Change of Use Planning Permission

  • 23-10-2020 8:37pm
    #1
    Registered Users, Registered Users 2 Posts: 7


    Evening everyone,

    We are looking at renting a 2500sqf office unit and converting it into a gym, we would need to apply for the unit's usage to be changed.

    Does anyone have experience with this or know how long it takes to complete.

    Thank You


Comments

  • Moderators, Society & Culture Moderators Posts: 40,800 Mod ✭✭✭✭Gumbo


    bobjimmy81 wrote: »
    Evening everyone,

    We are looking at renting a 2500sqf office unit and converting it into a gym, we would need to apply for the unit's usage to be changed.

    Does anyone have experience with this or know how long it takes to complete.

    Thank You

    Planning application process is 8 weeks from the date of lodgement.
    Realistically it’s a 4 month process allowing for time before hand to get plans drawn up, application organised and lodged. Then appeal period at the end and commencement notice.

    But, you will also need a fire cert and disabled access cert. these are separate statutory applications.