Building / planning

  • 23-07-2017 7:25pm
    #1
    Registered Users, Registered Users 2 Posts: 2


    I have received planning permission for a two storey side extension to my house was keeping a side entrance of 850
    But now I would like to lose the the side entrance and move the side of the extension over to boundary wall
    It has been done a lot around the area

    So I know I would have to resubmit plans to Dublin council
    But anyone know how long it would take
    Thank appreciate any good advice


Comments

  • Moderators, Society & Culture Moderators Posts: 40,365 Mod ✭✭✭✭Gumbo


    gar2055 wrote: »
    I have received planning permission for a two storey side extension to my house was keeping a side entrance of 850
    But now I would like to lose the the side entrance and move the side of the extension over to boundary wall
    It has been done a lot around the area

    So I know I would have to resubmit plans to Dublin council
    But anyone know how long it would take
    Thank appreciate any good advice

    Standard planning application for an alteration to previously approved permission.

    New drawings.
    New notices.
    8 weeks for decision.
    Another 4 weeks for final grant.


  • Registered Users, Registered Users 2 Posts: 2 gar2055


    kceire wrote: »
    Standard planning application for an alteration to previously approved permission.

    New drawings.
    New notices.
    8 weeks for decision.
    Another 4 weeks for final grant.

    Thanks for info someone was telling me it could take 5 to 6 months


  • Subscribers Posts: 42,172 ✭✭✭✭sydthebeat


    gar2055 wrote: »
    Thanks for info someone was telling me it could take 5 to 6 months

    it could take that long... kceire has outlined in the quickest timeline.

    after 8 weeks the council could request "further information" to be supplied.
    if this happens, then your timeline could very well extend to the 5 - 6 months suggested.


  • Moderators, Society & Culture Moderators Posts: 40,365 Mod ✭✭✭✭Gumbo


    gar2055 wrote: »
    Thanks for info someone was telling me it could take 5 to 6 months
    sydthebeat wrote: »
    it could take that long... kceire has outlined in the quickest timeline.

    after 8 weeks the council could request "further information" to be supplied.
    if this happens, then your timeline could very well extend to the 5 - 6 months suggested.

    +1

    Also, I haven't allowed for the time for the agent to prepare the drawings, arrange for the application etc