    Hi, we are just finished skimming and next job is floor insulation, putting down 2 layers of 75mm to make up the 150, I have got 25mm insulation to go around perimeter, it will go from subfloor to top of finish floor, the problem I am seeing is the plaster plus skim has added roughly 10/15mm to wall but the lite block on subfloor is untouched which would leave a gap behind perimeter insulation, looking for possible advice on what to do. Thank you