Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Malahide Viaduct report

  • 11-03-2010 10:33am
    #1
    Registered Users, Registered Users 2 Posts: 24,522 ✭✭✭✭


    Link
    IARNROD Eireann was warned about serious erosion on one of the country's busiest commuter lines three years before it collapsed into the sea, the Irish Independent has learned.

    A survey of the seabed in 2006 found evidence of serious erosion around the pillars supporting the Malahide viaduct.

    But Irish Rail failed to heed the warning because its engineers did not understand how the viaduct structure worked, the rail company's report into the incident reveals.

    The revelation raises serious questions about the safety of our railway network.

    Iarnrod Eireann was forced to launch an investigation into the safety of 105 bridges after the near-catastrophic collapse of the Malahide viaduct last August.

    The specialists examined the foundations and structure of each bridge, and all were deemed safe.

    However, the report into the collapse of the Malahide viaduct has highlighted serious new concerns about the company's safety culture. It is unclear why basic engineering details about one of the most heavily used lines in the country were lost.

    The report found that the seabed was being washed away from at least 2006, undermining the foundations of a pillar that supported the track.

    Engineers failed to realise that the viaduct's foundations had to be maintained because the knowledge had been lost as staff retired or moved to other positions in the company.

    The report said: "The collapse of the structure was due to the undermining of one pier's foundation caused by 'scour' erosion."

    It added that there was evidence some channels under the piers supporting the viaduct had been significantly deepened. "This is indicated in the 2006 scour inspection report."

    The findings contradict evidence given by company officials to the Dail transport committee last September. Chief executive Richard Fearn then told TDs and senators: "That survey (2006) showed no evidence of scour (erosion) and gave a clean bill of health for the following six years."

    But the 2006 survey said, like all bridges in water, the structure was prone to erosion. And it found that the seabed was being eroded near the support pillars -- a finding that should have set alarm bells ringing.

    But inspectors wrongly assumed the pillars that held up the track were sunk into the bedrock rather than resting on a man-made causeway, which was being gradually eroded.

    The Irish Rail report found:

    * There was evidence of the channels between Piers 4, 5 and 6 being "significantly deeper" than the channels between the other piers.
    * It was "likely" in 2006 that the bottom of the channels were "at or below" the foundation level of the adjacent piers, albeit some distance away.
    * Maintaining the causeway was of "paramount importance" to ensure the integrity of the viaduct, but it was "no longer fully appreciated".
    * The collapse was caused by the "undermining of one pier's foundation caused by scour erosion".

    Structure

    The report concludes that the emphasis was on maintaining the viaduct structure, and not the causeway.

    It added: "The importance of maintaining the weir profile was no longer fully appreciated."

    This lack of appreciation could have resulted in massive loss of life.

    On August 21 last year, erosion caused a supporting pillar -- Pier 4 -- to begin to collapse into the sea as a packed commuter train passed over it and tragedy was only narrowly averted.

    Iarnrod Eireann last night admitted safety staff had not known the foundations of the viaduct needed to be maintained. A spokesman said: "Our focus now is on learning from the key lessons of this most serious accident."

    So the engineers don't understand how the viaduct worked yet have signed off all the other bridges as safe, hardly confidence inspiring is it? It all seems a bit shambolic, I hope these "engineers" all got the boot for massive incompetence, though this is CIE so I doubt it. How do they look at a viaduct like that and think you only need to worry about the bit you can see?


Comments

  • Closed Accounts Posts: 13,549 ✭✭✭✭Judgement Day


    From the company that brought you Buttevant, Cherryville, Knockcroghery, Cahir and now Malahide - need anything more be said! This report is an appalling indictment of CIE/IE and the whole concern needs a root and branch overhaul with ALL senior management/board members pensioned off and replaced by competent outsiders.


  • Closed Accounts Posts: 7,686 ✭✭✭JHMEG


    the whole concern needs a root and branch overhaul with ALL senior management/board members pensioned off and replaced by competent outsiders.
    I'm looking out the window now for the flying pigs!


  • Registered Users, Registered Users 2 Posts: 9,814 ✭✭✭antoinolachtnai


    Seriously though, has no one in CIE heard of 'consulting engineers'? These guys are like ladders and concrete mixers, you can hire 'em by the day, even by the hour if needs be. You can even get a special one that only does viaducts over estuaries. Fonts of wisdom when it comes to things like foundations and old bridges.

