Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

4 Bay Slatted Shed Grant Spec Cost

  • 04-10-2020 1:54pm
    #1
    Registered Users, Registered Users 2 Posts: 614 ✭✭✭


    What is the current cost of building a 4 bay slatted shed with 14'6 slat and a creep with 60% grant? Is 15k a bay accurate?


Comments

  • Registered Users, Registered Users 2 Posts: 46 diesel druggie


    Hi there I recently constructed a shed with no grant as I said never again would I do a grant shed. Anyway here's my info for you

    It's four bay with a 16 ft creep, and 14'6" slats

    Labour at tank pour floor, tie steel, shutter walls.
    Slats 14' 6"
    Steel for tank re bar
    Steel for shed
    Sheeting 0.55 grant spec
    Barriers all locking
    Back and gable walls
    Concrete for tank and gable walls
    Concrete for apron and creep
    Additional Labour

    I'll fill in prices tomorrow when I have invoices but I know it's going to be definitely less than 40k


  • Registered Users, Registered Users 2 Posts: 614 ✭✭✭farmer2018


    Hi there I recently constructed a shed with no grant as I said never again would I do a grant shed. Anyway here's my info for you

    It's four bay with a 16 ft creep, and 14'6" slats

    Labour at tank pour floor, tie steel, shutter walls.
    Slats 14' 6"
    Steel for tank re bar
    Steel for shed
    Sheeting 0.55 grant spec
    Barriers all locking
    Back and gable walls
    Concrete for tank and gable walls
    Concrete for apron and creep
    Additional Labour

    I'll fill in prices tomorrow when I have invoices but I know it's going to be definitely less than 40k

    Why wouldn't you do a grant shed again? Surely the 60% is the only way to go.


  • Registered Users, Registered Users 2 Posts: 19,581 ✭✭✭✭Bass Reeves


    I would totally disagree about going for the grant especially if 60%is available. However you must be able to build shed to at or very near department costings. I build during the big environment scheme in 2008/2009 and came in on budget.

    A 4 bay shed with creep and lie back area should be able to be build to department costings. They cost work out as follows

    Shed 53k approx
    Vat from it 6.3k
    40% grant 18.7k
    60% grant 28k

    Net cost 60% grant 19k
    Net cost 40% grant 28k

    Biggest fault is lads not including all grant items in application. However that should not be an issue with application's done by agri consultant's.

    Slava Ukrainii



  • Registered Users, Registered Users 2 Posts: 46 diesel druggie


    farmer2018 wrote: »
    Why wouldn't you do a grant shed again? Surely the 60% is the only way to go.

    1 I can do it for less than a grant aided shed at the same spec

    2 No planning permission required

    3 Grant is taxable as it's income when you get it

    4 No deadlines I started this one in October 2018 I'm nearly done now

    5 As I done it in bits now and again I didnt draw a loan for this job done it when I had surplus funds

    6 Either the bank would want the grant mandated to them as far a I remember or the supplier is gone it any good that may have been in it.

    7 I wouldn't have got the 60%

    All above is only my view other lads may see it differently


  • Registered Users, Registered Users 2 Posts: 614 ✭✭✭farmer2018


    I would totally disagree about going for the grant especially if 60%is available. However you must be able to build shed to at or very near department costings. I build during the big environment scheme in 2008/2009 and came in on budget.

    A 4 bay shed with creep and lie back area should be able to be build to department costings. They cost work out as follows

    Shed 53k approx
    Vat from it 6.3k
    40% grant 18.7k
    60% grant 28k

    Net cost 60% grant 19k
    Net cost 40% grant 28k

    Biggest fault is lads not including all grant items in application. However that should not be an issue with application's done by agri consultant's.

    My advisor told me approx 70k for a 4 bay ex vat.

    It would be the contractor doing all the work.

    What would I be looking at paying my own money when the job is finished? Including vat back.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 32 Someyolk


    1 I can do it for less than a grant aided shed at the same spec

    2 No planning permission required

    3 Grant is taxable as it's income when you get it

    4 No deadlines I started this one in October 2018 I'm nearly done now

    5 As I done it in bits now and again I didnt draw a loan for this job done it when I had surplus funds

    6 Either the bank would want the grant mandated to them as far a I remember or the supplier is gone it any good that may have been in it.

