Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Altering internal layout after PP received

  • 11-12-2019 6:26pm
    #1
    Registered Users, Registered Users 2 Posts: 412 ✭✭


    We are buying a ‘Shell & Core’ apartment. Layout of rooms on drawing which was submitted for planning not the best. Can we change internal layout? No moving windows or anything external, just alternative placement of internal walls etc?


Comments

  • Moderators, Society & Culture Moderators Posts: 39,782 Mod ✭✭✭✭Gumbo


    xraylady wrote: »
    We are buying a ‘Shell & Core’ apartment. Layout of rooms on drawing which was submitted for planning not the best. Can we change internal layout? No moving windows or anything external, just alternative placement of internal walls etc?

    Apartment?
    Very unusual situation to be in?

    How did the apartment development come to be sold as shell and core?
    Who will provide the compliance with Planning, Fire Cert and Disabled Access Cert?


  • Registered Users, Registered Users 2 Posts: 1,194 ✭✭✭Stanford


    kceire wrote: »
    Apartment?
    Very unusual situation to be in?

    How did the apartment development come to be sold as shell and core?
    Who will provide the compliance with Planning, Fire Cert and Disabled Access Cert?

    I agree, you sure you have planning and not just Outline Planning?


  • Registered Users, Registered Users 2 Posts: 412 ✭✭xraylady


    Yes. Change of use from commercial to residential . Fire & disability access permissions sorted after change of use. Planned internal layout needs to be altered.


  • Registered Users, Registered Users 2 Posts: 28,773 ✭✭✭✭looksee


    Generally, Planning are not much concerned about internal changes, Building Regs might. You need to have your engineer/architect on board to sort this.


  • Registered Users, Registered Users 2 Posts: 1,194 ✭✭✭Stanford


    If you used an Architect or Engineer during the planning process I would advise you to consult them or whoever is going to certify planning/fire cert compliance, normally small internal alterations are fine but you may have difficulty if you change compliance with fire & disability regs.


  • Advertisement
  • Subscribers Posts: 41,830 ✭✭✭✭sydthebeat


    xraylady wrote: »
    Planned internal layout needs to be altered.

    this could affect the Fire Safety certificate... so you just cannot do it off the cuff.

    it may require an amended Fire safety Certificate application.


  • Registered Users, Registered Users 2 Posts: 1,194 ✭✭✭Stanford


    sydthebeat wrote: »
    this could affect the Fire Safety certificate... so you just cannot do it off the cuff.

    it may require an amended Fire safety Certificate application.

    My point exactly..!!


  • Moderators, Society & Culture Moderators Posts: 39,782 Mod ✭✭✭✭Gumbo


    xraylady wrote: »
    Yes. Change of use from commercial to residential . Fire & disability access permissions sorted after change of use. Planned internal layout needs to be altered.

    Ok so you my need to talk to a professional here as a commencement notice may be required. Did you obtain planning was it an SI30 development?

    You will need to appoint an Assigned Certifier and any changes to the granted FSC or DAC, if material in nature will required a revised certificate application.