€216m spent to date including compensation to disappointed bidders. The amount was roughly known already but the C&AG provides some breakdown.
6.38 Three public transport PPP projects in development over a number of years have been postponed. The status and expenditure to date of each is outlined in Figure 6.6. The status of the projects when they were postponed is reflected in the level of costs incurred. Metro West was postponed at railway order application process stage, Dart Underground at pre-qualification of bidders stage and Metro North at the short listing of bidders stage.
Figure 6.6 Expenditure on Cancelled Public Transport Projects to end December 2011 - Amounts in €000s
Expenditure category |Metro North|Dart Underground|Metro West
Property acquisition| 25,668|—|—
Design & PPP procurement| 31,673| 19,921| 5,328
Enabling works| 51,058| —| —
Legal, financial, commercial and insurance advisors| 20,670| 4,668| 37
Railway order application/preparation| 10,477| 1,435| 10,173
Oral hearing| 5,510| —| 918
Other/overheads| 9,418| 17,086| 2,079
Total| 154,474| 43,110| 18,535
Source: Department of Transport, Tourism and Sport
6.39 In the case of Metro North, a total of 13 properties were purchased by the Railway Procurement Agency (RPA) and these properties continue to be held by them. The costs of these properties, including advice and other property related costs, amount to €25.7 million. No lands were
purchased in the case of Dart Underground and Metro North.
6.40 As part of the PPP tender competition for Metro North, it was agreed to compensate the underbidders for their verifiable tendering costs up to a maximum of €1 million each in the event of the PPP procurement process being deferred. The RPA have paid one of the bidders € 1 million in
compensation and it is awaiting further information to support the compensation claim of €1 million from the other.