    7 I wouldn't have got the 60%

    All above is only my view other lads may see it differently

    You don’t get taxed on the grant you receive.
    A neighbour recently built a four bay double shed. It looks to be Finished to an extremely high standard. Got 60% of a grant on it. It’s costing him 22k out of his pocket. It would have been less but he put mats on for pens which drive the price well up.
    A grant job always pays in my opinion.


  • Registered Users, Registered Users 2 Posts: 19,581 ✭✭✭✭Bass Reeves


    1 I can do it for less than a grant aided shed at the same spec

    2 No planning permission required

    3 Grant is taxable as it's income when you get it

    4 No deadlines I started this one in October 2018 I'm nearly done now

    5 As I done it in bits now and again I didnt draw a loan for this job done it when I had surplus funds

    6 Either the bank would want the grant mandated to them as far a I remember or the supplier is gone it any good that may have been in it.

    7 I wouldn't have got the 60%

    All above is only my view other lads may see it differently

    1 no often people who carry out non grant jobs do not cost in there own time and machinery jobs

    2. Not getting planning causes issues down the line you can never apply for a grant again untill you are planning compliant. If any of that area is subject to CPO you will not be compensated. Finally you could be ordered to take it down or if pollution is a problem in your area you may be required to proof it's not from your shed

    3.Grant can be deducted from capital allowances.

    4 ya deadlines have to be met

    5 doing bit by bit means you are not costing your own labour , time or machinery costs into the job. These can often substantially reduce the cost of a grant job when costed into the project.

    6 rubbish banks much prefer if you are making repayments on a scheduled loan rather than giving a split loan to cover grant and a remaining Lian to cover the rest. This is subject to you not having excess borrowings

    7 both grants should come in substantially below not grant job unless specs are reduced. The only difference I ever really saw on costs was sheeting. The CE stamp costs extra. However if similar spec is followed on rest of shed there is little savings unless you intend to do a cash job. You may save a bit on labour using lads that have not got tax clearance certs but these often tend to be cowboy's anyway

    Slava Ukrainii



  • Registered Users, Registered Users 2 Posts: 2,120 ✭✭✭Who2


    15k approx for shed.
    4.5k for slats
    1500 for steel
    1500 for digging and back filling
    5k for concrete for tank
    5k for labour for tank
    Another 10k for back walls , gates, barriers and drinkers and lights should cover the most of it.
    Still a long way off 70k


  • Registered Users, Registered Users 2 Posts: 614 ✭✭✭farmer2018


    Someyolk wrote: »
    You don’t get taxed on the grant you receive.
    A neighbour recently built a four bay double shed. It looks to be Finished to an extremely high standard. Got 60% of a grant on it. It’s costing him 22k out of his pocket. It would have been less but he put mats on for pens which drive the price well up.
    A grant job always pays in my opinion.

    What did the shed cost in total?


  • Registered Users, Registered Users 2 Posts: 32 Someyolk


    farmer2018 wrote: »
    What did the shed cost in total?

    Round 55 I think before he put the mats on.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 19,581 ✭✭✭✭Bass Reeves


    farmer2018 wrote: »
    My advisor told me approx 70k for a 4 bay ex vat.

    What would I be looking at paying my own money when the job is finished? Including vat back.

    You can end up.paying anything for a shed if you are soft enough. If that advisor recommends any builders I go looking elsewhere. Builders that do the complete job charge 15-25% extra for that service. Subcontracting is usually the cheapest bit you need your ducks in a row.

    Grant is set to fixed costs so if you pay 40-50-60-70-80k grant remain the same. If you pay 70k for this shed Vat will be about 8.4k. Grant at 60% would be about 28k no matter if you pay 40 or 80k for shed. At 70k net of grant and vat shed will cost you 34k

    Slava Ukrainii



  • Registered Users, Registered Users 2 Posts: 32 Someyolk


    farmer2018 wrote: »
    My advisor told me approx 70k for a 4 bay ex vat.

    It would be the contractor doing all the work.

    What would I be looking at paying my own money when the job is finished? Including vat back.

    He is well over estimating at that imo. The shed I am on about is two 4 bay tanks. These are rough figures but the tanks cost round 25k including slats, labour etc. The shed was 18k (galvanised). 3 k to get it erected but he had a teleporter Of his own and he helped the two lads put it up. 4K bought the barriers, dividing gates drinkers etc and the rest was concrete for passage way etc.
    Built a few sheds here over the years and some lads try and rob you. You need to shop about.


