Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi all! We have been experiencing an issue on site where threads have been missing the latest postings. The platform host Vanilla are working on this issue. A workaround that has been used by some is to navigate back from 1 to 10+ pages to re-sync the thread and this will then show the latest posts. Thanks, Mike.
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Roads update Q4 2019

  • 28-12-2019 4:29am
    #1
    Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,460 Mod ✭✭✭✭


    N2 Ardee to Castleblayney: Route options published in November.
    N2 Clontibret to NI Border: Route options published in November.
    N2 Slane bypass: Emerging preferred route published in November. Submission to An Bord Pleanala expected by
    end of 2020.
    M4 Maynooth to Leixlip: Arup appointed as engineering consultants for Phases 1-4
    N4 Mullingar to Rooskey: AECOM/ROD JV appointed as engineering consultants for Phases 1-4
    N5 Ballaghaderreen to Scramoge: Advance works and fencing continue along the route
    N5 Westport to Turlough: Construction contract awarded to Wills/BAM JV, with construction to commence in early 2020.
    M6 Galway City Ring Road: Further information readvertised in Q4 2020. Oral hearing expected in early 2020.
    N11/M11 J4 to J14: Scheme options published in Q4 2019. Route selection to be complete in 2020.
    N17 Knock to Collooney: Route selection underway after public consultation on route constraints in Q4 2019
    M20 Cork to Limerick: Traffic surveys underway for project route selection
    N21 Abbeyfeale relief road: LIDAR and topographical route surveys have commenced.
    M21 Limerick to Foynes: Scheme was published including motorway order, CPO and Environmental Impact Assessment Report in December. Project submitted to An Bord Pleanala with decision expected in 2020.
    N21 Newcastlewest relief road:LIDAR and topographical route surveys have commenced.
    N22 Farranfore to Killarney: Tenders issued for engineering consultants for Phases 1-4
    N22 Macroom to Ballyvourney: Construction contract awarded to Jons/John Craddock JV, with construction to commence in early 2020.
    N24 Cahir to Limerick Junction: Arup appointed as engineering consultants for Phases 1-4
    N25 Waterford to Glenmore: Consultants completing Phase 1 by end 2019 with route selection to begin in 2020.
    M28 Cork to Ringaskiddy: High Court challenge to ABP planning decision was dismissed.
    N52 Tullamore to Kilbeggan: RPS appointed as engineering consultants for Phases 1-4
    N59 Oughterard to Clifden: 5.2km section from Maam Cross to Bunnakill to commence construction (Clare Civil as contractors) in January 2020. Fencing and advance works to commence on next 10km section between Bunnakill and Oughterard. Once design work on the Bunnakill to Oughterard section is complete, redesign will commence on the Maam Cross to Clifden section.
    N59 Westport to Mulranny: Southernmost section between Kilmeena and Westport to commence construction as part of N5 project in early 2020.
    N69 Listowel bypass: Opening of tenders approved by Kerry County Council in December. Procurement process to follow with scheme likely to start in mid 2020.
    N72 Mallow Northern Relief Road: JB Barry appointed as engineering consultants for Phases 1-4
    N86 Tralee to Dingle: Ground investigations and other advance works continue on the next 7km section between Ballynasare and Annascaul, and Doonore North and Ballygarret


Comments

  • Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,460 Mod ✭✭✭✭marno21


    Phase 7 - Completion
    M7 Naas/Newbridge bypass upgrade [13.5km D3M] [open to traffic]
    M11/N30 Gorey-Enniscorthy [27km D2M + 4km T2DC + 8km T1SC] [open to traffic]
    N56 Mountcharles-Drumbeigh [2.5km T1SC] [open to traffic]
    N59 Kilmeena [2.6km T3SC] [presumed open to traffic]
    N86 Camp-Ballygarret [1.1km T3SC] [open to traffic]
    N86 Ballynasare-Lispole [2.7km T3SC] [open to traffic]

    Phase 6 - Construction
    N4 Collooney-Castlebaldwin [14km T2DC + 1km T1SC] [construction underway; Q3 2021 completion]
    N5 Westport-Turlough [20km T2DC + 5km SC] [construction imminent; Q1 2022 completion]
    N22 Macroom-Ballyvourney [22km T2DC] [construction imminent; Q1 2023 completion]
    N25/N30 New Ross PPP [4km T1DC + 10km T2DC] [Q1 2020 completion]
    N56 Kilkenny-Letterilly [3.6km T3SC] [early 2020 completion]
    N56 Drumbeigh-Inver [2.5km T1SC] [late 2020 completion]
    N59 Maam Cross-Bunnakill [5km T3SC] [construction begin in January]
    N59 Kilmeena-Westport [construction imminent]

