Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie

simple question

Options
  • 17-12-2018 2:05pm
    #1
    Registered Users Posts: 393 ✭✭


    eh we'll it should be!!
    If I spent 66k on getting a job done and it is only 80% complete, how much will total job cost? My brain has stopped working today.


Comments

  • Registered Users Posts: 6,199 ✭✭✭troyzer


    strandsman wrote: »
    eh we'll it should be!!
    If I spent 66k on getting a job done and it is only 80% complete, how much will total job cost? My brain has stopped working today.

    (66/8)*10= 82.5


  • Registered Users Posts: 1,437 ✭✭✭NewClareman


    strandsman wrote: »
    eh we'll it should be!!
    If I spent 66k on getting a job done and it is only 80% complete, how much will total job cost? My brain has stopped working today.

    10% costs 66/8 = 8.25.
    Job cost = 100% = 82.5k 🙂


  • Registered Users Posts: 393 ✭✭strandsman


    sound out. Cheers


  • Registered Users Posts: 5,141 ✭✭✭Yakuza


    You forgot to add 10% for every time the builder takes in a deep breath during the estimate divided by the probability of it being done before Christmas.


Advertisement