userduluth wrote: » previous houses in Barnwell were atleast 3 or 4 months delayed and I don't expect anything spectacular happening in Beechwood either
k100 wrote: » Is the delay caused because the were focusing on beechwood? I did ask if they were closing purchases in batches of completion or per house completion They said per house basis, The closer your house is to the entrance of the estate the soon you it should be in theory?
userduluth wrote: » lot of delay happens due to Fingal issues which are out of the builders hands....but, dont know whats difference in approach between Hansfield homes and Barnwell builders as Hansfield homes seems to happen pretty quickly but Barnwell is delayed a lot
ShanMohan wrote: » Hi, I purchased the property in Barnwell Groove the construction of the door numbers 18-24 is still in progress there is no clear date of hand over from the builder. During sales , the builder has promised to deliver the property by Aug 2017. They have defaulted the Aug date and after several chase up builder informed that they will complete construction and handover by Nov 2017. However, there is no significant progress made for past few weeks, looks like the work is stopped not sure if they can still deliver by Nov 2017. I see their other site Beechwood is progressing in full pace. There is no clear communication from the builder end on the completion date. If someone has update on the completion of above door numbers(18-24 Barnwell Groove). Please post to this forum Thanks
userduluth wrote: » Hi I need some suggestions please, I found a big crack in the bathtub will the builder change it or do I need to do it my self?
Thomas16 wrote: » Hi, Better to ask Robert in the site office. Tadhg is the responsible person to do this. But Robert is a good man to deal with. I think, Tadhg doesn't give any warranty for the sanitary items!!! Normally If we buy such sanitary items, shop will give a 10-15 yrs warranty. I don't know any legal scope to get warranty from the builder. Thank You
nelly river wrote: » I was told January 2018 for completion of my Ash house in Beechwood. When is the time to choose kitchen/layout/finishes? I wanted to request positioning of extra sockets and extra light fittings, outdoor tap and outdoor socket. For the box bedroom, I wanted to add some storage. Thinking of a sliding wardrobe by cutting into bedroom 1 and taking some space from the bigger bedroom. Did anyone get the attic floored and a stira folding attic stairs at build stage? Does John O' Connor tile guy fit wooden floors. The Agent said if we wanted floors in before we move in, we can only use John. Anyone have a contact number for who I should engage with for these queries/jobs?
alexf1 wrote: » @K100 The kitchens are being done by Bedroom Elegance. I'd advise contacting them and making an appointment to go through available kitchen options or you'll get exactly what was in the showhouse. http://bespace.ie/ The wardrobes are done by a kitchen place called McCauls Kitchens (confusing I know...) and they also have some interior options if you fancy them. Give them a shout asap if you want anything different. http://www.mccaulkitchens.ie/ The electrician will add extra sockets and lights for a cost, but again, get in contact before they start working in the house. You can get their number from the site office.
ck0 wrote: » Hi again, Can somebody please PM me details of Jimmy O'Connor (tile guy)? Thank you!
ck0 wrote: » @jdp2017 Thanks! Need help! Did someone sign the contract yet? I am wondering regarding Help To Buy scheme. Estate Agents asked for an access code to get our allowance figures from Revenue and we gave them. However In the Contracts our solicitor has nothing is mentioned regarding any discounts we should have and the balance we would need to pay after grant is payed to a Builder. Shouldn't it (HTB) be outlined in the Contract ? Smth like (TOTAL_AMOUNT - HTB) = you have to pay at the end.
Thomas16 wrote: » J. O’ Connor Tiling Ltd ( Jimmy 087 2543099); email: info@joconnortiling.ie
k100 wrote: » Mine was not outlined, either. Your solicitor should have access to your allowance figures to confirm also with the developers Solicator and you write a cheque of (Total Deposit - HTB Allowance - booking deposit).
Phil.x wrote: » FYI
lunamia wrote: » You didn’t (couldn’t maybe) buy, but you’re always here keeping throwing s*it to this fantastic place. By the way, we don’t need your news, even because the apartments belong to Hansfield Wood, not Barnwell, which even with all the social houses/apartment is always better than what you can afford. You didn’t buy here, as you said, so have a life rather than loosing your time here with people that don’t appreciate your presence!
Phil.x wrote: » oh it's there alright, as well as the Two burnt marks on the ground from where two if not three cars were torched. I'm not surprised as it's in the middle of no man's land at the moment. Give it a few months and it will be like the middle east, something like ongar, renters land.