Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Irish enterprise refurbishment project completion date

  • 25-09-2015 4:50pm
    #1
    Registered Users, Registered Users 2 Posts: 84 ✭✭


    Hi all,
    Does anyone know if the refurbishment project has been completed?

    I noticed that the Dublin-Belfast trains are showing 1st and 2nd class as well as restaurant car.

    Thanks


Comments

  • Registered Users, Registered Users 2 Posts: 11,174 ✭✭✭✭Captain Chaos


    It's far from complete, it's very far behind schedule. Only one set is near ready to return to service and is still under testing. It is due to enter service on Monday. The other two links are covered by an IE ICR that has some first class and the other is covered by an NIR C3K set that is all common class.

    The Irish Rail site is wrong on the service details on all or some of the services on the Belfast route.


  • Registered Users, Registered Users 2 Posts: 8,922 ✭✭✭GM228


    It's far from complete, it's very far behind schedule. Only one set is near ready to return to service and is still under testing. It is due to enter service on Monday. The other two links are covered by an IE ICR that has some first class and the other is covered by an NIR C3K set that is all common class.

    The Irish Rail site is wrong on the service details on all or some of the services on the Belfast route.

    The set is not due to re-enter service on Monday, was planned for 21st of this month but was put back until sometime in October.

    The site is wrong for some trains, the 07.35, 13.20 and 19.00 (and their associated returns) have first class and dining car as they are worked by the 22000s.