Hi all,
My windows went in on Wed and stone mason is back to finish off stone above window sill level next week. I'm wondering if anyone has advice as to how to correctly position vertical dpc when stonework is being returned into window.
I got the window supplier to make the windows wider where stonework is being used to allow stone to return to the frame without narrowing the overall window frame width.
There is a gap between edge of window frame and opening at external leaf, I thought the windows would be tight to the blockwork when measured but it didn't turn out that way.
Here are some sketches to explain the 3 options I was looking at. It would be great if I could get opinions as to which is the best option or if anyone has another suggestion other than these 3.
Thanks
Option 1

Option 2

Option 3