Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

General timeline

  • 27-07-2017 4:43pm
    #1
    Registered Users, Registered Users 2 Posts: 415 ✭✭


    Hi,

    I just applied online for a new water connection. I'm wondering how long this process takes overall? Or how long until I'm contacted to proceed to next stage.

    Thank you


Comments

  • Closed Accounts Posts: 709 ✭✭✭Irish Water: Mairead


    Hi milhous,

    Thanks for your query.

    After assessing your enquiry, Irish Water will tell you if a connection is technically feasible. We will provide you with confirmation of feasibility which can be submitted with your planning application. Irish Water will then issue you with an offer to connect, detailing costs and the works required to enable your connection.

    It can take approximately 4 - 6 weeks after your initial application to receive a quote and then proceed with your connection.

    You can find more information on the New Connections process here.

    Kind regards,
    Mairead