simple question

  • 17-12-2018 02:05PM
    #1
    Registered Users, Registered Users 2 Posts: 393 ✭✭


    eh we'll it should be!!
    If I spent 66k on getting a job done and it is only 80% complete, how much will total job cost? My brain has stopped working today.


Comments

  • Registered Users, Registered Users 2 Posts: 6,170 ✭✭✭troyzer


    strandsman wrote: »
    eh we'll it should be!!
    If I spent 66k on getting a job done and it is only 80% complete, how much will total job cost? My brain has stopped working today.

    (66/8)*10= 82.5


  • Registered Users, Registered Users 2 Posts: 1,541 ✭✭✭NewClareman


    strandsman wrote: »
    eh we'll it should be!!
    If I spent 66k on getting a job done and it is only 80% complete, how much will total job cost? My brain has stopped working today.

    10% costs 66/8 = 8.25.
    Job cost = 100% = 82.5k 🙂


  • Registered Users, Registered Users 2 Posts: 393 ✭✭strandsman


    sound out. Cheers


  • Registered Users, Registered Users 2 Posts: 5,130 ✭✭✭Yakuza


    You forgot to add 10% for every time the builder takes in a deep breath during the estimate divided by the probability of it being done before Christmas.