Hi folks new here and looking for anybody in a similar position
My story goes as follows,
In 2005 I bought an old rural property,an old stone cottage,all in reasonable repair and liveable with running water,power etc.
The masterplan was to renovate the cottage,sell it and retain and biuld on half an acre of land included in the sale.Due to work and money it was 2007 before work started on stripping out the old cottage.One of the first things done was to ring the ESB and request the power to be disconnected to make it safe for workers to strip the roof etc.After a quick phone call,ESB were vans on site,power disconnected,all hunky dorey and me a very happy customer.
Move on 10 months and I have lost my business and am working for a company who is one the brink of closure so work was halted on the cottage until things improved.Both my partner and I decided the outlook was bleak so a move to New Zealand was planned and executed.
Fast forward to May 2010 and my partner wants to move back to Ireland as she misses family etc which in alot of ways suits us both so once back here we find ourselves in a position to continue work on the old house with a view to completing it and living there as the selling part of the equation was never going to happen in the recession.
We were on the home straight in October and me being all organised for once in my life decide to phone the ESB to get an idea of what is involved in getting reconnected.
Two phonecalls later they have reassured me once I get the new electrical work certifed safe and the cert sent to them it would be reconnected for 99euro within 48hrs.Again I am a happy customer..........but not for long.
D day arrives,the house is certified and the cert is sent to the ESB followed by a letter from the ESB to say they will be on site in 48hrs.
That 48hrs came and went so I phoned to see what was the delay only to be told that because the house had been disconnected for over 2 years it would now cost 1,644 euro and would take upto 12 weeks to connect the power because I was now classed as a new connection :mad:
I have spent hours on the phone since asking them how this silly rule can cost me an extra 1,544 euro just because of a date,its still the same house in the same place using the same power poles

I do intend to take this further,I believe the ESB regulator is the person I need to shoot,sorry talk to.
Has anybody else on here ever had the same problem or in general just got "done" by these cowboys?
Sorry for the biography and looking forward to your comments