  • Registered Users, Registered Users 2 Posts: 614 ✭✭✭farmer2018


    I thought that sounded way too high. The plan is to get a separate contractor for concrete and erecting the shed, I will shop around for sure.


  • Registered Users, Registered Users 2 Posts: 657 ✭✭✭josephsoap


    farmer2018 wrote: »
    What is the current cost of building a 4 bay slatted shed with 14'6 slat and a creep with 60% grant? Is 15k a bay accurate?

    How many cows would you fit in a bay with 14’6 slat ? Would 7 be tight for feeding space ?


  • Registered Users, Registered Users 2 Posts: 19,581 ✭✭✭✭Bass Reeves


    josephsoap wrote: »
    How many cows would you fit in a bay with 14’6 slat ? Would 7 be tight for feeding space ?

    It not feeding space it's the ability to lie down. A 14'6 slat with 18''toe space front and back gives a total area of 26 sq meters. The recommendation is 2.8-3 meters. If you match your cows to the bunches they are in you get 10 in most pens at least.

    Then the other thing is to have dry silage as cows need less time to feed. If a cow is eating 23dm silage it will generally take her 50-70% more time to consume enough compared to 40dm+silage

    Slava Ukrainii



  • Posts: 24,714 ✭✭✭✭ [Deleted User]


    1 no often people who carry out non grant jobs do not cost in there own time and machinery jobs

    2. Not getting planning causes issues down the line you can never apply for a grant again untill you are planning compliant. If any of that area is subject to CPO you will not be compensated. Finally you could be ordered to take it down or if pollution is a problem in your area you may be required to proof it's not from your shed

    3.Grant can be deducted from capital allowances.

    4 ya deadlines have to be met

    5 doing bit by bit means you are not costing your own labour , time or machinery costs into the job. These can often substantially reduce the cost of a grant job when costed into the project.

    6 rubbish banks much prefer if you are making repayments on a scheduled loan rather than giving a split loan to cover grant and a remaining Lian to cover the rest. This is subject to you not having excess borrowings

    7 both grants should come in substantially below not grant job unless specs are reduced. The only difference I ever really saw on costs was sheeting. The CE stamp costs extra. However if similar spec is followed on rest of shed there is little savings unless you intend to do a cash job. You may save a bit on labour using lads that have not got tax clearance certs but these often tend to be cowboy's anyway

    I agree with most of your post and I think if you can get 60% grant it’s madness leaving it behind as it just has to work out cheaper.

    However I often see the bolded bit mentioned and I always disagree, to me it makes absolutely no sense to put a cost to your own time when doing work yourself to save money as you won’t be paying yourself either way so it would be a wrong comparison.

    Like we put a lot of time into doing stuff ourselves to save money but the time we spend doing it is time we have to spare so saying well if I paid myself 50 euro an hour then it might cost less to pay someone else 50 euro an hour to do it faster however you never actually pay yourself so you can’t compare the cost with actually paying someone else.

    Maybe my post is confusing but I think people will understand what I mean.


  • Registered Users, Registered Users 2 Posts: 19,581 ✭✭✭✭Bass Reeves


    I agree with most of your post and I think if you can get 60% grant it’s madness leaving it behind as it just has to work out cheaper.

    However I often see the bolded bit mentioned and I always disagree, to me it makes absolutely no sense to put a cost to your own time when doing work yourself to save money as you won’t be paying yourself either way so it would be a wrong comparison.

    Like we put a lot of time into doing stuff ourselves to save money but the time we spend doing it is time we have to spare so saying well if I paid myself 50 euro an hour then it might cost less to pay someone else 50 euro an hour to do it faster however you never actually pay yourself so you can’t compare the cost with actually paying someone else.

    Maybe my post is confusing but I think people will understand what I mean.

    I think you miss understood my point. If a lad found a non grant job put as much time and effort into a grant job it would work out away cheaper.

    Often lads that pay over the top do nothing themselves. A lad putting up barriers himself drawing the muck from the digger, installing water himself etc can bring a grant job in 10-15% below grant costs. However he can now include these costs in the grant application. I know a lad that build a shed for the 60% grant money in 2008/9. He was in slightly ahead of the posse and ready to start 6-8weeks ahead of everyone else. He got the shed erected but sheeted it himself, did all the concrete work, did all the internal fitting. Wired it himself and had the electrician only there to certify. At the end it cost the money he got from the grant. His own time and machinery made up the rest of the grant cost application.

