Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Slatted house cost

  • 23-11-2016 9:55pm
    #1
    Registered Users, Registered Users 2 Posts: 577 ✭✭✭


    Anyone put up one lately. What sort of money are they costing these days. Might go extending next year..


Comments

  • Registered Users, Registered Users 2 Posts: 2,313 ✭✭✭TITANIUM.


    gerryirl wrote: »
    Anyone put up one lately. What sort of money are they costing these days. Might go extending next year..

    A fella down here reckons he put up a 3bay standard for finishing for 23k out the gate.


  • Registered Users, Registered Users 2 Posts: 2,262 ✭✭✭Farrell


    TITANIUM. wrote: »
    A fella down here reckons he put up a 3bay standard for finishing for 23k out the gate.

    As in 3 bay single with open front?


  • Registered Users, Registered Users 2 Posts: 577 ✭✭✭gerryirl


    That would not be dipped at that. That a cheap shed . I'm not going to skimp on quality. The shed I have at the minute is a super shed but It did cost me a small fortune though , want to some where in between this time


  • Closed Accounts Posts: 2,855 ✭✭✭I said


    TITANIUM. wrote: »
    A fella down here reckons he put up a 3bay standard for finishing for 23k out the gate.

    Grant spec or not?


  • Registered Users, Registered Users 2 Posts: 2,685 ✭✭✭Cavanjack


    Was trying to get a rough price on a 4 bay single with a 14' slat lately. Without shed walls (sitting in between two existing sheds) I was thinking I'd get It done for 20k after the grant.


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 2,313 ✭✭✭TITANIUM.


    Ya it was a 3bay single with open front. I can't say what spec it was. I would be thinking it was not a grant spec shed.


  • Registered Users, Registered Users 2 Posts: 577 ✭✭✭gerryirl


    Cavanjack wrote: »
    Was trying to get a rough price on a 4 bay single with a 14' slat lately. Without shed walls (sitting in between two existing sheds) I was thinking I'd get It done for 20k after the grant.


    Have you priced any one yet. That would seem super price, grand spec getting higher all the time


  • Registered Users, Registered Users 2 Posts: 2,685 ✭✭✭Cavanjack


    gerryirl wrote: »
    Have you priced any one yet. That would seem super price, grand spec getting higher all the time

    Would be going direct labour reckon I'd have slats on and passage way concreted for €19000 then surely another €10000 would build a simple lean to type shed. Add another €3000 for anything I'm missing leaves me with €32000. That would leave me with a cost of €19200 after 40% grant. Write it off against tax over a few years would leave it at half that price maybe.


  • Registered Users, Registered Users 2 Posts: 2,531 ✭✭✭High bike


    Cavanjack wrote: »
    Would be going direct labour reckon I'd have slats on and passage way concreted for €19000 then surely another €10000 would build a simple lean to type shed. Add another €3000 for anything I'm missing leaves me with €32000. That would leave me with a cost of €19200 after 40% grant. Write it off against tax over a few years would leave it at half that price maybe.
    doing one at the moment,4 bay with a 14'6'' slat and a 12'6'' lie back open at the front and it's coming in at28000 with nothing in it


  • Registered Users, Registered Users 2 Posts: 577 ✭✭✭gerryirl


    Jesus that's cheap , is it dipped, what's your tank coming in at with slats on


  • Advertisement
  • Closed Accounts Posts: 2,855 ✭✭✭I said


    High bike wrote: »
    doing one at the moment,4 bay with a 14'6'' slat and a 12'6'' lie back open at the front and it's coming in at28000 with nothing in it

    How much more re:feeding/dividing barriers and crush will it cost do ya reckon


  • Registered Users, Registered Users 2 Posts: 2,531 ✭✭✭High bike


    gerryirl wrote: »
    Jesus that's cheap , is it dipped, what's your tank coming in at with slats on
    thats just the shed not kitted out,75 ft tank and slats 14000,dug it out myself


  • Registered Users, Registered Users 2 Posts: 2,531 ✭✭✭High bike


    I said wrote: »
    How much more re:feeding/dividing barriers and crush will it cost do ya reckon
    dont know yet but the recession must be over,gave a man a list of what I wanted 3weeks ago to price and not a word from him since


