Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Maynooth Education Campus - builders liquidated.

  • 05-06-2018 7:22pm
    #1
    Registered Users, Registered Users 2 Posts: 8,080 ✭✭✭


    Seen it announced today that Sammon, the main builders of the Maynooth Education Campus have collapsed. All linked to Carrilion collapsing in the UK earlier in the year.

    Minister for Education is to put it out for retender, but between subcontractors now being left hundreds of thousands out of pocket, a half completed project to be inspected and new developers to be found - this is all bound to cause huge delays to its completion.

    So now Maynooth will be missing 2 planned secondary schools - meant to be amongst largest in Ireland and the old shared campus will have to soldier on.

    https://www.education.ie/en/Press-Events/Press-Releases/2018-press-releases/PR18-06-05B.html

    On a much more nimby note, I'm just annoyed the last thing they did do is knock down one of the walls along entrance to Moyglare Hall and leave temporary fencing out in the middle of the road. Now we'll be stuck with this ugly mess for a while, while everyone argues about bills, security and responsibility


Comments

  • Closed Accounts Posts: 3,378 ✭✭✭CeilingFly


    Patser wrote: »

    Minister for Education is to put it out for retender, but between subcontractors now being left hundreds of thousands out of pocket, a half completed project to be inspected and new developers to be found - this is all bound to cause huge delays to its completion.

    Its the joint partner of carrilion that are putting it out to tender. Very very very messy situation and very difficult for gov to do anything rash as there would be huge penalties.

    Hopefully there will be some system whereby contractors will get a good portion of what is owed.


  • Registered Users, Registered Users 2 Posts: 69,538 ✭✭✭✭L1011


    This isn't a PPP - it was a direct build contract to Sammon not connected to the Carillion PPP bundle. Carillion is why Sammon have gone under but this will be retendered conventionally


  • Closed Accounts Posts: 12,807 ✭✭✭✭Orion


    So another year down the Swanee.
    Timeline from KWETB regarding retender for Maynooth Education Campus

    *E tenders on June 23rd for qualifying contactors

    *Tender issued 23rd July

    *Revised tender by Sept 4th

    *Tender outcome by Oct 23rd

    *Tender Published by November 8th

    *Contractor on site end of March 2019

    *Completion of works Mid June 2020


  • Registered Users, Registered Users 2 Posts: 69,538 ✭✭✭✭L1011


    Not a huge amount of tightening up that can be done to the tender timeframe both with normal EU tendering rules, and KWETB under investigation for potential procurement fraud.

    However, the award to commencement is ridiculously long particularly with the heavy groundworks all complete - they can work over winter.


Advertisement