Rural Fibre Rollout Timeline Mayo

  • 27-10-2015 9:16pm
    #1
    Registered Users, Registered Users 2 Posts: 180 ✭✭


    Hi Eir,

    Regarding the the Rural fibre rollout, my home is situated in Tourmakeady Co.Mayo. On the map onhttp://fibrerollout.ie/where-and-when/ it is down as "Fibre Build Commenced".

    Is this correct? If so, when will fibre broadband be available to customers in this area? Will it be 2016/2017 etc..?

    Thanks alot,
    B


Comments

  • Closed Accounts Posts: 1,305 ✭✭✭eir: Alan


    bauney wrote: »
    Hi Eir,

    Regarding the the Rural fibre rollout, my home is situated in Tourmakeady Co.Mayo. On the map onhttp://fibrerollout.ie/where-and-when/ it is down as "Fibre Build Commenced".

    Is this correct? If so, when will fibre broadband be available to customers in this area? Will it be 2016/2017 etc..?

    Thanks alot,
    B
    Hi bauney

    Roll out works in your area is expected to commence soon however it is not expected to be finished and ready until approx 2020

    Thanks
    Al