  • Closed Accounts Posts: 2,855 ✭✭✭I said


    High bike wrote: »
    dont know yet but the recession must be over,gave a man a list of what I wanted 3weeks ago to price and not a word from him since

    Has he far to travel if he can't go home for lunch he mightn't want to travel very far


  • Registered Users, Registered Users 2 Posts: 2,531 ✭✭✭High bike


    I said wrote: »
    Has he far to travel if he can't go home for lunch he mightn't want to travel very far
    im sure the boss would give him a hang sandwich if push came to shove,more like he has work on and couldn't be arsed.If it was 5or6 yrs ago bet he'd be back with a quote fairly lively:D


  • Closed Accounts Posts: 2,855 ✭✭✭I said


    High bike wrote: »
    im sure the boss would give him a hang sandwich if push came to shove,more like he has work on and couldn't be arsed.If it was 5or6 yrs ago bet he'd be back with a quote fairly lively:D

    He might like chicken sangers ring the bollox again have ya anyone else with quotes


  • Registered Users, Registered Users 2 Posts: 577 ✭✭✭gerryirl


    A 3 bay 12foot 6 tank with slats up our way is 12 k plus vat, shed then could cost anything depending on quality, factor in walls , poured or blocks, concrete passage, stones then electric, water, it all adds up. Waiting on a few people to get back to me with prices


  • Registered Users, Registered Users 2 Posts: 180 ✭✭ELP


    Got mine poured this week 40ft with a 13ft slat. It will cost me about 8200+vat. That is digging shuttering and slat. Not great weather with frost when could I back fill?


  • Closed Accounts Posts: 3,433 ✭✭✭darragh_haven


    ELP wrote: »
    Got mine poured this week 40ft with a 13ft slat. It will cost me about 8200+vat. That is digging shuttering and slat. Not great weather with frost when could I back fill?

    Its supposed to be 21 days before you backfill. And in this cold weather, I'd try and leave for the 21 days. You could consider backfilling in 15 or 16 days in warm weather.


  • Registered Users, Registered Users 2 Posts: 2,531 ✭✭✭High bike


    ELP wrote: »
    Got mine poured this week 40ft with a 13ft slat. It will cost me about 8200+vat. That is digging shuttering and slat. Not great weather with frost when could I back fill?
    left it 3 weeks and didn't pack it too tight for another week and seems ok


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 2,531 ✭✭✭High bike


    I said wrote: »
    He might like chicken sangers ring the bollox again have ya anyone else with quotes
    no wont be ringing him don't believe in following lads to give em money,got a quote today of 280 incl vat for diagonal barriers ,how does that sound???????


  • Closed Accounts Posts: 2,855 ✭✭✭I said


    High bike wrote: »
    no wont be ringing him don't believe in following lads to give em money,got a quote today of 280 incl vat for diagonal barriers ,how does that sound???????

    In or around


  • Registered Users, Registered Users 2 Posts: 2,531 ✭✭✭High bike


    I said wrote: »
    He might like chicken sangers ring the bollox again have ya anyone else with quotes
    no wont be ringing him don't believe in following lads to give em money,got a quote today of 280 incl vat for diagonal barriers ,how does that sound???????


  • Registered Users, Registered Users 2 Posts: 577 ✭✭✭gerryirl


    What's a 3 or 4 bay stands no lads all in


  • Closed Accounts Posts: 2,855 ✭✭✭I said


    High bike wrote: »
    left it 3 weeks and didn't pack it too tight for another week and seems ok

    Have ya poured concrete for lie back yet


  • Registered Users, Registered Users 2 Posts: 2,531 ✭✭✭High bike


    I said wrote: »
    Have ya poured concrete for lie back yet
    my back is telling me I did it today😀


  • Closed Accounts Posts: 2,855 ✭✭✭I said


    High bike wrote: »
    my back is telling me I did it today😀
    Had ya no help


  • Registered Users, Registered Users 2 Posts: 2,531 ✭✭✭High bike


    I said wrote: »
    Had ya no help
    loads Dan and Ger


  • Closed Accounts Posts: 2,855 ✭✭✭I said


    High bike wrote: »
    loads Dan and Ger

    Leaning on the shovels no doubt


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 577 ✭✭✭gerryirl


    Anyone with a price


  • Closed Accounts Posts: 2,855 ✭✭✭I said


    gerryirl wrote: »
    Anyone with a price

    Today's journal has a nice shed in it today


  • Registered Users, Registered Users 2 Posts: 2,123 ✭✭✭Who2


    I said wrote: »
    Today's journal has a nice shed in it today

    Their was a fair turn in it for the builder at 49k including vat. well done shed but it will take a fair while for 20 sucklers in it to pay for it.


