Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

New House Build, Costs+ on engineering

  • 09-01-2019 9:26pm
    #1
    Registered Users, Registered Users 2 Posts: 35


    Hi,

    Via full service from an architect we tendered for construction of our house that is now stage 2 complete. Engineering drawings were not supplied at tender stage. During stage 1 the engineer drove a number of unanticipated requirements, some of which were not progressed and others which were.

    - Steel lintels over the windows were not progressed because it was proven that the concrete ones were certified to take the weight asked of them.
    - 2 corner floor to ceiling door sliders external to our kitchen which were originally expected to be supported by a single steel post with the rest supported by load bearing walls changed to requiring 3 posts, 3 concrete support pads in the foundation
    - steel was introduced at room entrances where the builder would have thought a concrete lintel would have sufficed.

    The sense I have is that the engineer over specced by default, the architect and builder won a pushback on some items and failed at others leaving us exposed to cost we did not anticipate.

    We think:

    - the architect should have known to get the engineering done before tender so the drawings could be published with tender. This would have avoided unanticipated costs.
    - the engineer has still likely overspecced


    We are thinking of getting a retrospective second option on the engineering gone into this. I think the architect has a case to answer here too. What do you think? Comments appreciated.

    Regards,
    Adrian


Comments

  • Moderators, Home & Garden Moderators Posts: 10,146 Mod ✭✭✭✭BryanF


    What’s was the contract sum?

    And what is the extra over for structural elements ?

    Assume this is a new build?

    What was/is the contingency sum ?


Advertisement