Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Ground works time frame

  • 09-03-2013 6:52am
    #1
    Registered Users, Registered Users 2 Posts: 196 ✭✭


    Hi folks,
    I'm looking for a time frame for the completion of ground works here considering all machinery and material is available.
    The work to be done is as follows.
    1.Dig out install and backfill septic tank, junction boxes X 4, and percolation area (20 pipes)
    2.Lay out all sewer pipes to septic tank and to waste surface water trap.
    3. Prepare and level trunking for foot paths and get drive way to a level finish.
    4. Pour and finish foot paths.
    5.Dig out, run ESB duct to house(30m-40m), back fill.
    What I am looking for is a rough amount of time for one guy labouring and one digger operator for as long as is needed. 90meters of footpaths 1.5M wide and 4 inch deep(roughly 15M3 ready mix). All material will be ready and available. We have our own mini digger and a hired digger at our disposal. Just trying to plan my time and figure out when I will need to be starting this to finish in time to move into the house. I'm hoping 3-4 days week will see it done but am I dreaming.