    Bedrock indeed.


  • Closed Accounts Posts: 13,549 ✭✭✭✭Judgement Day


    Years ago when I was interested in such things I often wondered did CIE have proper viaduct inspection vehicles like this one in the UK shown below. Now, I have seen a lot of CIE pw/inspection vehicles down the years but never this type of apparatus. Any of the trainspotting fraternity know? Certainly I would be a lot happier knowing that CIE at least owned such equipment given the large number of old viaducts on the rail network. Incidentally, I have definite knowledge of some highly dubious rail bridge replacement work in the south of the country which I will be placing in the public domain as soon as I can satisfy myself with the veracity of my information.

    page12-4.jpg


  • Registered Users, Registered Users 2 Posts: 22,798 ✭✭✭✭The Hill Billy


    And this is what IE have to say:
    (Link)
    Malahide Viaduct accident investigation by Corporate Communications

    Iarnród Éireann’s investigation into the Malahide Viaduct accident has been completed, the company has stated.

    A major accident was narrowly avoided on 21st August 2009, following the collapse of pier 4 of the viaduct. The line was closed for a period of almost 3 months, reopening on 16th November 2009.

    The company submitted the complete report to the Rail Accident Investigation Unit, and the Railway Safety Commission on 19th February 2010, and is today publishing the report’s summary, conclusions, actions taken to date and recommendations (attached).



    Company rejects claim of 2006 warning

    In addition, Iarnród Éireann wish to correct the assertion in today’s Irish Independent that the company “was warned about serious erosion…three years before” this accident. This is untrue. The 2006 Bridge Scour inspection of the Malahide Viaduct, carried out for Iarnród Éireann by independent specialist diver engineers, did not state that there was any reason for concern about scour at that time. It stated that as the bridge was susceptible to scour, that underwater examinations should continue at intervals not to exceed 6 years. It was Iarnród Éireann’s investigation into the accident which, using external hydrological expertise, assembled available data on the viaduct and surrounding area, allowing modelling of the viaduct and the likely effects of water over time. It was this post-accident investigation, and not the 2006 report, which retrospectively concluded that scouring may have commenced at the time of the 2006 investigation, albeit some distance away from the piers.



    Iarnród Éireann investigation into the Malahide Viaduct collapse

    Iarnród Éireann’s investigation was independently chaired by John Buxton, Chartered Civil Engineer, and was also advised by a panel of experts led by Dr Eamon McKeogh of University College Cork in relation to the complex hydraulic and environmental issues involves. The Iarnród Éireann report will also be considered by the Rail Accident Investigation Unit in the preparation of their independent investigation into the accident.

    The report found:

    - Works undertaken in 1967 on the superstructure of the viaduct also included significant grouting work, to a depth of 2 metres, to the causeway/weir. These works, it was believed, would generally reduce the need for ongoing maintenance, particularly the unloading of “rip-rap” stone (large stone blocks) which had been regularly carried out to maintain the causeway/weir profile by replacing stones washed away by the tides. Since this time, the placing of rip-rap was more limited and appeared to be carried out only to protect the piers.

    - Over time, erosion of a section of the causeway/weir between Piers 4 and 5 caused changes to the water flow under the structure, resulting in the majority of the water flowing in a deepened channel between these two piers, further increasing erosion. In a relatively short period of time, the weir “crest” receded from the seaward side of these piers to beneath the span between them and, subsequently, onto the other (estuary) side of the viaduct. In the months prior to the collapse, the channel deepened further and the flow became ever stronger with standing waves and, latterly, a “piping” mechanism causing further “scour” action. Eventually Pier 4 became undermined and collapsed.

    - A key finding of the investigation is that since grouting works were undertaken on the causeway/weir in 1967, the engineering emphasis has been focused on the maintenance of the viaduct structure itself. However, the condition of the grouting in the causeway/weir required maintenance. By this time, although protection of the pier foundations was still being undertaken, the importance of maintaining the weir profile was no longer fully appreciated. Prior to the collapse, therefore, it was no longer appreciated that the structure as a whole comprised two separate components: a causeway/weir and a viaduct. The structure is unusual in that the piers did not extend down to the “bedrock”, but are instead founded within the manmade causeway/weir formed of large rip-rap resting on the bed of the estuary, making the piers prone to erosion or “scour” damage.