    Slava Ukrainii



  • Registered Users, Registered Users 2 Posts: 2,377 ✭✭✭DBK1


    I think you miss understood my point. If a lad found a non grant job put as much time and effort into a grant job it would work out away cheaper.

    Often lads that pay over the top do nothing themselves. A lad putting up barriers himself drawing the muck from the digger, installing water himself etc can bring a grant job in 10-15% below grant costs. However he can now include these costs in the grant application. I know a lad that build a shed for the 60% grant money in 2008/9. He was in slightly ahead of the posse and ready to start 6-8weeks ahead of everyone else. He got the shed erected but sheeted it himself, did all the concrete work, did all the internal fitting. Wired it himself and had the electrician only there to certify. At the end it cost the money he got from the grant. His own time and machinery made up the rest of the grant cost application.
    Spot on Bass, my cousin and his father done the very same thing in 08 also. Back then you didn’t need to be ce certified to weld a grant shed so they made the shed themselves and done all labour for tank and shed themselves. They kept account of all their time spent and it all went in towards the grant. They ended up claiming back about the same amount as the materials cost so effectively had the shed for free.

    Nox I understand what you’re saying and what you mean and in general you’re right but it’s a different scenario when it comes to a grant job as you get to claim for all of your time spent up to the dept costings. I think the rate is €12.50 an hour so whether you’re welding, erecting the shed or just hanging gates, you get paid for it all.

    I’ve built using grants over the years and it just makes no sense to build without a grant if its available to be got.

    If materials can be purchased for less than 50% of the cost for a grant shed versus a non grant then you’d need to be seriously questioning either the quality of the materials or the integrity of the company selling the grant spec at such a high rate as there should be very little in the difference, maybe 10 to 15% max.


  • Registered Users, Registered Users 2 Posts: 19,581 ✭✭✭✭Bass Reeves


    DBK1 wrote: »
    Spot on Bass, my cousin and his father done the very same thing in 08 also. Back then you didn’t need to be ce certified to weld a grant shed so they made the shed themselves and done all labour for tank and shed themselves. They kept account of all their time spent and it all went in towards the grant. They ended up claiming back about the same amount as the materials cost so effectively had the shed for free.

    Nox I understand what you’re saying and what you mean and in general you’re right but it’s a different scenario when it comes to a grant job as you get to claim for all of your time spent up to the dept costings. I think the rate is €12.50 an hour so whether you’re welding, erecting the shed or just hanging gates, you get paid for it all.

    I’ve built using grants over the years and it just makes no sense to build without a grant if its available to be got.

    If materials can be purchased for less than 50% of the cost for a grant shed versus a non grant then you’d need to be seriously questioning either the quality of the materials or the integrity of the company selling the grant spec at such a high rate as there should be very little in the difference, maybe 10 to 15% max.

    Even now prefabricated barriers and gates are often no more than expensive than the material that goes into them. You will buy diagonal barriers for 250 each, two bar gates, adjustable heavy duty dividing gates etc. If you hang them yourself you Dave the labour on one of the sheds above the labour would be 5-600+ vat.9

    Slava Ukrainii



  • Posts: 24,714 ✭✭✭✭ [Deleted User]


    I think you miss understood my point.

    Apologies I did misunderstand.

    I didn't realise you can charge your own time to the grant, had assumed it would not be allowable.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 615 ✭✭✭Fine Day


    What is the thoughts of another TAMS for next year. I am sorry I did not start the process earlier this year but I think it maybe too late now.


  • Posts: 24,714 ✭✭✭✭ [Deleted User]


    Theheff wrote: »
    What is the thoughts of another TAMS for next year. I am sorry I did not start the process earlier this year but I think it maybe too late now.

    I'm wondering the same, its supposed to end this year but I'm very hopeful they will start another one in the coming year or two. I'm eligible for the 60% grant to build a shed and would hope to be able to get it in 2 years time or so.


