Dr. Nick wrote: » Cable laying on Ratoath to Dunshaughlin road this evening. More importantly, orange and black cables have reached Kiltale (Tara Exch), alllaid out on the side of the main Dublin/Trim road.
John mac wrote: » they had them laid out from Dunboyne nursing home through Summerhill and on to Rathmolyon last week . orange/black /blue cable ~12mm ish diameter (i was driving so its just a guess) as you say just laid out along the side of the road , coiled up every 20 meters
frozenfrozen wrote: » Not sure if this is the right thread for it I'm in an orange area. the line stops a good distance down our road, we aren't on the eir fibre rollout map http://fibrerollout.ie/rollout-map/ there are KN vans right outside the house now, with a big black spool, crane thing 4 vans and a further flat bed type thing at the top of the road. I asked them was it for internet, it is they said. I said but we're not on the blue line so to speak, "well it's being run here and everywhere will get it eventually" they said should I get my hopes up?
redfacedbear wrote: » I reported a few months back on a road down my way where they had gone a good 400-500m past the end of the blue line with the fibre. That road has now gone live but only as far as the end of the blue line. Any eircodes for houses beyond the limit are still failing on the eir website and blank on the openeir map. Fibre and splice boxes up but not live, must be beyond frustrating. I wouldn't get my hopes up if I were you!
frozenfrozen wrote: » redfacedbear wrote: » I reported a few months back on a road down my way where they had gone a good 400-500m past the end of the blue line with the fibre. That road has now gone live but only as far as the end of the blue line. Any eircodes for houses beyond the limit are still failing on the eir website and blank on the openeir map. Fibre and splice boxes up but not live, must be beyond frustrating. I wouldn't get my hopes up if I were you! Ok thanks that's me back down to planet earth. I suppose it's just as cheap for them to run everywhere they will eventually cover, now, while they're here and waiting on other stuff rather than just sitting idle.
rob808 wrote: » Try check the NBP map see if your house in light blue.
Dr. Nick wrote: » Cable laying on Ratoath to Dunshaughlin road this evening. More importantly (to me anyway ) , orange and black cables have reached Kiltale (Tara Exch), all laid out on the side of the main Dublin/Trim road.
Dr. Nick wrote: » Does any of this look familiar?
Allison Puny Appetite wrote: » Dr. Nick wrote: » Does any of this look familiar? Are you sure that is related to the FTTH rollout? Just googling the cable description it seems to be some sort of seismic monitoring? It is nothing like anything posted already in the thread.http://www.ymg.ru/en/content/seismic-equipmenthttp://geospace-ufa.ru/catalog/kabel/kabel-telmor.html
Gonzo wrote: » What's happening on the ratoath-dunshsughlin road is road surveying signs went up the other day.
Meath County Council website wrote: Teck Ireland wishes to advise the general public that a seismic survey will be carried out over the next few weeks by contractors IMC GSL - Surveying will continue for approx. 25 days. The first road to be surveyed is the "R125". The survey will include Rathmoylon, Summerhill and Ratoath. Date Released: 06 July 2017 Teck Ireland wishes to advise the general public that a seismic survey will be carried out over the next few weeks by contractors IMC GSL. This survey follows similar surveys carried out in county Meath in recent years. This survey will be a road survey using truck-mounted Vibroseis units and will be accompanied by a road crew placing small measuring units connected by cables at the side of road. Surveying will commence on or about the 30 June 2017 and will continue for approx. 25 days. The first road to be surveyed is the "R125". The survey will include Rathmoylon, Summerhill and Ratoath. The survey will produce geological data from depths as great as 2 km and is an element of our on-going mineral exploration programme. Teck Ireland wishes to apologise for any inconvenience arising from this work.
Pbbuster wrote: » Anyone having issues with ftth installation in the Galway area?? My forecast date is now 23/10/2017
d31b0y wrote: » I have to install new ducting on my private lane before install will go ahead. There is no ducting there at the moment and the current phone line just runs along a thin pipe on the ground. There are three houses on the lane but I believe only two will go ahead with the install. To be on the safe side, what size ducting would you recommend for three cores + some over?
Johnboy1951 wrote: » the question is which is correct? Openeir are the ones laying the fibre so if they do not have an exact date then eir retail are just guessing.
vintagevrs wrote: » So I spoke to my current provider of ADSL and asked them about FTTH. They gave the same date that Eir gave so I presume the system that the retailers use for orders/line checks is OpenEirs portal and this is where the specific date of the 2nd August came from. Still not DPs up, just the fibre on the poles. So I hope there's so activity outside this week.
Johnboy1951 wrote: » I have much more confidence in openeir's dates.
knipex wrote: » Be Very careful. I know of more than one person who was signed up to a special offer on "fibre" with their current supplier to later discover they were tied up to contracts for 2 years that were actually fiber to the cabinet.. In many cases they were 3, 4 5 or more kilometers from the cabinet so getting 1 mb down.. When FTTH did become available they ended up having to buy out 2 year contracts or stick with their current crappy copper.. Funny these "special offers" only became available 2 to 3 monhts before FTTH became available..
vintagevrs wrote: » That's my point though. My current provider would have got that date from OpenEir, they wouldn't deal with Eir.
vintagevrs wrote: » As for OpenEir emailing me and others, which I found surprising as I would expect them only to deal with Telcos and not the public, I would say they are just being safe and non specific.