Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

DPM where should it go and when

  • 19-11-2008 4:09pm
    #1
    Closed Accounts Posts: 4


    Hi,
    This is an Excellent forum, I have a question about the DPM.
    The situation is as follows.

    The building has all the walls completed.

    It has the following buildup:

    Compacted 3 inch down
    Randon Barrier
    Steel
    Raft Concrete slab

    The external leaf is concreteed to the low step of the raft with a block, then a soap bar and then DPC laid on top

    The internal leaf has DPC laid on top of raft, then a soap bar then dpc again.

    Is the DPM laid on top of the raft and folded up around by the edges of the internal walls?
    Then the insulation laid, UFH pipes and then screed.
    How high up the walls should it go?

    When is this part normally done, before windows and roof or after?

    Thanks...


Comments

  • Registered Users, Registered Users 2 Posts: 14,547 ✭✭✭✭Poor Uncle Tom


    The DPM should lap underneath the DPC on your internal leaf of the external wall all around creating a complete unbroken membrane throughout the entire footprint of the ground floor. Traditionally it is positioned a block below the DPC level and, as said, is lapped up the side of the last block and under the DPC on the inner leaf. Since the introduction of the Radon Barrier it is possible to get a membrane which will act as a DPM and a Radon Barrier but this is not always the case. If one barrier is used as both, its positioning is very important. It sounds as though your external finished ground level will be about 200mm below the Radon barrier level, if this is the case check if the barrier is meant to double as a DPM and also check that it is designed as a non liquid permeable membrane. Otherwise it is not possible with the walls in place to position a full DPM sucessfully, imo.


  • Closed Accounts Posts: 4 nfk


    Hi Tom,
    I'm not sure what type the Radon barrier is, its red in colour, fairly thick and not very flexable, I'll have to look at the packageing it came in to know for sure, it comes up to the top step where the first row of outer bricks sits.
    I think this will be just at ground level in my case.

    Has anyone just laid the DMP in each room with out having it under the DPC, was it a success?


  • Registered Users, Registered Users 2 Posts: 46,555 ✭✭✭✭muffler


    nfk wrote: »
    Has anyone just laid the DMP in each room with out having it under the DPC, was it a success?
    DPMs and DPCs must overlap at internal and external (inner leaf) walls.


  • Registered Users, Registered Users 2 Posts: 2,292 ✭✭✭RKQ


    Can you upload a few photo's?

    Its preferable that the dpm laps the dpc in the inner leaf of blockwork.
    It is still possible to lap the floor dpm up at least 150mm in each room. Its not ideal but its better than no dpm.
    If water enters the cavity at least it can't enter the side of the floor.

    Who designed or is certifying this construction?
    Have you discussed your concerns with your Certifier?


  • Closed Accounts Posts: 4 nfk


    Thanks RKQ,

    I have no way of transferring photos at the moment. I guess I'll make the best of the situation and lap the DPM up the height of the finished floors around by the edges and overlap it 150mm through the doors.


  • Advertisement
Advertisement