New Build

  • 09-08-2017 8:03am
    #1
    Registered Users, Registered Users 2 Posts: 26


    I am starting a new build in 2 weeks and plan is to connect to the mains I completed my application 2 weeks ago and I was told today that it would be 4-6 weeks to hear from irish water. My question is can I commence building without receiving the letter of connection from Irish Water.  


Comments

  • Closed Accounts Posts: 172 ✭✭Irish Water: Siobhan


    Hi smccart6

    Thank you for your query.

    We have requested further information on your behalf and a member of our team will contact you as soon as we receive an update.

    Please don't hesitate to contact us if you have any further queries.

    Kind Regards,
    Siobhan


  • Registered Users, Registered Users 2 Posts: 26 smccart6


    What further information?

    Hi smccart6

    Thank you for your query.

    We have requested further information on your behalf and a member of our team will contact you as soon as we receive an update.

    Please don't hesitate to contact us if you have any further queries.

    Kind Regards,
    Siobhan


  • Closed Accounts Posts: 172 ✭✭Irish Water: Siobhan


    Hi smccart,

    Thank you for your patience while we looked into your query.

    As every New Connection application differs, the response you receive in terms of the feasibility and costs of your proposed connection may have an impact on your current building plans.

    As such, pending a confirmation of this necessary information, we cannot advise you as to whether you should proceed with building works. If you choose to do so it would be at your own discretion.

    If you have any further questions, please let us know.

    Kind Regards,
    Siobhan