Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Mould during construction

  • 11-12-2019 7:11pm
    #1
    Registered Users, Registered Users 2 Posts: 585 ✭✭✭


    Hi,
    In the middle of an extension that seems to be taking forever to build. Lots of issues with the builder I wont go into in this particular post.
    So, house is about to be sealed soon, finally, should be before xmas.

    The building has been unsealed for a good 2 months now due to delays with weather and roofing etc etc but primarily due to slow contractor.

    Today I noticed that plywood above the joists on a new flat roof has lots of mould on it. The roof is a trocal roof but not fully sealed yet due to delays with capping and plastering. The mould is quite dense in a few patches and evident all over to a lesser extent. Builder is saying it can be cleaned off and he will dry the place out with a dehumidifier over the xmas break, and clean and treat etc.

    Is this a common problem during construction phase? Is the above likely to work to rid the place of the mould, it looks very disgusting to be honest. Is there anything else that can be done at this stage?
    I would truly love to fire the builder, but we are stuck at this stage if we want to have any chance to get this done.

    Thanks...


Comments

  • Moderators, Home & Garden Moderators Posts: 10,141 Mod ✭✭✭✭BryanF


    Not normal. What does the contract state? Is he paid in advance? Are you living in the house?


  • Registered Users, Registered Users 2 Posts: 585 ✭✭✭ravendude


    BryanF wrote: »
    Not normal. What does the contract state? Is he paid in advance? Are you living in the house?

    He is paid in arrears for work done. We are not living in the house, we are renting.