  • Registered Users, Registered Users 2 Posts: 11,396 ✭✭✭✭Timmaay


    In terms of grants, I thought you are suppose to work out the final cost after all vat/grants back, and that's the amount that you put down as a capital allowance. The only reason a grant might complicate that is if you only get the grant in the following tax year, and you have already put the full price (ex vat) of the shed in as capital allowances. But even in that case it would definitely not make sense to put the grant in as an income for that year.

    Also grants do mean having to be able to bridge the cost of the grant until you draw it down. This is usually while you are waiting for the vat to come back also.

    Another consideration is if you have several possible tams projects, such say a milking parlour etc, and you expect to go over your 80k ceiling across the full duration of the tams project, in this case it could well pay to sacrifice the tams grant on the shed, to draw down the milking parlour one instead.

    Final point I'll make is if the shed is an extension of existing sheds, this could considerably complicate the department specifications required for a grant spec shed (for example the new shed often cannot use the existing sheds pillars/rafters).


  • Registered Users, Registered Users 2 Posts: 614 ✭✭✭farmer2018


    I am applying for an exemption for a slatted shed for sucklers. My options are as as follows what would ye go for I have 168m2 to play with.

    1. 3 Bay with creep
    2. 3 Bay with double tank and bigger slats
    3. 4 bay with 14'6 slats.

    I have existing sheds which I can use as calving pins and I could feed in as a creep.

    Ideally I want a 4 bay with creep/pins.

    All advice welcome please.


  • Registered Users, Registered Users 2 Posts: 4,146 ✭✭✭Hard Knocks


    farmer2018 wrote: »
    I am applying for an exemption for a slatted shed for sucklers. My options are as as follows what would ye go for I have 168m2 to play with.

    1. 3 Bay with creep
    2. 3 Bay with double tank and bigger slats
    3. 4 bay with 14'6 slats.

    I have existing sheds which I can use as calving pins and I could feed in as a creep.

    Ideally I want a 4 bay with creep/pins.

    All advice welcome please.
    Could you go 4 bay now and add creep behind the slats again?


  • Registered Users, Registered Users 2 Posts: 615 ✭✭✭Fine Day


    farmer2018 wrote: »
    I am applying for an exemption for a slatted shed for sucklers. My options are as as follows what would ye go for I have 168m2 to play with.

    1. 3 Bay with creep
    2. 3 Bay with double tank and bigger slats
    3. 4 bay with 14'6 slats.

    I have existing sheds which I can use as calving pins and I could feed in as a creep.

    Ideally I want a 4 bay with creep/pins.

    All advice welcome please.

    Would you not go and get planning for a shed that best suits your needs ad opposed to building a shed that is half right.


  • Registered Users, Registered Users 2 Posts: 614 ✭✭✭farmer2018


    Theheff wrote: »
    Would you not go and get planning for a shed that best suits your needs ad opposed to building a shed that is half right.

    Will be late for December Tams.


  • Registered Users, Registered Users 2 Posts: 615 ✭✭✭Fine Day


    farmer2018 wrote: »
    Will be late for December Tams.

    Is there not a TAMs for 2020 announced. I believe an exception takes time also.


  • Registered Users, Registered Users 2 Posts: 614 ✭✭✭farmer2018


    Theheff wrote: »
    Is there not a TAMs for 2020 announced. I an exception believe takes time also.

    4 weeks


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 615 ✭✭✭Fine Day


    farmer2018 wrote: »
    4 weeks

    Is TAMS there next year.


  • Registered Users, Registered Users 2 Posts: 19,581 ✭✭✭✭Bass Reeves


    Do a two stage shed. You could get the first half in for the Dec TANS if there is a TAMS in 2021 you could put on the second half of the shed.

    Design it as an A roof shed. You will be build the first half as a lean two. Put the high side at the back of the slats and the roof will slant down over the feed passage. A 16'6'' slat with 20'' of toe space back and front and an 8' overhang on the feed passage is 160 meters square.

    Then apply for planning for the lie back . You could have the lie back as deep as 28'. Even if you had to do this part without TAMS it would not break the bank. But you would have the shed you have want

    Slava Ukrainii



  • Registered Users, Registered Users 2 Posts: 3,806 ✭✭✭kk.man


    Do a two stage shed. You could get the first half in for the Dec TANS if there is a TAMS in 2021 you could put on the second half of the shed.