    Phase 5 II - Tender
    N3 Snugborough Interchange
    N8/N25/N40 Dunkettle Interchange [mid 2020 start]
    N56 Dungloe-Cloghbolie [7.1km T3SC] [Q1 2020 start; Q1 2022 completion]

    PIN (Prior Information Notice) for tender issued:
    N56 Letterilly-Kilraine [7.5km T3SC] [tender due Q1 2020]
    N69 Listowel bypass [6km SC] [mid 2020 start]

    Phase 5 - Advance works and land acquisition
    N5 Ballaghaderreen-Scramoge [35km T1SC] [CPO & advance works underway; late 2020 start]
    N59 Moycullen bypass [4.5km T1SC] [tender shortly]
    N86 Ballynasare-Annascaul [4.7km T3SC] [tender due, advance works ongoing]
    N86 Doonore North-Ballygarret [2.3km T3SC] [tender due, advance works ongoing]

    N59 Bunnakill-Oughterard [10km T3SC] [advance works ongoing]
    N59 Derrada-Newport [4.7km T3SC] [advance works ongoing]

    N59 Derrada-Roskeen [4km T3SC] [in queue, phased implementation]
    N59 Roskeen-Mulranny [8km T3SC] [in queue; phased implementation]
    N86 Dingle-Lispole [10km T3SC] [in queue; phased implementation]
    N86 Camp-R560 [1.1km T3SC] [in queue; phased implementation]
    N86 Gortbreagoge-Doonore North [7.4km T3SC] [in queue; phased implementation]

    Phase 4 - Statutory process
    M6 Galway City Ring Road [12km M + 6km T1SC] [decision due mid 2020]
    M21 Adare-Rathkeale-Foynes [16km M + 17km T2DC] [planning decision pending]
    M28 Cork-Ringaskiddy [12km M] [approved by An Bord Pleanala; appeal period active]
    N52 Ardee bypass [4.5km T2SC] [design review + possible Part VIII planning underway]

    Phase 3 - Design
    N3 Clonee-M50 [5km D3M/T1DC]

    Phase 2 - Route selection
    N13/N56 Letterkenny Bypass + DC upgrade [preferred route due January]
    N13/N15 Ballybofey/Stranorlar bypass [preferred route due January]
    N14 Letterkenny-Lifford [19km T2DC] [preferred route due January]

    N2 Slane bypass [3.4km] [emerging preferred route published]
    N55 Athlone-Ballymahon [on hold pending design funding]

    N2 Ardee-Castleblayney [32km] [route options published]
    N2 Clontibret-NI Border [28km] [route options published]
    M11 J4 Bray- J14 Coyne's Cross [23km] [options published; ABP by Q2 2021]
    N70 Milltown bypass [route options published]**

    Phase 1 - Feasibility study/project scope
    N17 Knock-Collooney [55km] [constraints study underway]
    M20 Cork -Limerick [constraints study underway]
    N21 Abbeyfeale bypass [constraints study underway]
    N21 Newcastlewest bypass [constraints study underway]
    N25 Waterford-Glenmore [9.5km DC] [constraints study underway]

    N2 Ashbourne-Kilmoon Cross [6km] [consultants appointed]
    M4 Leixlip-Maynooth [10km] [consultants appointed]
    N4 Mullingar-Roosky [52km T1/T2DC] [consultants appointed]
    N3 Virginia bypass [consultants appointed]
    N11/N25 Oilgate-Rosslare [consultants appointed]
    N24 Cahir-Limerick Junction [27km T2DC] [consultants appointed]
    N52 Tullamore-Kilbeggan [consultants appointed]
    N72/N73 Mallow Northern Relief Road [consultants appointed]

    N4 Carrick on Shannon-Dromod [21km T2DC] [tender out for consultants]
    N22/N23 Farranfore-Killarney [27km T2DC + 1km SC] [tender out for consultants]
    N25 Carrigtwohill-Midleton [tender our for consultants]

    N24 Waterford-Cahir
    M50 Dublin Port South Access Road
    N59 Clifden-Maam Cross [design work to begin after MC-Oughterard design complete]
    N71 Bandon relief road extension