    - Climatic, oceanographic and hydrological changes over recent decades have increased the hydraulic “head” and hence the erosive effect of the water flowing into and, more especially, out of the Broadmeadow Estuary over the causeway/weir.

    - During the week before the collapse, a group leader of Malahide Sea Scouts observed that a rock at the base of pier 4 had been washed away and contacted Iarnród Éireann on 17th August to report this. The information reported by this member of the public was dealt with in a professional manner by Iarnród Éireann staff. However a misunderstanding appears to have developed so that the engineer delegated to inspect the viaduct on 18th August was looking primarily for cracks or missing stones in the pier structure rather than in its foundations. He found the “dressed” stonework of the viaduct to be in need of pointing and there were some cracked stones on a number of piers. Whilst none of these faults were of a serious structural nature, their presence appeared to him to explain the reason for the report from the canoeist. Therefore this visual inspection did not lead engineers to question the stability or the structural integrity of the viaduct.



    A series of actions have already taken place or are underway arising from the accident.

    - The replacement Pier 4 is founded on piles and all the remaining existing piers have been retro-fitted with piled foundations. A bridge monitoring system has been installed on the Malahide Viaduct

    - The list of structures susceptible to scour has been reviewed and is now more comprehensive. Pier and abutment depths are being established for all bridges on the scour list wherever practicable. Where this is not possible, other mitigating measures will be implemented.

    - There is one other structure on the IÉ network that has similar foundations to Malahide, Rogerstown Viaduct. This is on the same route as the Malahide Viaduct. Pier and abutment depths have been established for this structure and found to be deeper than for Malahide and are secure.

    - The Acting Chief Civil Engineer has initiated a full review of the systems in place for monitoring structures subject to scour and has commissioned consultants to look at international best practice for this with a view to implementing system improvements.

    - The driver of the 18.07hrs Balbriggan to Pearse train has been commended for his quick thinking in placing his power controller into the ‘coast’ setting which reduced the forces acting on the collapsing viaduct as the train passed over it. His actions to protect the line after the incident were also exemplary as were those of the CTC Signalman who has also been commended.

    - The need to maintain the causeway/weir of the Malahide Viaduct to an acceptable profile is now clearly understood. The weir has been reconstructed to its original profile. Furthermore an improved weir profile is being developed, in line with the outcome of the studies undertaken by UCC.

    - Information on the viaduct that is currently known, or can reasonably be collected including archived materials, is being assembled and will be made available through IAMS (Infrastructure Asset Management System). Thus in future, IAMS will form the basis of the required inspection and maintenance process and staff will be better equipped to undertake these duties. Similar information will also be added, on a risk prioritised basis, for all other structures on Iarnród Éireann.

    - Most of the bridges on the “scour inspection list” have been inspected (by engineer divers) and this work will be completed by April 2010. Following on from these inspections each structure will be given a risk rating and the inspection frequency will be based on this rating. Trigger levels will be defined for special additional inspections of the structure as required (e.g. exceptional tides) and/or its closure when conditions deteriorate. A re-opening process for each structure is also to be documented.



    The investigation also makes a series of recommendations.

    - Recommendation 1: Complete all of the above actions.

    - Recommendation 2: The structures standard should be revised to include more information on ‘scour’, the erosive effects of different water conditions (e.g. standing waves), particularly in the context of the design of remedial measures.

    - Recommendation 3: The introduction of the revised structures standard should be supported by the running of a series of Structures Inspection Training Courses. The training should incorporate ‘follow up’ mentoring in the field by experienced, competent staff.

    - Recommendation 4: Roles and reporting lines for structures and track patrolling inspections should be reviewed and a ‘handover’ process should be put in place to ensure knowledge is not lost on staff movements within the organisation or when staff leave the service.

    - Recommendation 5: Flood and tidal warning arrangements, using information from Met Éireann and the Coast Guard, should be formalised throughout Iarnród Éireann.

    - Recommendation 6: Consideration should be given to extending the installation of monitoring/warning equipment to structures susceptible to scour so that changing conditions at sites during adverse conditions can be monitored.

    - Recommendation 7: The bridge card system of monitoring the condition of structures should be expanded to incorporate all relevant information that needs to be recorded during an inspection. The records should cover each span or relevant element of the structure and these should be incorporated into an enhanced IAMS based system supported by photographs.

    - Recommendation 8: The process for dealing with reports from the public should be documented and unified across the organisation.