    Design it as an A roof shed. You will be build the first half as a lean two. Put the high side at the back of the slats and the roof will slant down over the feed passage. A 16'6'' slat with 20'' of toe space back and front and an 8' overhang on the feed passage is 160 meters square.

    Then apply for planning for the lie back . You could have the lie back as deep as 28'. Even if you had to do this part without TAMS it would not break the bank. But you would have the shed you have want

    Bass what would a 3 span cost (2 with slats 10 space each and the 3rd just concrete for machinery etc). I won't be applying for the grant but I won't be cutting corners either. There be no need for a gable end at one end as it be horizontal to an existing round roof shed?


  • Registered Users, Registered Users 2 Posts: 3,806 ✭✭✭kk.man


    Do a two stage shed. You could get the first half in for the Dec TANS if there is a TAMS in 2021 you could put on the second half of the shed.

    Design it as an A roof shed. You will be build the first half as a lean two. Put the high side at the back of the slats and the roof will slant down over the feed passage. A 16'6'' slat with 20'' of toe space back and front and an 8' overhang on the feed passage is 160 meters square.

    Then apply for planning for the lie back . You could have the lie back as deep as 28'. Even if you had to do this part without TAMS it would not break the bank. But you would have the shed you have want

    Bass what would a 3 span cost (2 with slats 10 space each and the 3rd just concrete for machinery etc). I won't be applying for the grant but I won't be cutting corners either. There be no need for a gable end at one end as it be horizontal to an existing round roof shed?


  • Registered Users, Registered Users 2 Posts: 19,581 ✭✭✭✭Bass Reeves


    kk.man wrote: »
    Bass what would a 3 span cost (2 with slats 10 space each and the 3rd just concrete for machinery etc). I won't be applying for the grant but I won't be cutting corners either. There be no need for a gable end at one end as it be horizontal to an existing round roof shed?

    Friend is doing a two bay slatted with a 10' lie back and two bay straw bedded for sucklers he putting in a crush . Off the top of my head he has it costed at 52K at TAM's spec. Less vat at 7k and grant at 17k gives him an end day cost at 28k. He do some of the work himself and hopes it will come on around 25K net. He has not really the tax to write off the 25k but he is happy enough at that.

    Not sure how you calculate back from that. It very hard to calculate non grant work

    Slava Ukrainii



  • Registered Users, Registered Users 2 Posts: 614 ✭✭✭farmer2018


    Have found out now I will only get the 40% what are my opinions? Is it worth availing of the 40%?


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 615 ✭✭✭Fine Day


    farmer2018 wrote: »
    Have found out now I will only get the 40% what are my opinions? Is it worth availing of the 40%?

    Yes I would say so. You will have a better shed at the end of the day.


  • Registered Users, Registered Users 2 Posts: 614 ✭✭✭farmer2018


    Can someone please tell me what will a 70K shed cost me getting a 60% grant vs 40% grant? Thanks.


  • Registered Users, Registered Users 2 Posts: 5,344 ✭✭✭Grueller


    farmer2018 wrote: »
    Can someone please tell me what will a 70K shed cost me getting a 60% grant vs 40% grant? Thanks.

    28k against 42k total cost to yourself.


  • Registered Users, Registered Users 2 Posts: 614 ✭✭✭farmer2018


    Grueller wrote: »
    28k against 42k total cost to yourself.

    I been told the shed will cost more than what the actual department costings are and that's the amount I will get for the grant.


  • Registered Users, Registered Users 2 Posts: 1,524 ✭✭✭grassroot1


    farmer2018 wrote: »
    I been told the shed will cost more than what the actual department costings are and that's the amount I will get for the grant.

    Yes that is correct look at what you can afford build a flexible shed and work from there.
    A slatted shed is only dear the day the payments are due. Either build or get out slopping in the muck is a non runner in todays world.
    DM IF you want have built 2 units since 08 so if you need a word no problems.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 2,685 ✭✭✭Cavanjack


    farmer2018 wrote: »
    I been told the shed will cost more than what the actual department costings are and that's the amount I will get for the grant.

    Was over at a friends the other day that feeds a lot of bulls. He is nearly finished a tams shed. 4 bay 26’wide feeding out both sides. Lovely shed built very well. Galvanised steel structure split into 8 pens. Very well finished. Lovely airy shed.
    He thinks 65kplus the vat will finish it. He is getting a 60% grant on it. Department costings are 70k so his own labour will bring his costings up to 70k. 60% of that should give him back 42k. So The shed will cost him 23k out of his pocket. Serious value.
    If he was getting a 40% grant he would get 40% of the 70k back. This would still be great value.
    Looking at his shed a grant is definitely the way to go.