    Phase 0 - Pre-appraisal
    N25 Castlemartyr relief road [planning to commence in 2020]
    N26 Ballina Relief Road [planning to commence 2020]
    N40 Cork North Ring Road [planning to commence in 2020]
    N84 Ballindooley-Clonboo [pre appraisal underway]

    The extended panel (to be advanced post 2027)
    M1 Lissenhall-Balbriggan
    N2 Kilmoon-Slane
    N2 Slane-Collon
    N3 Cavan-Butlersbridge
    M4 Maynooth-Kilcock
    N5 Turlough-Bohola
    M7 Newbridge-Monasterevin
    N13 Stranorlar-Letterkenny-Bridgend
    N15 Sligo-Cliffony
    N17 Tuam-Claremorris
    N21 Rathkeale-Abbeyfeale [33km T2DC]
    N22 Ballincollig-Macroom [24km T1DC]
    N24 Limerick-Caherconlish
    N25 Midleton-Youghal
    N25 Waterford-Dungarvan
    N26 Ballina-Bohola Phase 2
    N27 Cork Airport-N40 [to be advanced under CMATS]

    Dead until further notice
    N2 Ardee-Collon
    N15 Stranorlar-Lifford
    N23 Castleisland-Farranfore
    N24 Boher-Limerick Junciton
    N25 New Ross-Wexford
    N30 Moneytucker-New Ross


  • Registered Users Posts: 830 ✭✭✭DumbBrunette


    Thanks Marno :) Here's a few more projects you could add, as follows-

    N26 Cloongullane (1.8km Type 2 SC): At tender, contract award in Q2 2020.

    N60 Lagnamuck (1.4km Type 2 SC): Open to traffic.

    N60 Heathlawn (3.6km Type 2 SC): To be tendered in 2020.

    N60 Manulla (4km Type 1 SC): CPO to be issued in Q1 2020.

    Galway Co Co are also working on the N17 Milltown realignment (4km Type 1 SC) but it's very hard to find information on it. There have been two public consultations and there is a preferred route so I could see it going to ABP in 2020.


  • Moderators, Science, Health & Environment Moderators Posts: 5,145 Mod ✭✭✭✭spacetweek


    2020 won't be too great for new starts.
    Three schemes that were supposed to start in 2019 and one single carriageway.
    Rest are all very minor.


  • Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,460 Mod ✭✭✭✭marno21


    spacetweek wrote: »
    2020 won't be too great for new starts.
    Three schemes that were supposed to start in 2019 and one single carriageway.
    Rest are all very minor.

    The funding profiles for many minor schemes seem to indicate they will start in 2020 which is good news for much of the neglected national secondary network.

    The main issue now is the lack of major schemes with planning, something which has been repeatedly pointed out by myself and others over the past few years, we’ve reached the day where it’s an issue now.

    Apart from the N5 (down to start this year) and the M28, there is no other major scheme with planning permission (apart from Dunkettle and it’s issues). This year we should hopefully see the M21 and M6 schemes get planning which will help down the road

    The positive I can take at the minute is how quickly Roscommon County Council have progressed the N5 scheme after it got planning. At present, they are still on track to get it from planning approval to shovels in the ground in less than 2 years. That’s a 35km scheme in a sensitive area. If they can do that, I have hope for the M6/M21/M28 schemes moving quickly after planning approval provided funding is forthcoming. It’s a big change from the current starts which took years from planning approval to construction start.


  • Moderators, Science, Health & Environment Moderators Posts: 5,145 Mod ✭✭✭✭spacetweek


    Marno, any point trying to update your list there? Mightn't be much change after the doldrums of lockdown.


  • Advertisement
  • Registered Users Posts: 130 ✭✭tharlear


    Phase 4 - Statutory process
    M6 Galway City Ring Road [12km M + 6km T1SC] [decision due mid 3030]

    Phase 1 - Feasibility study/project scope
    M20 Cork -Limerick [constraints study underway, due when hell freezes over, which is due shortly before 3030]

    Dart interconnector, that will have to wait a while.


  • Moderators, Entertainment Moderators, Science, Health & Environment Moderators Posts: 14,460 Mod ✭✭✭✭marno21


    spacetweek wrote: »
    Marno, any point trying to update your list there? Mightn't be much change after the doldrums of lockdown.

    Will put up a combined Q1/Q2 update later. Hadn’t bothered with Q1 when lockdown kicked off