Paying builder last payment

Options
  • 04-10-2023 4:31pm
    #1
    Registered Users Posts: 8,960 ✭✭✭


    HI,

    Just wondering what is typical in terms of the last payment to builder?

    2 week after completion? 2 months after completion? And what percentage should last payment be?



Comments

  • Registered Users Posts: 6,562 ✭✭✭Allinall


    I would have thought that should have been agreed before the job started.

    Had an extension done a few years ago. Payments were staggered. Roughly 20% at specified stages.

    Final payment was at sign off by engineer, with 5% of total contract held back for 3 months.