    - Recommendation 9: The effects of climate change, land and leisure developments in the Broadmeadow catchment area should be kept under review by IÉ so that the organisation is well placed to take informed action to mitigate any potential future adverse effects on the railway. In particular, it is recommended that dialogue is initiated with the relevant state agencies accordingly.

    Iarnród Éireann assures customers that these recommendations will be fully implemented, as will any and all recommendations arising from the investigation of the Rail Accident Investigation Unit.

    The investigation also states that the public spiritedness of third parties who contacted Iarnród Éireann prior to and subsequent to the incident should be commended.

    Malahide Viaduct Summary and Conclusions


  • Advertisement
  • Closed Accounts Posts: 7,686 ✭✭✭JHMEG


    Why are IE trying to defend anything. The viaduct collapsed cos they fscked up. The proof is in the pudding.


  • Closed Accounts Posts: 13,549 ✭✭✭✭Judgement Day


    During the week before the collapse, a group leader of Malahide Sea Scouts observed that a rock at the base of pier 4 had been washed away and contacted Iarnród Éireann on 17th August to report this. The information reported by this member of the public was dealt with in a professional manner by Iarnród Éireann staff. However a misunderstanding appears to have developed so that the engineer delegated to inspect the viaduct on 18th August was looking primarily for cracks or missing stones in the pier structure rather than in its foundations. He found the “dressed” stonework of the viaduct to be in need of pointing and there were some cracked stones on a number of piers. Whilst none of these faults were of a serious structural nature, their presence appeared to him to explain the reason for the report from the canoeist. Therefore this visual inspection did not lead engineers to question the stability or the structural integrity of the viaduct.

    This would indeed inspire confidence! Just like Buttevant - some people knew the facing points were not connected to the signal cabin, some people knew where they keys were kept, some knew there was an express due etc. etc...... :confused:


  • Registered Users, Registered Users 2 Posts: 24,522 ✭✭✭✭Cookie_Monster


    During the week before the collapse, a group leader of Malahide Sea Scouts observed that a rock at the base of pier 4 had been washed away and contacted Iarnród Éireann on 17th August to report this. The information reported by this member of the public was dealt with in a professional manner by Iarnród Éireann staff. However a misunderstanding appears to have developed so that the engineer delegated to inspect the viaduct on 18th August was looking primarily for cracks or missing stones in the pier structure rather than in its foundations. He found the “dressed” stonework of the viaduct to be in need of pointing and there were some cracked stones on a number of piers. Whilst none of these faults were of a serious structural nature, their presence appeared to him to explain the reason for the report from the canoeist. Therefore this visual inspection did not lead engineers to question the stability or the structural integrity of the viaduct.
    [/B]

    Again same question though, We'll just go and check the bits that are easy to see :rolleyes: Why get a qualified engineer to go out and half check the bridge. Surely he would have noticed what the sea scouts did even if wasn't particulrly looking for that, lots of missing rocks...


    And loathe as I am to say it, I'd believe the Independent over CIE


  • Registered Users, Registered Users 2 Posts: 4,316 ✭✭✭KC61


    I think that the question is how did that misunderstanding happen and what steps are being taken that something like this does not happen again?

    The engineer may well have done exactly what he was asked to do, and have been unaware of the real problem, but what went wrong between the information arriving and he carrying out his inspection?

    The fact is that someone mucked up on this big time, and I can't see how the Chief Civil Engineer can remain in her position as it sounds as if the fundamental systems of communication broke down.


  • Closed Accounts Posts: 20,373 ✭✭✭✭foggy_lad


    During the week before the collapse, a group leader of Malahide Sea Scouts observed that a rock at the base of pier 4 had been washed away and contacted Iarnród Éireann on 17th August to report this. The information reported by this member of the public was dealt with in a professional manner by Iarnród Éireann staff. However a misunderstanding appears to have developed so that the engineer delegated to inspect the viaduct on 18th August was looking primarily for cracks or missing stones in the pier structure rather than in its foundations. He found the “dressed” stonework of the viaduct to be in need of pointing and there were some cracked stones on a number of piers. Whilst none of these faults were of a serious structural nature, their presence appeared to him to explain the reason for the report from the canoeist. Therefore this visual inspection did not lead engineers to question the stability or the structural integrity of the viaduct.

    i would have thought that anyone with reasonable intelligence would know that cracks and missing pointing work on an old bridge subject to massive forces from flowing water would show a bit more concern than just calling out the plasterers to do a bit of pointing on the bricks!

    also none of the faults on their own would indicate anything serious but together would indicate at least the possibility of serious damage but to admit that might have cost too much!