  • Registered Users, Registered Users 2 Posts: 6,225 ✭✭✭charolais0153


    Who2 wrote: »
    Their was a fair turn in it for the builder at 49k including vat. well done shed but it will take a fair while for 20 sucklers in it to pay for it.

    They said it holds 9 cows a bay:rolleyes: that declan fennel gets some awful advertising doesn't he any shed that's built is nearly always by him


  • Closed Accounts Posts: 2,855 ✭✭✭I said


    Who2 wrote: »
    Their was a fair turn in it for the builder at 49k including vat. well done shed but it will take a fair while for 20 sucklers in it to pay for it.

    Yeah some price when ya consider what OP build his one for.Usual the grant spec rides ya one way or the other.


  • Registered Users, Registered Users 2 Posts: 577 ✭✭✭gerryirl


    Who2 wrote: »
    Their was a fair turn in it for the builder at 49k including vat. well done shed but it will take a fair while for 20 sucklers in it to pay for it.

    ya ive been trying to figure out prices for it. Id say it s not too far off the mark to be honest . Remember he has a 9 foot tank and a 14"6 slat. Thats a big tank. He has alot of steel in it dipped and then the mats . If you take the price of the mats out and the 3 extra loads of concrete it around 38 plus vat

    Its a fine shed but there a a couple of changes Id make and It would cost him little more if any. Id have made the walk way a crush. it could still be a walkway. Id have done put different gates from the pen into the back bit. Id have them split in the middle to get cattle into or into the crush also he could have creep gate for calves on it. this would not have altered the price much. Having said that its still a tidy shed and hope it makes him plenty of money which the way its going at the minute he wont make a penny ...lol :)


  • Advertisement
  • Registered Users, Registered Users 2 Posts: 2,123 ✭✭✭Who2


    gerryirl wrote: »
    ya ive been trying to figure out prices for it. Id say it s not too far off the mark to be honest . Remember he has a 9 foot tank and a 14"6 slat. Thats a big tank. He has alot of steel in it dipped and then the mats . If you take the price of the mats out and the 3 extra loads of concrete it around 38 plus vat

    Its a fine shed but there a a couple of changes Id make and It would cost him little more if any. Id have made the walk way a crush. it could still be a walkway. Id have done put different gates from the pen into the back bit. Id have them split in the middle to get cattle into or into the crush also he could have creep gate for calves on it. this would not have altered the price much. Having said that its still a tidy shed and hope it makes him plenty of money which the way its going at the minute he wont make a penny ...lol :)
    Its way overpriced for what youll get back out of it, and if your anyway half handy youd have it up for an awful lot less, ive done a 4 bay with creep with a 14,6" slat for half the price a while back. im putting up another small 2 bay next spring and i reckon ill be out at around 14k after vat. he only had 1 bay up for the same coin.
    As for the pen size, unless theres longer bays you wont fit more than 7 average cows into a pen as each animal needs to be get its share, cows are tramps for bullying as they get on.


  • Registered Users, Registered Users 2 Posts: 577 ✭✭✭gerryirl


    agree with you it been overpriced for what youll get back out of it... a 3 bay tank 8 foot with slats my way is 12k plus vat. Everyone is in or around that price. shed then after that and a bit of concrete. Its the shed where the big differ in price is. Dipped, width of uprights etc.


  • Closed Accounts Posts: 3,239 ✭✭✭Willfarman


    It'll still be standing in 40 years time when the price of it is long forgot..

    Minus the vat and minus the grant its the price of a new car.. Which will be in scrap in 15 years time!