Psdp and Pscs

  • 17-08-2014 4:22pm
    #1
    Registered Users, Registered Users 2 Posts: 167 ✭✭


    Design on my house started in February 2012. Do I need a a Psdp now? I have a feeling I don't because of when the design process started.

    Also, if I run the build as a self build do I need a Pscs? Can I appoint myself as the Pscs? What does the Pscs need to do? Does the project need a safety file because of when the design started?


Comments

  • Registered Users, Registered Users 2 Posts: 1,583 ✭✭✭kkelliher


    lownhard wrote: »
    Design on my house started in February 2012. Do I need a a Psdp now? I have a feeling I don't because of when the design process started.

    Also, if I run the build as a self build do I need a Pscs? Can I appoint myself as the Pscs? What does the Pscs need to do? Does the project need a safety file because of when the design started?

    Yes you need to appoint if (a) there is more than one contractor, (b) there is a particular risk, (c) the work lasts more than 30 days or more than 500 person days


  • Moderators, Home & Garden Moderators Posts: 10,146 Mod ✭✭✭✭BryanF


    lownhard wrote: »
    Also, if I run the build as a self build do I need a Pscs?
    have you appointed a certifier (chartered arch/eng) under the new building control regs? has the self-build route been accepted by them?


  • Banned (with Prison Access) Posts: 246 ✭✭RITwing


    lownhard wrote: »
    Also, if I run the build as a self build do I need a Pscs? Can I appoint myself as the Pscs? What does the Pscs need to do? Does the project need a safety file because of when the design started?

    Axiomatic really. If you need to ask so many questions about the role of PSCS then you need to appoint one who can answer them.


  • Registered Users, Registered Users 2 Posts: 2,300 ✭✭✭martinn123


    lownhard wrote: »
    Design on my house started in February 2012. Do I need a a Psdp now? I have a feeling I don't because of when the design process started.

    Also, if I run the build as a self build do I need a Pscs? Can I appoint myself as the Pscs? What does the Pscs need to do? Does the project need a safety file because of when the design started?

    Have a read of this thread

    http://www.boards.ie/vbulletin/showthread.php?p=82266802

    should answer most of your questions.


  • Registered Users, Registered Users 2 Posts: 8 shaydoc


    Hi all Self builders,
    I am not sure if this is the correct forum for this question, so please re-direct me if needed.

    I am in a position of being self builder, on a renovation/extension project that needs multiple contractor/tradesmen types and will last 6 months, Is there anything stopping me appointing myself as a PSDP and PSCS and execute those roles from a work quality and safety point of view.
    Or what options are open to me to get the role of PSDP and PSCS executed for a selfbuilder.
    any advice appreciated.


  • Advertisement
  • Moderators, Home & Garden Moderators Posts: 10,146 Mod ✭✭✭✭BryanF


    shaydoc wrote: »
    Hi all Self builders,
    I am not sure if this is the correct forum for this question, so please re-direct me if needed.

    I am in a position of being self builder, on a renovation/extension project that needs multiple contractor/tradesmen types and will last 6 months, Is there anything stopping me appointing myself as a PSDP and PSCS and execute those roles from a work quality and safety point of view.
    Or what options are open to me to get the role of PSDP and PSCS executed for a selfbuilder.
    any advice appreciated.

    Hsa.ie

    Read the regs and comeback and tell us what you think?

    iF you take on this responsibility you had better understand your obligations..


  • Registered Users, Registered Users 2 Posts: 8 shaydoc


    BryanF wrote: »
    Hsa.ie

    Read the regs and comeback and tell us what you think?

    iF you take on this responsibility you had better understand your obligations..

    Hi BryanF,
    thanks for response.
    I have been on hsa.ie, read the publications for Homeowner and COntractors-Proj-SUpervisors guides, and the responsibilities are not small.

    But I am wondering how other self builder are executing this activity?
    Handling PSDP/PSCS them selves?
    Getting Engineer to carry out PSDP?
    Do I get another professional to carry out PSCS on site? Get a professional to advise me during construction phase?

    I have moved from single Builder path to Selfbuild path due to builder quotes over our budget. NOw I am in the middle of the commencement notice period and and trying to get this PSCS/PSDP decided on.

    thanks.


  • Moderators, Society & Culture Moderators Posts: 40,339 Mod ✭✭✭✭Gumbo


    Get whoever you are using to certify the build to act as these roles.
    If anything goes wrong, a judge will ask who the person was and what made him competent to carry out that role. OP, based on your posts, you are not competent to carry out that role, I mean no disrespect but competency comes from qualifications, experience and training over time.

    Ask your engineer or architect to act into these roles.