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 11,994 ✭✭✭✭expectationlost


    heres the a report on the viaduct, this seems to be an independent one commission by IR,

    http://www.rte.ie/news/2010/0311/malahide.pdf

    when the rail accident investigation one coming out?


    whoops i see another thread now del


  • Registered Users, Registered Users 2 Posts: 11,994 ✭✭✭✭expectationlost


    this is what they've been saying all along we dealt with the pier we dealt with the pier

    heres the report

    http://www.rte.ie/news/2010/0311/malahide.pdf

    perhaps if the engineer had spoken to the canoeist but, but the canoeist is was probalby just some annoying pest to IRs view


  • Closed Accounts Posts: 13,549 ✭✭✭✭Judgement Day


    Barry Kenny explaining on Today FM now. :pac::pac::pac:


  • Closed Accounts Posts: 7,686 ✭✭✭JHMEG


    Barry Kenny is a tool. Both times I heard him on the radio today he resorted to trying to shout down anyone who criticised IE.


  • Closed Accounts Posts: 13,549 ✭✭✭✭Judgement Day


    JHMEG wrote: »
    Barry Kenny is a tool. Both times I heard him on the radio today he resorted to trying to shout down anyone who criticised IE.

    Barry Kenny is an axxhole but he is only a mouthpiece for his masters. I had him on SE Radio a few years back trying to defend the awful railcars on the Rosslare line - apart from the fact that he didn't even know that the trains were carrying Fastrack parcels (stacked in the exit doorways), agreed with me that the trains were dirty, cold and uncomfortable he then proceeded to ask me what was wrong with them. What a complete tool and what I would give to get into a radio studio with him!


  • Registered Users, Registered Users 2 Posts: 8,779 ✭✭✭Carawaystick


    Irish Rail wrote:
    Recommendation 5: Flood and tidal warning arrangements, using information from Met Éireann and the Coast Guard, should be formalised throughout Iarnród Éireann.
    Isn't there a very obvious missing organisation which is responsible for flooding missing? They operate a number of Dams about the country.
    Is it just coastal bridges IÉ are concerned about or are they ignoring bridges over the rivers of the country?


  • Closed Accounts Posts: 23,316 ✭✭✭✭amacachi


    Engineers failed to realise that the viaduct's foundations had to be maintained because the knowledge had been lost as staff retired or moved to other positions in the company.
    If that's accurate.. Christ.


  • Registered Users, Registered Users 2 Posts: 24,522 ✭✭✭✭Cookie_Monster


    amacachi wrote: »
    Engineers failed to realise that the viaduct's foundations had to be maintained because the knowledge had been lost as staff retired or moved to other positions in the company.
    If that's accurate.. Christ.

    once again I am astounded, how can that possibly be an excuse?


    They'll forget how to drive loco's next and only be able to operate railcars. :rolleyes:


  • Closed Accounts Posts: 20,009 ✭✭✭✭Run_to_da_hills


    Engineers "forgot" bridge foundation.

    Metroherald gave them a headline slating this morning, will IR now ban this paper from being destributed from their property. :D


  • Closed Accounts Posts: 2,372 ✭✭✭steamengine


    amacachi wrote: »
    If that's accurate.. Christ.

    And put 'Sweet mother of divine' in front of that as well !!!

    Are there no original plans, blueprints archived somewhere ?

    Filing cabinets and plans don't retire !!! :confused:


  • Advertisement
  • Closed Accounts Posts: 369 ✭✭Michael B


    My God that's ridiculous. Bunch of idiots!


  • Closed Accounts Posts: 20,009 ✭✭✭✭Run_to_da_hills


    Michael B wrote: »
    My God that's ridiculous. Bunch of idiots!

    They can just thank the above there was no fatalities, if there was they would have been hung drawn and quartered with class action lawsuits and possible manslaughter charges.


  • Closed Accounts Posts: 309 ✭✭FlameoftheWest


    and yet CIE/Irish Rail managers/engineers pose all heroically with smug grins on Malahide Viaduct while having their photos taking during the rebuilding process.