  • Registered Users, Registered Users 2 Posts: 614 ✭✭✭farmer2018


    Cavanjack wrote: »
    Was over at a friends the other day that feeds a lot of bulls. He is nearly finished a tams shed. 4 bay 26’wide feeding out both sides. Lovely shed built very well. Galvanised steel structure split into 8 pens. Very well finished. Lovely airy shed.
    He thinks 65kplus the vat will finish it. He is getting a 60% grant on it. Department costings are 70k so his own labour will bring his costings up to 70k. 60% of that should give him back 42k. So The shed will cost him 23k out of his pocket. Serious value.
    If he was getting a 40% grant he would get 40% of the 70k back. This would still be great value.
    Looking at his shed a grant is definitely the way to go.

    Yes it is but still there is a big difference between the 60% and 40% approx 14k on 70k, could be make or break at the end of the day.


  • Registered Users, Registered Users 2 Posts: 19,581 ✭✭✭✭Bass Reeves


    farmer2018 wrote: »
    Can someone please tell me what will a 70K shed cost me getting a 60% grant vs 40% grant? Thanks.

    I presume the 70k is Inc vat.
    Vat will be about 8k.
    Grant at 60% is 37k
    Grant at 40% is 25k

    Shed @60% costs 25k net

    However you need to make sure that the total cost of 70k is allowed at department costings.

    70k seems a lot at costings for a 4 bay Suckler unit even allowing for calving pens, a crush, lie back or creep area etc.
    Shed @40% costs 37k net

    Slava Ukrainii



  • Registered Users, Registered Users 2 Posts: 2,685 ✭✭✭Cavanjack


    farmer2018 wrote: »
    Yes it is but still there is a big difference between the 60% and 40% approx 14k on 70k, could be make or break at the end of the day.

    Going without a grant could would cost not much less imo. Maybe 10k less for a fairly well done non grant spec shed of the same size maybe.
    So it’ll cost 60k without a grant. Still better off with the grant.
    For a building that should last 50 plus years I wouldn’t worry too much about 14k. It’s tax deductible also so if you pay the higher rate of tax it’s really only 8k more expensive than getting the 60% grant.


  • Registered Users, Registered Users 2 Posts: 19,581 ✭✭✭✭Bass Reeves


    Cavanjack wrote: »
    Going without a grant could would cost not much less imo. Maybe 10k less for a fairly well done non grant spec shed of the same size maybe.
    So it’ll cost 60k without a grant. Still better off with the grant.
    For a building that should last 50 plus years I wouldn’t worry too much about 14k. It’s tax deductible also so if you pay the higher rate of tax it’s really only 8k more expensive than getting the 60% grant.

    This is why lads putting in high fixed costs is not a reality even if you are depreciating or paying off a shed. Yes it a cost bits it's a 5-10 year cost on a 50 year plus investment. Any shed build to grant spec will have that life span longer if you make sure to get the actual physical tank and structural steel right. I galvanized the RSJ's. I definitely galvanize the upright RSJ's on any slatted unit whatever about the roof ones.

    I build a shed and slab in 2008-2010. It cost about 120 k. The vat was 15 k the grant was 63k the shed cost 42k net. it was as depreciated at the high tax rate so cost about 25k net. That 50/ euro per year over 50 years.

    It is a sour shed and I put in four straw beef and a crush. In 2014 I got fed up of buying straw and keeping them clean so I put a tank under three of of them it cost about 16 k net of vat no grant but a penning etc was Insitu so it was really digging out and putting in a tank and slats. However it was something I would not even consider looking for a grant for. Again it was depreciated against high rate of tax. So for sub 35k after tax I have housing for the equivalent of 100 stores with a crush under same roof along with a silage slab that is 20m X 12M. That about 700 we euro per year. At present I have 60 stores and 16 bullocks that did not finish off grass. If you put on the cost on the stores it a net cost of less than 12/ head per year. Even allowing for inflation and not allowing for tax on depreciation it about 25/ in that situation

    Slava Ukrainii



Advertisement