Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Invoices and RIAI standard form of contract

  • 15-04-2014 10:19am
    #1
    Registered Users, Registered Users 2 Posts: 659 ✭✭✭


    Is a builder obliged to issue an invoice on foot of an interim certificate or is presentation of the certificate enough to demand payment ?

    Thanks.


Comments

  • Registered Users, Registered Users 2 Posts: 6,548 ✭✭✭Claw Hammer


    Is a builder obliged to issue an invoice on foot of an interim certificate or is presentation of the certificate enough to demand payment ?

    Thanks.

    In order to be able to sue for payment an invoice needs to be issued.Normally it is agreed beforehand that payment must be made on completion of the interim certificate before work progresses further.


  • Registered Users, Registered Users 2 Posts: 78,580 ✭✭✭✭Victor


    Is a builder obliged to issue an invoice on foot of an interim certificate or is presentation of the certificate enough to demand payment ?
    Yes. The exact timing of the invoice may be a sensitive matter for the builder as it may cause a VAT liability for them immediately.