in that direction that can be targeted for high density development around potential stations.
    There a whole load of squares in and around Rathmines that could be used - not without cost, but cheaper than St. Stephen's Green.
    dowlingm wrote:
    The TBM is already in the ground so it's a question of pushing it on and dealing with the spoil (and the canal).
    Canals are easy - during construction you drain them and put in a small diameter pipe to handle the flow.


  • Registered Users, Registered Users 2 Posts: 9,389 ✭✭✭markpb


    Maybe I'm missing something obvious here but instead of replacing the Luas Green line with a metro, why not just connect Metro North with the Green line so the trams can run from Swords to Sandyford (and beyond)? It would seem to be much cheaper and simpler.

    It also allows the TBMs to be directed somewhere else, perhaps driving the metro south west instead of south. Surely we're better off achieving better coverage than replacing or upgrading an existing tram line?


  • Registered Users, Registered Users 2 Posts: 5,346 ✭✭✭dowlingm


    markpb - they want to run metro trains up to every 90 seconds. For that to work an interlining junction at StSG between Green Line and a putative MetroSouthWest would be next to impossible I think. They couldn't make that work here in Toronto on 3 minute headways during a recent maintenance procedure without it going @rse over teakettle a few times.


  • Closed Accounts Posts: 122 ✭✭Prof_V


    Victor wrote:
    There are numerous sites - Iveagh Gardens/Adelaide Road,
    Which only works if the line crosses Adelaide Road on the level; that means Metro running in mixed traffic on Peter Place, too. Go under Adelaide Road and you've nowhere to put the ramp to surface level without ripping the Green Line out of Peter Place. Go over Adelaide Road (fending off the aesthetic lobby) and you get a lot of land take in the Iveagh Gardens, plus, at any workable gradient, the line will be dangerously shallow under the buildings on the south side of the Green.
    the old John Player site,
    Where is this? The only John Player site I know is the factory on the South Circular near the National Stadium, which certainly isn't on the Green Line. Is this the Carroll's site on the canal? The portal in the 1998 Atkins study was around here, and it would work perfectly well for a greenfield scheme. Unfortunately, you have to work around the Green Line. If you want to avoid prolonged closure of the Luas line and minimise demolition, you have to get to Luas track level north of Dartmouth Road, but the space available for the ramp would force you to cross the canal at street level:( . With a bit of demolition, you could get to Northbrook Road, which still doesn't give enough depth, especially with the sewer tunnel below Grand Parade. Basically I think there's no way of making this site work without extended Luas closure or extensive demolition.
    Alexandra College.
    Possibly the only workable location.
    There a whole load of squares in and around Rathmines that could be used - not without cost, but cheaper than St. Stephen's Green.
    Presumably you mean as tunnelling worksites, rather than for high-density development:) .
    Canals are easy - during construction you drain them and put in a small diameter pipe to handle the flow.
    I doubt a bored tunnel would even need that in ordinary circumstances, and the tunnel would almost certainly be bored at that point. (You could try cut-and-cover under the canal as a solution to the Northbrook Road problem, but the need to go over the sewer tunnel might make that unworkable, and anyway you'd need to extend the cut-and-cover a bit north of the canal, which doesn't seem possible without large-scale demolition, or just (im)possibly, tearing up Harcourt Terrace.)


  • Registered Users, Registered Users 2 Posts: 9,815 ✭✭✭antoinolachtnai


    Prof_V wrote:
    Where is this? The only John Player site I know is the factory on the South Circular near the National Stadium, which certainly isn't on the Green Line. Is this the Carroll's site on the canal? The portal in the 1998 Atkins study was around here, and it would work perfectly well for a greenfield scheme. Unfortunately, you have to work around the Green Line. If you want to avoid prolonged closure of the Luas line and minimise demolition, you have to get to Luas track level north of Dartmouth Road, but the space available for the ramp would force you to cross the canal at street level:( . With a bit of demolition, you could get to Northbrook Road, which still doesn't give enough depth, especially with the sewer tunnel below Grand Parade. Basically I think there's no way of making this site work without extended Luas closure or extensive demolition.

