Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Self build design stage

  • 15-08-2018 9:21pm
    #1
    Registered Users, Registered Users 2 Posts: 6


    We’re hoping to build next spring so getting plans in place and applying for planning shortly. Planning on building bungalow 3 bed 1500sq foot and converting to dormer later but now we’re thinking of putting in dormer windows at build stage so Work later is all internal. Anyone have any experience with this? We won’t get mtg to cover full build st this time


Comments

  • Boards.ie Employee Posts: 12,597 ✭✭✭✭✭Boards.ie: Niamh
    Boards.ie Community Manager


    Moved to Construction & Planning, hopefully you can get some help here, Mariokk.


  • Moderators, Society & Culture Moderators Posts: 40,366 Mod ✭✭✭✭Gumbo


    Mariokk wrote: »
    We’re hoping to build next spring so getting plans in place and applying for planning shortly. Planning on building bungalow 3 bed 1500sq foot and converting to dormer later but now we’re thinking of putting in dormer windows at build stage so Work later is all internal. Anyone have any experience with this? We won’t get mtg to cover full build st this time

    Add the dormers and the structure now!
    Getting that work done later will cost twice as much plus the damage to the existing house then that you will need to finish.


  • Registered Users, Registered Users 2 Posts: 1,175 ✭✭✭kieran.


    Have a plan for how you are going to link the ground floor and first floor insulation and air-tightness layers if you dont plan it out now you wont be able to get continuity later.