Advertisement
If you have a new account but are having problems posting or verifying your account, please email us on hello@boards.ie for help. Thanks :)
Hello all! Please ensure that you are posting a new thread or question in the appropriate forum. The Feedback forum is overwhelmed with questions that are having to be moved elsewhere. If you need help to verify your account contact hello@boards.ie
Hi there,
There is an issue with role permissions that is being worked on at the moment.
If you are having trouble with access or permissions on regional forums please post here to get access: https://www.boards.ie/discussion/2058365403/you-do-not-have-permission-for-that#latest

Tunnelling under the airport

  • 26-04-2006 1:56am
    #1
    Registered Users, Registered Users 2 Posts: 78,580 ✭✭✭✭


    The NRA seems to be knocking this on the basis that it would be too expensive to do bored tunnels. However they could do cut and cover tunnels (less deep and cheaper) if they tied it in with the existing station void and the work on the new runway and Terminal 2.
    • Commence preparations and construction of west end of 10L/28R.
    • Commence cut and cover tunnel either side of 11/29 threshold, including start of 10L/28R and additional taxiways (not on drawings).
    • Complete construction of west end of 10L/28R.
    • Transfer operations from 11/29 to 10L/28R (short).
    • Complete cut and cover tunnel under 11/29 threshold.
    • Demolish 11/29.
    • Complete construction of west end of 10L/28R.
    • Transfer operations from 10R/28L to 10L/28R.
    • Commence cut and cover tunnel either side of 10R/28L threshold as far as apron.
    • Complete cut and cover tunnel under 10R/28L.
    • Extend 10R/28L.
    • Re-open 10R/28L with left/right operations.
    • Proceed with cut and cover tunnel under surface car park.
    • Demolish sections of apron (note aircraft can use 10R/28L taxiway to access cargo area).
    • Build cut and cover tunnel under apron.
    • Connect to existing sections of tunnel.
    • Build Terminal 2 over tunnel.