    No, this can be done, without too much damage. You would have to take out a row of modern houses, but it is very feasible. The RPA would get all of what it would spend on real estate back when it sold off the site at the end of the tunneling project.

    The RPA has never canvassed the owners of this property. If they want to do this, they'd better get a move on, because there is planning permission applied for to knock down at least one of these of these houses and construct a taller building.


  • Closed Accounts Posts: 1,735 ✭✭✭Irish and Proud


    That's Enough!!! Now, what else can we do with €5bn?

    Let's forget about the metro for now and decide what we can realistically achieve with the €5bn. :)

    1) INTERCONNECTOR!!! €3bn :)

    Key part of major DART rail upgrade which will allow a fourfold increase in passenger capacity in Dublin (25m to 100m) by eliminating crossover and single point conflicts.

    2) Two DART lines replacing the current line: :)

    DART 1 - Bray/Greystones, via Loop Line, to M3(P+R)/Maynooth
    DART 2 - Hazelhatch, via Interconnector, to Balbriggan/Howth

    These lines (which are currently planned) will implement the increase in passenger capacity, as well as creating a much larger catchment area for the DART network.

    3) Feasibility Study for DART 3: Tallaght, via Citywest, Interconnector and Grange (Northern DART Line needs to be upgraded anyway), to Airport and possibly Swords. :)

    This third line would make good use of the Interconnector by linking the Airport to the city’s two mainline stations: Heuston and Connolly. Also, most additional sections required would be overground in relatively open terrain, so construction would be cheaper. Again, the DART catchment would be greatly expanded.

    4) 3/4 tracking on sections of the Northern, Western and South Eastern Commuter Lines:) - Express commuter trains might have a purpose then! :rolleyes:

    Oh no! Please don’t tell me that the SE DART line can’t be expanded :( - I travel it every day and see room for 3 tracking between Booterstown and Dun Laoghaire - OK some land reclamation, road undercutting at Monkstown, a couple of demolitions, a short one track tunnel section in Dun Laoghaire, and station modifications would be required, but could be done if the political will was there. Station modifications could typically consist of switching southbound platforms from land facing to sea facing towards a new southbound track alignment - existing southbound track would become a bi directional express line with platforms at Blackrock and Dun Laoghaire stations.

    A major headache regarding rail capacity is the lack of passing loops for trains running at different speeds. Passing could be accommodated by either creating multi-track sections such as the Kildare Route Project, or providing more platforms at key stations where for example, DART trains would allow connections to, and priority for, commuter trains. :)

    With the above done, we could have a major economic boom in Dublin which could generate well enough dosh for a proper metro with proper escalator and interchange provisions in the future. :D

    Now, about the LUAS…..


  • Registered Users, Registered Users 2 Posts: 5,346 ✭✭✭dowlingm


    Irish and Proud - Interconnector is separately funded from metro. It's not either /or.

    To me, we need the extra line that extending metronorth to Tallaght would provide rather than expensively connecting and somewhat upgrading Green LUAS to Metro, since we are now years behind where we are supposed to be. Let's face it, given the land acquisition and tunnelling you'd probably be at Harold's Cross for the same money as connecting to Green LUAS and then you're left with a somewhat useless Line BX tail.


  • Registered Users, Registered Users 2 Posts: 1,274 ✭✭✭gjim


    It's time for everyone to let go the fanciful notion that the Green Luas will be upgraded to metro. This idea/lie was created to cover Mary O'Rourke's damaging meddling with the original plan for a cross shaped tram system (extending north to the airport). Because she was too weak to politically support the orginal plan (against some city centre retailer NIMBYs) or too pig-headed to resist meddling with it, the tracks south of the canal were laid with and extra 100cm or so between them and this this was trumpeted as "future proofing" for the "inevitable" upgrade to metro. This was supposedly the public's compensation for living with a disconnected tram system in the short term.

    It's simply not going to happen. The disruption would be too great and the benefits minimal. The future for this Luas line is to continue as a tram line North to Liffey junction and hopefully at some stage beyond it.

    Metro North should extend to Tallaght or at least the TBM should continue south in the direction of Tallaght even if they don't have the money to lay the tracks and build the stations and so forth.


  • Advertisement
Advertisement