    This mentality is all over the that company; the usual strike/industiral action at CIE Unions when they are given a new bus or train always ends with these muppets getting into the cabs when their resume work with his "aren't we just wonderful for stopping the strike!" and they really mean it. Remember the carry on surrounding the Mk4 introduction and the "we are now flying Jumbo Jets and should be paid big money" when they finally drive the new trains they pull out of Connolly and Kent blarring the horns while waving their fists out the loco cab windows expacting the Irish citizeny to cheer them on.

    You could not make this up if you tried.


  • Closed Accounts Posts: 309 ✭✭FlameoftheWest


    They can just thank the above there was no fatalities, if there was they would have been hung drawn and quartered with class action lawsuits and possible manslaughter charges.

    Would never happen in Ireland. Just wouldn't. CIE are immune from accountabiltiy and always have been.


  • Closed Accounts Posts: 7,686 ✭✭✭JHMEG


    They can just thank the above there was no fatalities,
    Absolutely.
    if there was they would have been hung drawn and quartered with class action lawsuits and possible manslaughter charges.
    They couldn't find who spent the €150 million on PPARS. Not likely they'd be able to find anyone responsible in CIE either.


  • Registered Users, Registered Users 2 Posts: 24,522 ✭✭✭✭Cookie_Monster


    JHMEG wrote: »
    Absolutely.


    They couldn't find who spent the €150 million on PPARS. Not likely they'd be able to find anyone responsible in CIE either.

    they'd probably blame the poor train driver...


  • Registered Users Posts: 912 ✭✭✭Hungerford


    Filing cabinets and plans don't retire !!! :confused:

    Not coming from an engineering background myself, I would have assumed they would have realised themselves that the foundations were a crucial part of a viaduct. Obviously not...


  • Registered Users, Registered Users 2 Posts: 11,994 ✭✭✭✭expectationlost


    and barry kenny explaination is oh no it wasn't spotted in 2006 we plainly forgot how the bridge was built as if thats better reason??? and the two issues are connected, if they had accepted in 2006 that the bridge was vunerable if scouring continued then would have prepared for it, its not hindsight


  • Closed Accounts Posts: 20,373 ✭✭✭✭foggy_lad


    Hungerford wrote: »
    Not coming from an engineering background myself, I would have assumed they would have realised themselves that the foundations were a crucial part of a viaduct. Obviously not...
    only if the cost of maintenance was right.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 5,337 ✭✭✭dowlingm


    If that was in Japan the Minister, the local Dick Fearn and the local head of engineering would likely be making a televised press conference apology!

    In Canada CN or CP would just say "oops!"


  • Closed Accounts Posts: 20,009 ✭✭✭✭Run_to_da_hills


    dowlingm wrote: »
    If that was in Japan the Minister, the local Dick Fearn and the local head of engineering would likely be making a televised press conference apology!

    In Canada CN or CP would just say "oops!"

    In Japan if there was casualties those responsible would have topped themselves.


  • Closed Accounts Posts: 49 Soil Mechanic


    *cough cough*

    A thought has just occured to me........

    Surely this is not another case of highly qualfiied Civils & Structures Engineering Professionals near completely ignoring the underlying Geotechncial aspect........
    (with a capital "G")

    Such things never happen in Ireland.....

    *cough*
    :rolleyes:



    Now if you'll excuse me, I have an urgent & ongoing appointment with a grindstone to whittle my axe.............;)

    SM


  • Registered Users Posts: 38 kev1


    Hi,

    Could someone please inform me what the location of Pier 4 is (the pier that collapsed).??

    I have read that the first & last piers are centred at 12.25m and the middle nine piers are centred at 15.85m.
    So is Pier 4 counted from the Dublin side or from the Belfast side?

    Therefore Pier 4, would be approx 59.8m from whichever side, am i right?

    If someone could enlighten me about this it would be great.

    Thanks in advance.


  • Registered Users, Registered Users 2 Posts: 78,493 ✭✭✭✭Victor


    I think it was more towards the Dublin end.


  • Closed Accounts Posts: 13,549 ✭✭✭✭Judgement Day


    In the context of the apparent disarray in CIE/IEs infrastructure division that the Malahide incident highlighted, some people may find this newscutting from 2003 'interesting'. :eek:

    001iub.jpg


  • Advertisement
  • Registered Users Posts: 581 ✭✭✭Transportuser09


    Its very baffling that those in charge where not aware of the structure of the viaduct. It must be made sure that it never happens again. Hopefully this near miss will be an important lesson and a step towards making sure that it doesn't.


Advertisement